With its projected revenue forecast in doubt, an inexplicably high Guaranteed Maximum Price to build, and other local hotels/resorts now facing imminent foreclosure, a forthcoming announcement by the new Rio Nuevo Board that the proposed TCC expansion and hotel deal is dead will be no surprise to anyone who has been watching this saga unravel over the past several months:


In back and forth game, hotel may now be dead
By Joe Pangburn
Inside Tucson Business
October 01, 2010

The downtown convention center hotel could very well be dead in the water and even those who were strongly in favor of the plan can walk away and still save face. The potential knockout punch was dealt through a unanimous vote by the Tucson City Council to send the project back to Rio Nuevo, specifying city staff could not bring the project back to the council until four items are fulfilled. The council wants Rio Nuevo to abide by the establishing legislation, which means the Rio Nuevo Board must first vote on moving forward with the hotel. The other three conditions include:

• A reduced guaranteed maximum price (GMP) for the project and reduced developer and design/build fees.

• A resolution of issues relating to the use of local subcontractors on the project – or hiring more local subcontractors to build the hotel.

• Acquiring additional security – money – from the hotel operator, Sheraton.

“The city taxpayers cannot backstop this entire project,” said Steve Kozachik after the vote. On the surface, it appears to be the latest toss in the back-and-forth game the council and the Rio Nuevo board have played the last few weeks with neither body wanting to cast the first vote on the project. Hotel developer Garfield Traub has said they will work on lowering the GMP and will talk about lowering design/build fees, and that these are reasonable requests.

Those close to the situation say they don’t expect all four conditions to be met. Because of that, the project may never come back to the city for a vote. The ultimatum motion actually gives Mayor Bob Walkup, the city council and Rio Nuevo the political coverage to back away from the project while still being able to claim they made the effort and also protected taxpayers. The $258 million package of the hotel, convention center improvements and parking garage has to be approved and bonds sold before the end of the year or the bond instrument the city planned to use – Build America Bonds – will become more expensive and the total price will go up again.
 
Cuz they know it's a bad idea too :haha:

you need to realize that all government is run by corporations now...Sheraton doesn't have to incur the risk or cost of buidling the hotel (that's on the taxpayers thanks to corrupt politicians) but the DO get to reap the rewards if it's successful. they are a large corporation and deserve to have taxpayers work for them, not the other way around...this is the America we have asked for, folks...socialism at its best (worst)... :tup:
 
Even as the downtown dining scene kicks up a notch this month with the opening of Janos Wilder's Downtown Kitchen + Cocktails, Kwang An says his new sports bar/restaurant may not open until the streetcar construction on Congress is finished in 2012:


AnCongresssite.jpg

The proposed site of An Congress is at East Congress Street and North Fifth
Avenue, but the restaurant's opening has been delayed.
(photo: Dean Knuth)


An Congress opening delayed
Timing for restaurant debut downtown is now uncertain

by Coley Ward
Arizona Daily Star
October 7, 2010

Kwang C. An's new downtown restaurant won't open next month as originally planned. Not even close. An and partner Scott Stiteler say they aren't sure when An Congress, at the southwest corner of North Fifth Avenue and East Congress Street, will open. "I want to make sure the timing of opening up something of that size coincides with other projects moving at a good clip," Stiteler said. Tucson's $182 million modern streetcar, which has been twice delayed, is one of Stiteler's biggest concerns. The streetcar is now scheduled for August 2013 at the earliest. An said his restaurant might not open until 2012. He doesn't want to open until installation of new rail lines on Congress Street has finished. "I want to do it right," he said. The city Transportation Department estimates the rail-line construction on Congress Street will begin in mid-to-late 2011 and last six months. "It's important to me and a lot of downtown businesses that the streetcar go on as scheduled," Stiteler said. Stiteler and An plan to meet sometime in the spring to discuss a new opening date for An Congress. In the meantime, renovation of the building, which is currently boarded up, will continue.

An Congress eagerly Awaited
Other business owners on Congress Street are eager for An Congress to open its doors. Ari Shapiro, who owns Xoom Juice, a smoothie company across the street from An Congress, said he's "going with the flow." "I'd like there to be more density on Congress," he said. "But I'm willing to wait, because I've always approached this with a long-term vision." Shapiro knows An Congress, when it does open, could bring lots of people to the block. An is well known around town for his hokey TV commercials featuring former Arizona Diamondbacks player Luis Gonzalez (who An calls his "No. 1 son"). He owns Great Wall China, near Davis-Monthan Air Force Base, and Mr. An's Teppan Steak and Seafood Sushi Bar, on North Oracle Road. His east-side restaurant Sakura, which he sold in 2008, was a favorite of spring-training baseball players and other local celebs, whose pictures still hang on the restaurant's walls.

Others have plans
While An Congress is on hold, Stiteler will focus on his other downtown properties. Former Time Market general manager Kade Mislinski recently leased the building next to An Congress, which is also owned by Stiteler. Mislinski said he plans to open a restaurant that will serve pastrami sandwiches and beer. "We're going to be pickling, curing and smoking all our own meats," he said. Across the street, Xoom Juice's Shapiro is planning a coffee bar called Sparkroot in a retail space also owned by Stiteler. Meanwhile, a traveling exhibit of artifacts from the Titanic will come to the Rialto Block, 300 E. Congress St., later this month. Stiteler and developer Don Martin own that property.
 
Last edited:
:yuck: Is this the sick joke sheraton plays making cities pay for their hotel


FYI: Sheraton would not have any ownership interest in the convention center hotel, and only be the hotel operator, receiving a certain portion of revenues as such. Additionally, Sheraton's parent company, Starwood Hotels, owns less than a quarter of the hotels they operate worldwide under various brands (including Westin, W, etc.), with the majority owned by franchisees.

Sheraton was selected as the operator as they were part of the winning RFP submitted by developer Garfield Traub over three years ago. The city's proposal to make Sheraton put up additional security money as the hotel's operator without any ownership interest in the property is a long shot at best, and will not likely succeed.
 
FYI: Sheraton would not have any ownership interest in the convention center hotel, and only be the hotel operator, receiving a certain portion of revenues as such. Additionally, Sheraton's parent company, Starwood Hotels, owns less than a quarter of the hotels they operate worldwide under various brands (including Westin, W, etc.), with the majority owned by franchisees.

Sheraton was selected as the operator as they were part of the winning RFP submitted by developer Garfield Traub over three years ago. The city's proposal to make Sheraton put up additional security money as the hotel's operator without any ownership interest in the property is a long shot at best, and will not likely succeed.

wow.........:omg: so the city of tucson pretty much would own the hotel
 
:yuck: Is this the sick joke sheraton plays making cities pay for their hotel

whoa, can we tone down the font size there a bit???? it's not a sick joke...it's how business is done in America these days...get the guy who won't even use it (ie, joe average tax payer) to foot the bill, throw a bone to the politicians who arranged for it to happen, and then the corporation reaps the rewards. welcome to business as usual in the good ol' usa...

okay, so yeah it is a sick joke...and the joke is on us!
 
Without addressing the city's latest four requirements for the TCC hotel deal, the Rio Nuevo Board has sent the council a notice to proceed, provided the city addresses 13 of their own concerns. (Councilman Kozachik says the city shouldn't even bother with this latest request....can this process get any more convoluted?):


Rio Nuevo sends letter to proceed
Gives city 13 stipulations

By Joe Pangburn
Inside Tucson Business
October 08, 2010

The hot potato game that is the plan for a downtown convention center hotel keeps getting tossed around. The Rio Nuevo Multipurpose Facilities District board voted 8-2 Oct. 7 to send a notice to proceed to the City of Tucson on the hotel project with 13 hard and soft concerns the board wants to see happen. This follows the four requirements the council put on the project when it sent it back to Rio Nuevo late last month.

Major issues for the district board include:

- A ground lease on the property--which the district owns and calculates is worth $438,000 annually--will be free to the city for five years but will reset to market rate after that.

- District participation will be 100 percent of the hotel site-generated TIF money for the first 10 years and then reduced by 5 percent annually with a floor of 50 percent.

- Design plans will be purchased by the city for $10 million.

- Income will be distributed 50/50 between the city and the district.

- The district will have representation at the table at negotiations for all project contracts.

- Any reduction in the GMP shall be used for a face-lift to the TCC.

The notice to proceed from the district is only good for 90 days. The motion was made by Dan Cavanaugh, but multiple friendly amendments to the motion made it as large as it is. "Somebody is going to have to make a bet on this town to succeed," Cavanaugh said. "I believe it will and I believe this is a good bet on the future of this city." The board voted 8-2 to proceed with the letter even though at least four said the numbers for the project "penciled out funny." "If this district had the resources to backstop this hotel itself, I still could not support this hotel in this form," said Board Member Rick Grinnell who voted against the letter. "The numbers just don't work. And I cannot agree to send this letter to proceed knowing I also have a responsibility to the taxpayers of Tucson and I can't vote for something that will hurt them."

City Councilman Steve Kozachik said the letter should not even be delivered to the city of Tucson as the board failed to address any of the concerns the council set forth in its Sept. 28 meeting. "Not only has the District Board failed to respond to any of the items contained in the Mayor and Council motion, they have instead sent back to the City a hotel proposal that increases the contribution of the taxpayers, while at the same time ensuring the District will reap both immediate rewards in the form of a $10 million charge to the City for the construction drawings as well as long-term financial rewards in both lease payments and in any potential revenues generated by the proposed hotel," Kozachik wrote in an open letter responding to the district's letter. "And now the whole project threatens to encumber the City with a risk so great that financially it is a 'poison pill.'"

He said the discussion of the hotel project should now end and the focus should turn to successfully negotiating an Intergovernmental Agreement that outlines the rights and responsibilities of each party. The council will meet Tuesday (Oct. 12) but have not outlined if they will spend time on the letter.
 
While 20 low-end apartment complexes have recently fallen into foreclosure, developers are moving ahead with nearly 1,000 high-end units in four separate projects:


LegacyAptsatDoveMountain.jpg

Due to a shortage of high-end apartments and despite the economy's current
instability, the 168-unit Legacy Apartments at Dove Mountain is under construction.
(render: Robinette Architects)


Optimistic, contrarian developers plan four new apartment complexes
By Roger Yohem
Inside Tucson Business
October 08, 2010

Due to some optimistic and contrarian developers who won’t let “the Great Recession” hold them back, four new apartment projects totaling 937 units are scheduled to open in late 2011. Already under construction is Legacy Apartments at Dove Mountain, 12100 N. Mountain Centre Road, a $14 million, Class A luxury complex in Marana. The 168-unit project is environmentally friendly on an 8.65-acre site just east of the intersection of Dove Mountain Boulevard and Tangerine Road. The other three projects are expected to break ground before the end of this year. They are The Place at Creekside, a 352-unit complex at 9971 E. Speedway; Riverside Crossing, a 301-unit complex at West River Road and North LaCholla Boulevard; and The Place at Canyon Ridge, a 116-unit project at 2656 W. Broadway Blvd.

At first glance, construction of these apartments seems to be a high-risk venture, contrary to the financial hardships caused by the down economy. Plus there are about 20 existing, local apartment complexes that have fallen into foreclosure in the last 18 months. “Actually, there is a lot of rationale to this. First, upper-end apartments do very well but a lot of the higher-quality buildings have been converted to condos. That took a lot of them off the rental market,” said Mike Chapman, apartment expert and first vice president of CB Richard Ellis. “Most of the vacancies and financial stress have been in the lower end.”

The shortage of quality units was compounded by a shortage of available, quality sites. Residential home builders grabbed some of the best locations, thwarting apartment growth that often numbered 4,000 new units a year, Chapman explained. Since 2005, only 1,500 units have been built. “There’s been an apartment shortage for quite some time. It’s now impossible to overbuild them like what happened in the 1980s and 90s,” he said. Another factor is the drop in construction-related costs since the frenzied peak of the housing boom. Because it costs less to build now, it is possible to save significant dollars in avoided costs.

Chapman pointed out that the apartments “will be available in the winter season, a traditionally strong rental period. And they are hoping the market and economy will be in better shape by then.” The Legacy Apartments at Dove Mountain consists of 12, two-story buildings and a clubhouse, recreation center, pool and spa, business center and putting green. It was designed by Robinette Architects, 1670 E. River Road. T.L. Roof & Associates, 710 S. Campbell Ave., is the general contractor. Public records list the owner as Legacy Apartments at Dove Mountain LLC, based in Seattle. The construction value is about $12.5 million. The land was purchased in mid-September for $1.4 million from Rita Land Corp LLC, an affiliate company of Tucson developer David Mehl’s Cottonwood Properties.

“Our design has a very strong showing of native landscaping and low water use, what I call a Southwest Contemporary blend into the desert,” said Ron Robinette, president. “There will be a big open belt on the east and north. For renters on the perimeter, they will have pretty fantastic views of the Tortolitas and toward Pusch Ridge and the Catalina Mountains. We kept it rural, other than a little pizzazz at the entry going in.” Local contractors include DC Concrete, Schuck & Sons Construction, the Grounds-keeper and Dar-Hill Corporation. Both The Place at Creekside and The Place at Canyon Ridge are being developed by MC Companies, with corporate offices in Tucson and Scottsdale. Riverside Crossing is a project of Tucson developer Humberto Lopez’s HSL Properties.
 
Last edited:
ADS says The Gadsden Co. is getting a sweetheart deal from the city to develop their first project in the Mission District, a vacant 14-acre parcel on Congress St. west of I-10:


MissionDistrictlow-incomehousingrender.jpg

A 143-unit low-income housing project is scheduled to begin construction in mid-2011.
(render: Lizard Rock Designs)


City pushes big flip for struggling builder
by Josh Brodesky
Arizona Daily Star
October 10, 2010

After all that's gone wrong with downtown development, you'd think the city would know better by now. Tucson is broke. But that's not stopping it from selling off a prime piece of downtown real estate to the struggling Gadsden Co. for $250,000. The day that sale goes through, Gadsden will flip the property for $1.43 million to Chicago-based Senior Housing Group LLC, which plans to build a six-story, 143-unit affordable housing project.

Gadsden says the big flip doesn't mean big profits - but that depends on perspective. The deal, which all sides are pushing to close by Dec. 1, calls for $500,000 to be placed in an escrow account, which the city and Senior Housing Group will use to pay for things like sidewalks and sewer lines. But Gadsden was supposed to pay for those kinds of improvements in the first place - its exclusive development agreement for the site requires it. Now Gadsden's going to use someone else's dough to meet those obligations. As for the rest of the money Gadsden will land from the sale? That's Gadsden's. "There is nothing creative about this," said Adam Weinstein, a Gadsden partner. "There is nothing cute about it." Actually, there is plenty of creativity here. The deal is the perfect fit for a struggling developer, a city desperate for something real to be built downtown and another developer with federal tax credits to burn. More on that later, but first, a quick bit of history:

Back in 2008 Gadsden signed a deal with the city to develop 14 acres on the west end of downtown, just west of the Santa Cruz River and south of Congress. The site has been a dust bowl for years, but Gadsden has big plans for it: roughly 400 housing units, shops, office space, and a "boutique" hotel, along the planned streetcar route. The city offered the property to Gadsden at a bargain rate - but split it into four phases. In order to claim the property's second phase, Gadsden had to complete certain goals for phase one. The original deadline was supposed to be March 2009, but Gadsden has yet to deliver, and earlier this year the city extended the date to March 2011. "So far, I've seen very little progress in that regard from Gadsden - virtually nothing," city attorney Damian Fellows wrote in a recent e-mail to staff. "Instead what I see is an urgency created by Gadsden to gain staff's assistance to effectuate its goal to profit off of land speculation. "Gadsden's overriding objective, it appears to me, is to flip this property while ignoring its obligations under the existing Development Agreement."

Why the urgency? Enter Senior Housing Group and its president Steve Greenbaum, who has a deadline to spend 10 percent of his project's overall costs in order to claim his federal tax credit. That deadline was Dec. 1, but has since been pushed to June 30. Greenbaum approached Gadsden about buying some of the city land for his tax-credit financed project. It seemed a good fit. The Gadsden development calls for affordable housing, and Greenbaum liked the overall plan and close amenities. But the property Greenbaum and Gadsden agreed to is designated for the third phase - and Gadsden still hasn't met its obligations for phase one. The cure? Turn phase three into phase one. Then give Gadsden credit for the roughly $26 million Greenbaum is spending on construction. "In our development agreement, you'll see some milestones, performance milestones we have to do," said Jerry Dixon, a Gadsden partner. "We have to do $10 million in phase one before we can take down phase two. Well, here we will do $25 million in phase one, which we think gives us the right to take down phase two and phase three."

City officials either don't see anything wrong with the Gadsden flip, or won't admit they see anything wrong with it. In an interview, Fellows, the city attorney, backed away from his earlier critical e-mails. The deal is sound, he said. Some of his criticism was based on a misunderstanding about what parcels were being flipped. Meanwhile Councilwoman Regina Romero and City Manager Mike Letcher called it a "win" for the community. Gadsden, they said, has hung tough through the recession while making a huge investment in this project and the neighboring Mercado San Augustin. "We have a developer who is really struggling," Romero said. "These developers, hate 'em or love 'em, this particular group is really looking out for the needs of the community, really trying to do the right thing."

Everyone involved insisted the city can't just cut Gadsden out, even though the city still owns the property, because Gadsden has a development agreement. Never mind that Gadsden hasn't fulfilled its obligations and would be in default if the city hadn't extended the deadline to give Gadsden time to finish the deal with Greenbaum. Jessie Sanders, Rio Nuevo project coordinator, said the city hasn't held up its end of the deal, either, noting it never delivered on any of the promised west side Rio Nuevo projects, which could put the city in a legal bind. "When you look at the development agreement, both sides have not performed up to the level, and if somebody wanted to, you know, this could get really ugly," Sanders said. "This is what I've told all sides: Our job is to find success in a way that passes the sniff test for whoever wants to be negative." Well, with that said, take a deep whiff and decide for yourself.
 
Last edited:
ADS says The Gadsden Co. is getting a sweetheart deal from the city to develop their first project in the Mission District, a vacant 14-acre parcel on Congress St. west of I-10:

True, and although I agree the city gives these deals to developers that end up not building anything, in this case Gadsden is one of the few that have actually built something. Also, the city has failed on the promises, like the article states, on all the heritage parks, the UA Science center, etc.
 
AZ Dept. of Transportation to finish widening on I-10
Posted: Oct 11, 2010 3:22 PM
Updated: Oct 11, 2010 7:16 PM


TUCSON- Just when you thought construction on Interstate Ten through Tucson was finished, think again.

The Arizona Department of Transportation will continue the widening project that will last two years, beginning this winter.

It took two and a half years for A-DOT to widen the freeway south of Prince Road to 29th St.

Now A-DOT will finish what they started north of Prince Road between Ruthrauff.

A-DOT's Todd Emery says construction is to start sometime in February or March, "Imagine its going to be a challenge to build this."

One side of 1-10 will be shut down for one year and then reversed the next, with the goal of relieving congestion, "The plan is to try to beat that, to plan ahead to address those need now."

Emery says the primary concern is safety at the Prince and I-10 rail road crossing, where there have been a number of accidents, "We're going to take that and move Prince up and I-10 down so that when the project is done, Prince will go over I-10 and it will also go over the railroad."

Once construction is complete, the Prince Road crossing is going to look similar to the Miracle Mile crossing, "And this is going to make that area much safer than what it is now."

The west side of the 2 mile stretch along 1-10 will be shut down first.

A-DOT says the first year of construction will be the toughest because the Prince Road area will be shut down entirely.

The price tag for this project is $115 million dollars.