With its projected revenue forecast in doubt, an inexplicably high Guaranteed Maximum Price to build, and other local hotels/resorts now facing imminent foreclosure, a forthcoming announcement by the new Rio Nuevo Board that the proposed TCC expansion and hotel deal is dead will be no surprise to anyone who has been watching this saga unravel over the past several months:
In back and forth game, hotel may now be dead
By Joe Pangburn
Inside Tucson Business
October 01, 2010
The downtown convention center hotel could very well be dead in the water and even those who were strongly in favor of the plan can walk away and still save face. The potential knockout punch was dealt through a unanimous vote by the Tucson City Council to send the project back to Rio Nuevo, specifying city staff could not bring the project back to the council until four items are fulfilled. The council wants Rio Nuevo to abide by the establishing legislation, which means the Rio Nuevo Board must first vote on moving forward with the hotel. The other three conditions include:
• A reduced guaranteed maximum price (GMP) for the project and reduced developer and design/build fees.
• A resolution of issues relating to the use of local subcontractors on the project – or hiring more local subcontractors to build the hotel.
• Acquiring additional security – money – from the hotel operator, Sheraton.
“The city taxpayers cannot backstop this entire project,” said Steve Kozachik after the vote. On the surface, it appears to be the latest toss in the back-and-forth game the council and the Rio Nuevo board have played the last few weeks with neither body wanting to cast the first vote on the project. Hotel developer Garfield Traub has said they will work on lowering the GMP and will talk about lowering design/build fees, and that these are reasonable requests.
Those close to the situation say they don’t expect all four conditions to be met. Because of that, the project may never come back to the city for a vote. The ultimatum motion actually gives Mayor Bob Walkup, the city council and Rio Nuevo the political coverage to back away from the project while still being able to claim they made the effort and also protected taxpayers. The $258 million package of the hotel, convention center improvements and parking garage has to be approved and bonds sold before the end of the year or the bond instrument the city planned to use – Build America Bonds – will become more expensive and the total price will go up again.
In back and forth game, hotel may now be dead
By Joe Pangburn
Inside Tucson Business
October 01, 2010
The downtown convention center hotel could very well be dead in the water and even those who were strongly in favor of the plan can walk away and still save face. The potential knockout punch was dealt through a unanimous vote by the Tucson City Council to send the project back to Rio Nuevo, specifying city staff could not bring the project back to the council until four items are fulfilled. The council wants Rio Nuevo to abide by the establishing legislation, which means the Rio Nuevo Board must first vote on moving forward with the hotel. The other three conditions include:
• A reduced guaranteed maximum price (GMP) for the project and reduced developer and design/build fees.
• A resolution of issues relating to the use of local subcontractors on the project – or hiring more local subcontractors to build the hotel.
• Acquiring additional security – money – from the hotel operator, Sheraton.
“The city taxpayers cannot backstop this entire project,” said Steve Kozachik after the vote. On the surface, it appears to be the latest toss in the back-and-forth game the council and the Rio Nuevo board have played the last few weeks with neither body wanting to cast the first vote on the project. Hotel developer Garfield Traub has said they will work on lowering the GMP and will talk about lowering design/build fees, and that these are reasonable requests.
Those close to the situation say they don’t expect all four conditions to be met. Because of that, the project may never come back to the city for a vote. The ultimatum motion actually gives Mayor Bob Walkup, the city council and Rio Nuevo the political coverage to back away from the project while still being able to claim they made the effort and also protected taxpayers. The $258 million package of the hotel, convention center improvements and parking garage has to be approved and bonds sold before the end of the year or the bond instrument the city planned to use – Build America Bonds – will become more expensive and the total price will go up again.