Tucson Development Thread


The new streetcar was a factor in the announcement of a new 10-story tower for the Marriott University Park, reportedly the most successful hotel in Tucson:


MarriottUniversityParktower.jpg

All of the ground-floor retail space has been pre-leased for
the Marriott expansion.
(render: J.L. Investments)


Marriott University Park to add retail, multi-screen theater, up to 132 suites
$35 million building

By Roger Yohem
Inside Tucson Business
March 27, 2010

Despite the economy, the commercial and retail area west of the University of Arizona’s Main Gate is burgeoning and the Marshall Foundation is moving ahead with plans to develop property it owns to add another 132 suites to the Marriott University Park in a complex that will also house a six- to eight-screen movie theater and new retail space. The parcel to be developed is a parking lot immediately east of the existing 250-room, nine-story hotel on the south side Second Street. Officials with the Marshall Foundation say the $35 million venture is economically sound, even in an uncertain economy, because the foundation adheres to the golden rule of real estate: location, location, location. “Obviously, this Marriott is a very successful hotel with great occupancy because of its location next to the university, doing business with the university, and hosting business conferences,” said Jane McCollum, general manager of foundation. “And its location near the modern street car route is another reason for expansion.” J.L. Investments will develop the property with co-owner Tom Warne as the project manager.

Warne said the project is down to a few plan amendments and zoning approvals that are still needed from the City of Tucson. Once those are in place, the final design and construction drawings will be done, financing options explored, and a construction timeline set. He said the new building will be nine or 10 stories high with up to 132 hotel suites, mixed-use retail space on the ground floor, and the theater on the second floor. “We already have leased all the retail. We needed those leases to move forward,” said the Marshall Foundation’s McCollum, although she would not identify the tenants. “We’ve always planned to build a movie theater, that concept has been on the books for about 10 years,” she said. “It will enhance the media arts program at the university, as we are dedicating two screens to the university during the week.” The theater also will create opportunities for hosting film festivals and private screenings.

The existing Marriott hotel has 233 rooms and 17 suites, with just under 12,000 square feet of meeting space. Opened in 1996, it also has a restaurant and fitness center. Mark Van Buren, general manager of the hotel, called the planned expansion a “home run.” “We have such a great location. For many reasons, we already are the most successful hotel in the greater Tucson area,” Van Buren said. “Many of our guests are what we call business transients. They do business with the university, do training and are gone. People don’t realize there is a lot more business activity going on here than in other parts of town.” McCollum believes the larger Marriott University Park and the city’s planned downtown convention hotel will complement each other. The streetcar’s “university-downtown connectivity” will be an economic booster. For example, she said, Marriott guests will be able to ride the streetcar to events downtown. Likewise, downtown hotel guests can easily get to merchants, restaurants and entertainment on Fourth Avenue and University Main Gate areas. “That kind of traffic is great for economic development without the infrastructure issues. They spend their money and leave,” she said.

Both McCollum and Warne praised the “cooperation and unanimous support” the development has received from the West University Neighborhood Association and the city council. She said both groups see the social and economic benefits. In the past two years, Warne said he has appeared before Mayor and Council nine times. He said every meeting “was extremely positive and constructive. They know this project will generate a lot of retail sales taxes and bed taxes.”
 
Although another $1M or more is needed to complete the replica of the historic Mission Gardens at the proposed Tucson Origins Heritage Park, a local contractor and blacksmith have donated time and materials to install new mesquite-plank gates and ocotillo fencing to secure the entrances in the adobe perimeter wall built last year:


MissionGardensgate.jpg
MissionGardensocotillogate.jpg

(photos: city of Tucson)


http://dot.tucsonaz.gov/projects/project.cfm?cip=663A9BB2-E468-E114-9D339C76A737EF96
 
Last edited:
SanXavierMissiontowers.jpg

The upper reaches of the east bell tower of Mission San Xavier del
Bac shows its age next to the restored west tower.
(photo: Kelly Presnell)


Tough economic times clip White Dove's wings
Historic San Xavier Mission lacks funds to complete repairs

by Doug Kreut
Arizona Daily Star
March 28, 2010

A prominent feature of Mission San Xavier del Bac - which has graced the desert southwest of Tucson for two centuries - faces unchecked decay now that critical funding has been cut. Work to repair and restore the mission's deteriorated east bell tower was supposed to be under way this spring, but not a dab of new mortar has been applied. A previously approved $150,000 grant from the Arizona Heritage Fund to kick-start the project was abruptly canceled last year. Persistent efforts to get the funding restored have failed, so the bell tower will languish for the foreseeable future - making eventual restoration ever more costly, said Vern Lamplot, executive director of the Patronato San Xavier. The group oversees fundraising and restoration for the mission, which attracts 200,000 visitors annually.

Restoration of the tower was to be the last major step in more than two decades of work that has included repair of walls, renovation of the west tower and meticulous cleaning of religious art inside the mission. Lamplot said the Heritage grant - opening access to matching grants - would have been sufficient to launch the $1.5 million tower project. With those funding arrangements on indefinite hold, the Patronato has turned to a smaller project - restoration of an arcade outside the mission's sacristy. Work there began this year and is scheduled for completion by May 2011. Lamplot said the Patronato has raised much of the $300,000 needed for the arcade work. Because the project is smaller and more manageable, Lamplot said, "If we had to stop it suddenly, it wouldn't be too big a problem. "The tower project is very different" because the tower's interior will be exposed while the work proceeds, Lamplot said. "We wanted to have reliable grant funding before starting so it will be open to the elements for the shortest possible time," he said.

THE TOWER'S FUTURE

The east bell tower of the mission has always been an eye-catcher - mainly because it has remained unfinished since Tohono O'odham workers, under the direction of Spanish Franciscans, stopped work on the building in 1797. The tower's missing top might be quirky, but it's not the problem. The problem is that the tower - which is to be left in its incomplete state for historical purposes - is showing serious deterioration inside and out. Restorers want to stabilize it, remove a damaging cement plaster that traps moisture, and replace it with a "breathable" lime mortar. Similar work was completed on the west tower in 2008. "That east tower is seriously in need of work right now," said Bernard "Bunny" Fontana, a writer, historian, educator and one of the founders of the Patronato San Xavier. "If you look at that tower, you can see stuff falling off of it," Fontana said. "It could eventually get to the point where it's dangerous and we need to take some emergency measures."

There is a glimmer of hope. Lamplot, who has tried repeatedly to get the Heritage funds reinstated, said state officials "told us that we wouldn't have to apply again. They said that when the funds were restored, we would be informed." So far, silence. "We're waiting for the economy to improve in hopes of getting the funding," Lamplot said. "But it's hard to tell when that might happen." Fontana, known for a wry sense of humor, noted that the stalled tower-restoration effort might actually amount to a sort of "historical continuity." "It's almost certain," he said, "that the reason the tower was never finished in the first place is that they ran out of money" back in 1797.

WORK IN PROGRESS

While the bell tower weathers in the desert sun, a restoration crew is tackling the painstaking job of stabilizing and restoring the sacristy arcade. "The arcade was added to the east side of the church in the early 1800s - no one is sure of exactly when," said Bob Vint, architect for restoration work at the mission, often called the White Dove of the Desert. "It's made of unfired mud adobe and is in a deteriorated condition." A crew from Morales Restoration & Builders, with a long history of work at the mission, is removing a layer of cement plaster, stabilizing joints and supports, and then making repairs with mud adobe and lime mortar.

Removing the cement plaster and replacing it with adobe and lime mortar materials like those used by the original builders is part of an effort to rid the entire mission of cement plaster. The impermeable cement - applied during earlier renovations in an ill-conceived effort to shore up the building - actually did more harm than good by trapping water that gradually caused structural damage. The work on the arcade is aimed not only at restoring the structure but also increasing resistance to potential earthquake damage. "We excavate every single joint and make sure they're stable," said Daniel Morales, who directs the crew's work. "It's quite involved. You can't just come in and replaster. You can fix the top all you want, but that won't be good if you don't stabilize the bottom first."

Virtually all the work, including removal of the cement plaster and applying the lime mortar, must be done by hand, as gently as possible. "We're trying to keep the vibration to a minimum to protect the bricks behind the plaster," Morales said. Meanwhile, the Patronato is continuing to raise money from donors and fundraising events to ensure completion of the arcade work and some smaller projects. "That's money we have to find each year, but it's worth it," Lamplot said. "San Xavier is unique. It's regarded as the best example of Spanish Baroque architecture in the United States."


SUPPORT THE MISSION
The Patronato San Xavier is holding a fundraising concert April 18 at the mission, 1950 W. San Xavier Road.
The concert, featuring flamenco music, begins at 5 p.m. Admission is $75.
Call 407-6130 for reservations. Proceeds will support continued restoration work.
 
Along with the new Depot Plaza underground garage opening in September, this city-owned parking garage at Plaza Centro will provide needed parking for 4th Ave. and Congress St. businesses:


PlazaCentrogaragerender.jpg

(render: Downtown Tucsonan)


New multi-use parking garage set for E. Congress
by Teya Vitu
Downtown Tucsonan
March 30, 2010

Construction can start on a 378-space Plaza Centro Garage once $5.6 million in certificates of participation are sold to fund the project. The City Council in February approved an amendment to the Plaza Centro development agreement that included a go-ahead on building the garage, said Chris Leighton, parking coordinator of the city’s ParkWise division. Leighton estimates breaking ground possibly in August for the four-level, above-ground garage at 345 E. Congress. It will be wedged between Congress, the railroad tracks and the new Fourth Avenue underpass, which already has an elevator in place to link the underpass sidewalk with the garage level. “The garage’s location starts solving the Fourth Avenue parking problems,” Leighton said.

The garage could be done as soon as summer 2011, Leighton said. It will serve the east end of Downtown, including Hotel Congress, the Rialto Theatre and, principally, the proposed Plaza Centro housing and retail project, the brainchild of developer Jim Campbell, who also suggested the alignment for the Fourth Avenue underpass. “I’m not quite ready to figure out exactly the direction I want to go with (Plaza Centro),” Campbell said. “I still have a bunch of balls in the air with it.”
 
The $11M first phase of the Grant Rd. widening/improvement project will stretch from 15th Ave. to Castro Ave. (including the Oracle Rd. intersection), and is scheduled to begin construction in summer, 2011:


GrantandOracleRdsintersectionrender.png

rendering of Grant/Oracle intersection
(render: RTA)


See Grant Rd. plan at Wednesday open house
by Dylan Smith
TucsonSentinel.com
March 19, 2010

Check out the planned improvements to Grant Road at an open house Wednesday evening. The Regional Transportation Authority will hold an information session at the Tucson Association of Realtors, 2445 North Tucson Boulevard, from 5:30 - 8 p.m. The first phase of upgrades to the roadway are planned to break ground in summer 2011, beginning with the West Grant and North Oracle Road area.


Where & when:
* Grant Road Improvement Plan Open House
* 2445 N. Tucson Blvd.
* Wednesday, March 24, 5:30 - 8 p.m.

www.rtamobility.co
http://www.grantroad.info/
 
The new streetcar was a factor in the announcement of a new 10-story tower for the Marriott University Park, reportedly the most successful hotel in Tucson:


MarriottUniversityParktower.jpg

All of the ground-floor retail space has been pre-leased for
the Marriott expansion.
(render: J.L. Investments)


Marriott University Park to add retail, multi-screen theater, up to 132 suites
$35 million building

Seems like a great place for students to hang out, especially the mobile-limited freshman...wish UA had that when I was there...
 
Nice series of updates for Tucson. Thanks, Kaneui. :)

Even in the midst of the depressed economy, with the modern streetcar green-lighted, the new UniSource HQ going up, the ongoing facade restoration program, and the expected convention center expansion and headquarters hotel, Tucson is adding some significant new development in the downtown area.

Along with the new mixed-use tower at the Marriott University Park, we should see more TOD announcements over the next several months for additional projects along the streetcar route.
 
Ya Im hoping the streetcar helps clean up some deteriorating streets and streetscapes as well as spruce up the 4th Avenue roughness. UA, downtown and everything in between should be fun to watch transform from now on
 
Of the 37 downtown properties acquired by ADOT under the original plan to complete the Barraza-Aviation Parkway, 11 have been sold thus far and ten more are headed for the auction block on Monday:


Lots of warehouses on block at April 6 ADOT auction
by Teya Vitu
Downtown Tucsonan
April 01, 2010

Ten state-owned warehouses and sundry other properties along the Aviation Corridor will go on the auction block April 6, the most warehouses the Arizona Department of Transportation has offloaded at one time in the Warehouse District. City easements on several warehouses expired and finalizing an alignment for the Downtown Links northward extension of the Barraza-Aviation Parkway led ADOT to auction off so many properties at one time, ADOT spokeswoman Teresa Welborn said. The auctions start at 11 a.m. April 6 at the ADOT District Office, 1221 S. Second Ave. The combined minimum bids for the properties is $4 million, but if recent ADOT warehouse auctions are any indication, the sale totals will be much higher.

ADOT acquired 37 properties, mostly warehouses, from 1987 to 1991 to clear them away to build a state highway to link Barraza-Aviation Parkway to Interstate 10. In the intervening years, the city took over the road project and realigned the route.
So far ADOT has sold 11 properties, but the state has collaborated with the city and tenant artists for years to find ways to disperse the warehouses to support the arts district that has evolved in them over the decades. “The people have been able to lease below market rates for a long time,” Welborn said. “It was an incubator site we were able to provide.”

Downtown Warehouse District properties up for auction include:

• 35 E. Toole Ave., 17,358 square feet with a 15,445 square-foot warehouse. Minimum bid: $380,000.

• Toole Avenue parking lot between Sixth and Seventh avenues, 46,569 square feet. Minimum bid: $652,000.

• 119 E. Toole Ave., 23,385-square-foot building, 18,375-square-foot lot. Minimum bid: $360,000. • 102-106 E. Council St., 4,627-square-foot building, 950-square-foot lot. Minimum bid: $287,000.

• 174 E. Toole Ave., 2,750-square-foot building, 2,960-square-foot lot. Minimum bid: $207,000.

• 406 N. Church Ave, 8,511-square-foot building, 31,228-square-foot lot, and Perry Avenue at Sixth Street, 16,273-square-foot lot. Minimum bid: $1.394 million.

• 534, 536, 538 N. Stone Ave., 12,771-square-foot building, 12,381-square-foot lot. Minimum bid: $561,000.


For more info.:
http://www.azdot.gov/highways/row/propmgmt/PDF/April_6_2010_Auction.pdf
 
An interview with a Garfield Traub exec has no new revelations, but confirms the fact that convention center hotels no longer get built without some public sector financing:


Some questions - and answers - about the TCC hotel
by Teya Vitu
Downtown Tucsonan
April 02, 2010

Garfield Traub Development and Starwood Hotels (Sheraton) were selected from a field of four development teams in November 2007 to build a 707-room convention center headquarters hotel to support a Tucson Convenion Center expansion and spur major conventions and conferences to commit to Downtown. Two-plus years later, financing still needs to be rounded up for the $200 million project and the proposed hotel was reduced to 525 rooms. The Downtown Tucsonan recently talked about where things stand with the hotel with Steve Moffett, president of Garfield Traub’s hospitality division.

Q: More than two years have passed since Garfield Traub was picked to build a TCC hotel but a hotel is still not under construction. Why not?

Moffett: We were selected two years ago but we did not sign our development agreement until May of last year (2009). Since we have signed our development agreement, we’ve been working diligently. It takes about one year for architects to draw a building to get it ready for construction. We’re under that year time frame. We’re right on schedule. When we were selected we had positioned the hotel a little further north of of where it currently is. About the same time we were selected, the city was undergoing an urban renewel plan with a company called EDAW. EDAW suggested McCormick Street cut through from Church all the way through to Granada. The problem was where McCormick met Granada, that’s where we had the hotel. So the city said to us “we need to have you consider another site.” It took us several months to work with the city to get that site.

Q: What still needs to happen before hotel construction starts?

Moffett: The next thing we need to do is our contractor needs to get bids from about 160 contracts going out to bid. We need to get a guaranteed maximum price for the hotel in order to complete the capital plan that gets to presented (to the Rio Nuevo Board and City Council).

Q: When is hotel construction expected to start?

Moffett: Our schedule is we’d like to start construction in August of this year, finishing up in fall of 2012.

Q: What is the status of the new TCC main entrance on the east side and what role will it play?

Moffett: We had to move our hotel to a new spot because of a McCormick Street extension. The problem we were faced with is our ballroom sits exactly where the current entrance is on the west side of the convention center. The first thing we need to do is tear down that main entrance. So you need to create a new entrance. So we had to start construction on a new entrance on the east side. We are redoing that entire parking lot (on the TCC’s east side). You’ll see (the new main entrance) starting to close in and we’ll start working on the inside (in April). That construction will be done in May.

Q: This hotel was originally proposed at 707 rooms. Why was it reduced to 525 rooms?

Moffett: Short term (the city) said don’t consider the arena. Only consider the first expansion of the convention center and tell us how big the hotel needs to be. The city told us not to consider those plans (for several convention center expansions and a new arena). We’re taking the convention center and we’re adding 33,000 square feet of exhibition space immediately west of the existing exhibit hall and on top of that we’re building 22,000 more square feet of meeting space. We were told what would it take to support just that one expansion of the convention center. Starwood said we would need between 500 and 550 rooms.

Q: Whatever happened to the proposed new arena?

Moffett: That’s a city question. When we had the original contract (to build the arena), the former city manager said that wasn’t progressing as fast as he wanted and he wanted to go a different direction. What I do know is the state Legislature told the Rio Nuevo district you can only concentrate (Rio Nuevo spending) on a hotel and arena, but do the hotel first.

Q: How will the hotel be financed?

Moffett: The hotel will be publicly owned with tax-exempt bonds to finance the hotel.

Q: Are the revenue estimates reasonable and how are they determined?

Moffett: We have three sets of projections. Starwood did an income projection based upon the full year of 2008 performance of the market in Tucson and they looked at other convention hotels and the number of rooms we have. They updated that in the fall 2009 and they updated it again in early 2010. The 2010 projection actually considered the whole year of 2009, which was a reduced projection because 2009 was a bad year in the industry. Because these are tax-exempt bonds, the district has to have a third party, independent of our team, come in and project the income. (Rio Nuevo) hired a company called HVS. In my opinion, the revenue estimates from HVS are conservative and the estimates from Starwood are very reasonable.

Q: How will the debt service be handled?

Moffett: The debt service from the bond will be paid first from revenue from the hotel, second from the city hotel occupancy tax (6 percent) from this hotel that will pledged to pay debt service. Then you’ve got 2 percent of the city sales tax from the hotel will be pledged to debt service and there is a 2 percent surcharge on guests of only this hotel, and there are debt service reserves of roughly $15 million.

Q: Under what scenario would the city’s general fund be tapped to pay down debt?

Moffett: I don’t think there is a scenario where the general fund would be used. There would have to be a certain (very low) occupancy for several years before you burn through some of the funds available. In my opinion, you have too many entities marketing this hotel to ensure the success to ever allow that to happen. One of the groups that will be marketing this property is a group Starwood has called the Convention Collection. That’s a group right now of 32 convention center headquarter hotels that are all over 500 rooms. In 2009, the average occupancy, and remember 2009 was one of the worst years in the history of the hotel industry, was 67.2 percent. 69 percent is not far fetched at all (for Tucson to come out ahead).

Q: Why is this project important for economic development in Tucson?

Moffett: Tucson has a convention center and Tucson is not in the convention business. Why is Tucson not in the convention business? Because you don’t have a headquarters hotel. Every time a person attends a convention and stays overnight in any city in the U.S., they spend an average of $300 to $350 a day, more than 10 times what is spent by people who don’t spend the night. Those conventions don’t just fill this hotel. We’re only going to be able to give a room block of about 400. You’re going to have conventions that are going to need 1,000 rooms, 1,500 rooms. All of the conventions need more rooms. Those are going to become citywide events.

Q: If this hotel is needed, why isn’t the private sector doing it?

Moffett: Convention center headquarters hotels cost on average $300,000 a room to build. In order to support that with private funding, that hotel would have to charge an average of $300 every night throughout the year. In Tucson that can’t happen. We will get an average daily rate of $163. Twenty years ago if you were trying to build a hotel, a bank would lend you 80 to 90 percent of the value of your hotel. Today I can at best get 50 percent of my cost from a traditional lender. It has to have public assistance in some sort of fashion. Full service convention center hotels have all had public support in the last 20 years.
.
 
Last edited:
Under pressure from adjacent business owners, UniSource will be adding over 2,000 s.f. of ground-floor retail along the Sixth Ave. side of their new headquarters building, in addition to 8,700 s.f. facing Broadway:


Retail space added to new UniSource HQ
by Dale Quinn
Arizona Daily Star
April 1, 2010

Responding to concerns from neighboring businesses, UniSource Energy Corp. has agreed to add retail space to its planned downtown headquarters. The power provider, which is the parent of Tucson Electric Power Co., recently unveiled plans for the building that included 8,700 square feet of retail space - but none of that was located along South Sixth Avenue. That worried Tim Fuller, who owns the building across the street on Sixth Avenue. He had concerns about his property facing the "dead side of a building" that wouldn't generate much foot traffic. He also was worried about several unsightly electrical boxes designed to sit along Sixth Avenue as part of the new building's power system.

To alleviate that anxiety, the building's designers met with Fuller on Wednesday and told him of new plans to add more than 2,000 square feet of retail space, with some facing Sixth Avenue, said UniSource spokesman Joe Salkowski. They also said they would move the electrical boxes to a place where they would be shielded from the street, Salkowski said. "Is it perfect? No," Fuller said of the design changes. But he quickly added that he was grateful UniSource addressed his main concern: the lack of retail space along Sixth Avenue. "They came and met with us, they listened to what we said … and they did what they said they'd do," Fuller said. Fuller owns the property at 135 S. Sixth Ave. that housed Barrio Food & Drink, which quietly closed its doors about a month ago. He's remained tight-lipped about who might be moving into the property, but he did say it would remain a restaurant.

Janos Wilder - the restaurateur who owns the Janos Restaurant and JBar at the Westin La Paloma Resort & Spa in the Foothills - confirmed his attendance at a meeting where the UniSource building's designers discussed its Sixth Avenue facade. But Wilder, who has expressed interest in opening a restaurant downtown, would not say whether he had any plans to move into the space once occupied by Barrio.

One of Fuller's tenants, Terry Etherton, who owns the Etherton Gallery, said the appearance of the UniSource building along Sixth Avenue would be very important to anyone running a restaurant. Etherton said he supports construction of the new building, in part because it will replace the long-deteriorating Santa Rita Hotel. But the initial design was "woefully weak as far as retail," he said. "We want something that's going to create some foot traffic and bring people downtown," Etherton said.But after the meeting Wednesday, Etherton said he was encouraged by UniSource's decision to focus more of the retail along Sixth Avenue, which is important because UniSource is developing a key piece of property in the heart of downtown. "They have a great opportunity right now to make a statement and do something that's real sensitive to our neighborhood," Etherton said. The neighborhood association in nearby Armory Park hasn't yet taken a formal position on the building's design, as some residents support it and others say it clashes with the historical area.
 
Seems like a great place for students to hang out, especially the mobile-limited freshman...wish UA had that when I was there...

Yea, I'm really excited for this project and the streetcar. I always walk past that ugly vacant lot next to the hotel and I'm sure glad that they're building something that is needed especially for a growing university :awesome:
 
Kozachik to request freeze on hotel plan
Current funding hard to track, and so is the oversight, he says

by Rob O'Dell
Arizona Daily Star
April 5, 2010

Tucson City Councilman Steve Kozachik will call for a halt to all spending on a proposed convention center hotel because of confusion over whether the city or Rio Nuevo is in control of the project. "Who's been keeping track of the money? Nobody," Kozachik said, adding that as a whole, the city and the newly appointed Rio Nuevo board were "completely dysfunctional" in overseeing a new convention hotel. The freeze on funding would affect only about $3.8 million of the $17.5 million that Garfield Traub and its contractors are set to receive from building a new east entrance to downtown's Tucson Convention Center and designing a new convention hotel. The development team already has been paid the remaining $13.7 million.

Kozachik said the freeze is needed because the new Rio Nuevo board is currently lost trying to figure out what money was spent and what current contracts it has. All the while, Garfield Traub is being paid because the city is currently approving payments sent its way by Greg Shelko, the former Rio Nuevo director who is now a consultant to the new Rio Nuevo board. Until the city and the new Rio Nuevo board - which basically used to be a city agency but is now a separate entity because of legislation passed by the state - can agree on a new intergovernmental agreement that defines the responsibilities between the two, Kozachik said, the hotel should be put on hold. The current agreement between the two is outdated because of Rio Nuevo changes passed by the Legislature. "We need to stop spending the people's money until we figure it out," he said. "I want to stop the design until we know we're going to build it. The city can absolutely do that. . . . Right now, what's being done is irresponsible."

Other City Council members and Rio Nuevo board members were noncommittal about cutting off the funding for design. Although the council is slated to discuss Rio Nuevo in two different items on Tuesday - one about staffing and one about a new agreement - Councilwomen Karin Uhlich and Regina Romero said there wasn't a formal proposal, so they couldn't comment. Romero said she agrees with Kozachik that the relationship between Rio Nuevo and the city needs to be better defined with a new agreement. She also said she shares Kozachik's position that any funding of the hotel cannot hit the city's general fund. Councilman Rodney Glassman said he wants Rio Nuevo money to be spent on revenue-generating projects such as the hotel and a new arena, and he chided previous councils for not spending money on Rio Nuevo projects.

Rio Nuevo board member Craig Finfrock said the board is more interested in forming a coherent and workable organization, and it wants to work to potentially hire a new attorney, accountant and executive director before taking drastic measures such as stopping work on the hotel. "We need to create our organization and then get our arms around the project," Finfrock said of the hotel, adding that he believed much of the board agreed. One aspect that Finfrock said he would oppose was shutting down the construction on the east entrance of the TCC, which is currently in progress. About $1.5 million of the $3.8 remaining to be billed to Garfield Traub is for the east entrance.

However, Rio Nuevo board member Scott Egan said he tended to agree with Kozachik's call to freeze funding, adding that he wants to put a limit on new spending until the board determines what happened to the money previously. Although he would like to stop hotel spending, Egan said, the contracts must be looked at to determine the costs of stopping the contract. In addition, he said, the Rio Nuevo board is in the midst of finding a new lawyer, and he said he doesn't want to freeze spending until the new legal representation is secured. The city is waiting for a capital plan from one of its financial advisers on how the hotel would be funded with bonds and what the cost of financing would be. The city would almost certainly have to back the bonds, because Rio Nuevo's funding stream is so limited over the course of the next eight years. Kozachik has an unlikely ally in his hotel-spending halt in liberal activist Jody Gibbs, who has been highly critical of the city's decision-making on Rio Nuevo and other planning areas. Gibbs said the hotel will be good for the hotel developer but not for taxpayers. "The city of Tucson will be left there standing on the corner holding the bag," Gibbs said. "For the city to put money into this is insane. I support him."
 
Kozachik to request freeze on hotel plan
Current funding hard to track, and so is the oversight, he says

by Rob O'Dell
Arizona Daily Star
April 5, 2010

Tucson City Councilman Steve Kozachik will call for a halt to all spending on a proposed convention center hotel because of confusion over whether the city or Rio Nuevo is in control of the project. "Who's been keeping track of the money? Nobody," Kozachik said, adding that as a whole, the city and the newly appointed Rio Nuevo board were "completely dysfunctional" in overseeing a new convention hotel. The freeze on funding would affect only about $3.8 million of the $17.5 million that Garfield Traub and its contractors are set to receive from building a new east entrance to downtown's Tucson Convention Center and designing a new convention hotel. The development team already has been paid the remaining $13.7 million.

Kozachik said the freeze is needed because the new Rio Nuevo board is currently lost trying to figure out what money was spent and what current contracts it has. All the while, Garfield Traub is being paid because the city is currently approving payments sent its way by Greg Shelko, the former Rio Nuevo director who is now a consultant to the new Rio Nuevo board. Until the city and the new Rio Nuevo board - which basically used to be a city agency but is now a separate entity because of legislation passed by the state - can agree on a new intergovernmental agreement that defines the responsibilities between the two, Kozachik said, the hotel should be put on hold. The current agreement between the two is outdated because of Rio Nuevo changes passed by the Legislature. "We need to stop spending the people's money until we figure it out," he said. "I want to stop the design until we know we're going to build it. The city can absolutely do that. . . . Right now, what's being done is irresponsible."

Other City Council members and Rio Nuevo board members were noncommittal about cutting off the funding for design. Although the council is slated to discuss Rio Nuevo in two different items on Tuesday - one about staffing and one about a new agreement - Councilwomen Karin Uhlich and Regina Romero said there wasn't a formal proposal, so they couldn't comment. Romero said she agrees with Kozachik that the relationship between Rio Nuevo and the city needs to be better defined with a new agreement. She also said she shares Kozachik's position that any funding of the hotel cannot hit the city's general fund. Councilman Rodney Glassman said he wants Rio Nuevo money to be spent on revenue-generating projects such as the hotel and a new arena, and he chided previous councils for not spending money on Rio Nuevo projects.

Rio Nuevo board member Craig Finfrock said the board is more interested in forming a coherent and workable organization, and it wants to work to potentially hire a new attorney, accountant and executive director before taking drastic measures such as stopping work on the hotel. "We need to create our organization and then get our arms around the project," Finfrock said of the hotel, adding that he believed much of the board agreed. One aspect that Finfrock said he would oppose was shutting down the construction on the east entrance of the TCC, which is currently in progress. About $1.5 million of the $3.8 remaining to be billed to Garfield Traub is for the east entrance.

However, Rio Nuevo board member Scott Egan said he tended to agree with Kozachik's call to freeze funding, adding that he wants to put a limit on new spending until the board determines what happened to the money previously. Although he would like to stop hotel spending, Egan said, the contracts must be looked at to determine the costs of stopping the contract. In addition, he said, the Rio Nuevo board is in the midst of finding a new lawyer, and he said he doesn't want to freeze spending until the new legal representation is secured. The city is waiting for a capital plan from one of its financial advisers on how the hotel would be funded with bonds and what the cost of financing would be. The city would almost certainly have to back the bonds, because Rio Nuevo's funding stream is so limited over the course of the next eight years. Kozachik has an unlikely ally in his hotel-spending halt in liberal activist Jody Gibbs, who has been highly critical of the city's decision-making on Rio Nuevo and other planning areas. Gibbs said the hotel will be good for the hotel developer but not for taxpayers. "The city of Tucson will be left there standing on the corner holding the bag," Gibbs said. "For the city to put money into this is insane. I support him."

It is truly amazing how much back and forth has gone on regarding this project. I'm finally fed up with even hearing about it anymore. It seems like a lifetime ago that this project was first talked about, and still nothing...
 
It's upsetting to read that this whole hotel plan is kind of a mess right now. Isn't the construction of the hotel suppose to start SOON anyway? Someone commented on KVOA saying they know someone in construction assigned to the project who says they are going to break ground next month...I hope things get organized quickly because I am too getting fed up with nothing happening.
 
While the new Rio Nuevo board tries to sort itself out (yet another of the governor's new appointees resigned this week due to residency ineligibility - http://azstarnet.com/news/local/govt-and-politics/article_09ba6610-6cc4-565a-834d-7cc81cedef9f.html), it appears Councilman Kozachik has little support in questioning the proposed convention center hotel: first the city attorney told him the matter couldn't be discussed as it wasn't on the council's agenda, then Mayor Walkup objected to him trying to block payments to the developer for design services.


City to provide Rio Nuevo staff till June 30
But council says extension depends on new agreement

Rob O'Dell
Arizona Daily Star
April 7, 2010

Tucson will provide staff free for the new Rio Nuevo board until June 30, the City Council decided unanimously Tuesday, but won't continue after that date unless a new agreement with the board is drawn up. The council also voted unanimously to renegotiate the intergovernmental agreement with the new Rio Nuevo board before June 30, which would refine how the new board and the city will interact. The current agreement between the two is moot because of the Rio Nuevo reforms passed by the state. June 30 is the end of the city fiscal year. The city will also immediately begin tracking the costs of services provided to Rio Nuevo, something it hasn't done for more than a year, since then-City Manager Mike Hein told staff to stop billing Rio Nuevo for work done on the redevelopment project.

On a related issue, the council did not vote on a proposal by Councilman Steve Kozachik to cut off the remaining funding for design of a Tucson Convention Center hotel. Although the council talked about it briefly and Kozachik proposed cutting off the funding, city Attorney Mike Rankin cut off the discussion because the item wasn't on the council agenda. Kozachik said he wanted to stop all the remaining $3 million in design being done by developer Garfield Traub until the city and the Rio Nuevo district determine they are going forward with the hotel. However, he said he was not interested in stopping construction of the new entrance to the Convention Center, which makes up about $1.5 million of the $3.8 million still left to be paid to Garfield Traub out of a $17.5 million contract. Mayor Bob Walkup objected to putting the funding on hold, saying the process would "never recover." "We're confident the data will support a convention center hotel," Walkup said, a statement challenged by Kozachik. Walkup said the council wouldn't have authorized it if it didn't make sense.
 
Last edited:
Although two of the three of downtown properties auctioned off on Tuesday went to previous buyers of ADOT parcels, the remaining seven did not receive any bids:


3 downtown lots sold to bidders in ADOT auction
by Coley Ward
Arizona Daily Star
April 7, 2010

On Tuesday, the state of Arizona sold three of its downtown Tucson properties at auction. The largest parcel went to Geoff Shephard, president of Arizona Autopark, who paid $652,000 for a 46,569-square-foot lot on Toole Avenue, between Sixth and Seventh Avenues. Shephard said he would continue to use the lot, which the city has rented since 1987, for parking. "We'll be offering a very good deal to city employees - the cheapest in downtown," he said. This is the second time that Shephard's company has owned the parking lot; years ago he sold it to the state - one of 37 properties that the Arizona Department of Transportation bought between 1986 and 1991 for a proposed expansion of the Aviation Parkway corridor through downtown. The city's easement over six of the properties expired in February, and control of the lands reverted to the state. Now ADOT is divesting itself of its Tucson properties.

Developer Steve Fenton and Peach Properties' Patricia Schwabe bought the other two lots sold at Tuesday's auction. Fenton paid $402,000 for a 17,358-square-foot lot at 35 E. Toole Ave. Previously, the building there was home to ArtWorks, an inner-city program for high school youths. Before that, it was called the Crane Plumbing Supply Warehouse. Fenton said he would restore the building and use it as an "arts-related warehouse." The building might house artist studios or gallery space, he said. Peach Properties paid $360,000 for an 18,375-square-foot lot at 119 E. Toole Ave. Once home to Baker Bros. Produce Warehouse, the building there was most recently occupied by RISE, a nonprofit social-service agency.

Both of the buildings bought by Fenton and Peach Properties have their warts. In 2007, an Arizona Daily Star investigation documented fire damage to the ceiling of the Baker Bros. building and noted that the east and west sides of the warehouse had been condemned. At the Crane Plumbing Supply Warehouse, there were extensive amounts of friable and non-friable asbestos, as well as substantial water damage to the roof and ceiling. Schwabe said she would refurbish the Baker Bros. warehouse, then convert it into a restaurant. "It needs a lot of work," she said.

Both Peach Properties and Fenton have been aggressively buying downtown buildings since ADOT started selling them last year. In October, Peach Properties paid $252,000 for Zee's Warehouse, 1 E. Toole Ave., which is vacant but once was home to Zee Haag, an artist. In November, Fenton paid $101,000 for the building that is home to Solar Culture, 31 E. Toole Ave., a gallery and music venue. The next month, Fenton paid $512,000 for the building at 15-19 E. Toole Ave., which housed the rehearsal space of Salvador Duran, a Latin singer and flamenco guitar player, in addition to Astro Fab furniture makers and artist Jessica McCain's studio. All have since moved out. Both of the warehouses Fenton bought face a vacant lot where Pima County and the city of Tucson plan to build a new courthouse. That project is on hold.

Seven properties went unsold at Tuesday's auction. The Gloo Factory, a nonprofit media-resource center at 106 E. Council St., was one of the properties that didn't receive a bid. Gloo Factory owner Dwight Metzger, who has been raising funds to buy the building but still has a way to go, said he was happy to live to fight another day. "Maybe time is on our side," Metzger said.

ADOT will continue to market the unsold properties, spokeswoman Teresa Welborn said. "They'll stay on the ADOT Web site on the page that says 'properties for sale,' " she said. If ADOT receives an offer for one of its remaining properties, it will trigger a 30-day clock. A second offer during that time will send the property to auction. If no other offer is made, the original bidder can purchase the property.
 
Rather than a restaurant or nightclub, the first new tenant for downtown's recently restored Rialto Block will be Premier Exhibitions, whose initial six-month lease will open with "Bodies...The Exhibition" on May 15:


DonMartinBodiesexhibit.jpg

Don Martin, co-owner of the Rialto Block, talks about
the importance of the exhibit to downtown revitalization.
(photo: Downtown Tucsonan)


‘Bodies - The Exhibition’ coming to Rialto Block
by Teya Vitu
Downtown Tucsonan
April 06, 2010

Bodies…The Exhibition, which has fascinated audiences around the world since 2005, will have a limited engagement at the Rialto Block, 300 E. Congress St., adjacent to the Rialto Theatre, starting May 15. The exhibition will have 10 full bodies in a variety of poses, displaying all organs. One pose will be an orchestral conductor, said Cheryl Muré, vice president of education for Premier Exhibitions, which owns Bodies…The Exhibition. Bodies will have a total of 160 examples of full bodies and body parts preserved with liquid silicon rubber, a process known as polymer preservation. One exhibit includes a healthy lung and a smoker’s lung. “This is one of the most dramatic expositions,” Muré said. “We’ve had many people decide to stop smoking after coming to the exhibition.” “Bodies” currently also has exhibitions at the Luxor in Las Vegas, at the South Street Seaport in New York City, and in Dallas and Montreal. Past exhibitions included Seattle, Warsaw, Athens, Dublin, Puerto Rico and Atlanta.

Rialto Block owners Don Martin and Scott Stiteler intended to put a restaurant into the building but two months ago were approached by Premier Exhibitions. They have a six-month agreement with Premier that will likely be extended to include other Premier shows, possibly Titanic artifacts. “This is over the top,” Martin said. “I couldn’t imagine a better way to kick start this block. How cool would it be to keep this an exhibit hall.” Bodies…The Exhibition opens May 15 for a likely eight-week engagement. Tickets are $14 for children; $17 for military/veteran; $18 for students and seniors; and $22 for adults. Special rates also are available for college and school groups. Tickets go on sale April 23. Tickets are available at the Rialto Box Office or at www.bodiestucson.com.
 
With his prior efforts in downtown revitalization, hopefully the new Downtown Tucson Partnership CEO can find a way to keep the facade restoration program going:


Downtown Partnership names Michael Keith as interim CEO
Downtown Tucsonan
April 8, 2010

Lifelong Tucsonan Michael Keith will become the interim CEO of the Downtown Tucson Partnership effective May 7. Keith will replace Glenn Lyons, who will be leaving that position to become president and CEO of the Downtown Community Alliance in Des Moines, Iowa. Keith will begin working with Lyons immediately to ensure a smooth transition. Keith is president of Contemporary West Development, which specializes in historic restoration and new residential development in downtown Tucson. He led the effort in 2007 to prepare the comprehensive City of Tucson Downtown Infrastructure Study and has been involved in several downtown renovation and improvement projects.

“Under Glenn Lyons’ leadership, the Downtown Tucson Partnership has been an integral part of the tremendous renaissance taking place Downtown,” said Larry Hecker, Chair of the Downtown Tucson Partnership’s Board of Directors. “We are well on the way to restoring downtown to its position as the heart and soul of our community. We are fortunate that a person with Michael’s skills, experience and knowledge stepped forward to ensure that the steadily gaining momentum of downtown revitalization will not slow.”

“It seems to me, looking around the country, that there is no linear progression to how downtowns get revitalized” said Keith. “Progress happens in fits and starts, quiets down, starts up again. You can feel the surge building up again in Tucson, a vibe downtown that is really beginning to intensify. I think the Downtown Tucson Partnership, with its cross-section of businesses, developers, merchants, artists, and civic leaders, must and will play an increasingly active and visible role in this resurgence.”
 