Although it won't affect next month's gem show, the discovery of some missing caissons at TCC will delay the opening of the new east entrance by two months:
Somebody forgot load-bearing pillars at TCC
By Roger Yohem
Inside Tucson Business
January 15, 2010
Tucson (Convention Center) we have a problem: Contractors working on the facilities’ new $4.3 million grand entrance have discovered that five weight-bearing pillar structures were never installed as required 20 years ago, despite the fact that city inspectors signed off on the project. Among other things, it will delay the project by at least two months into April. The good news, relatively speaking, is that contractors Garfield Traub have figured out a fix that shouldn’t cost any more than $280,000.
Stephen Moffett, division president for Garfield Traub, said case of the missing caissons, as they’re called, was discovered during excavation. “The as-built drawings from 20 years ago show five caissons there, in place, supporting the structure. The project was signed off by the city but the as-built drawings are not correct,” he said. As-built drawings are supposed to reflect all changes made during construction. In this case, instead of caissons, a load-bearing beam was installed. “We are adding weight to the building,” Moffett said. “We were counting on those caissons being there.”
Tommy Obermaier, deputy director of the convention center, said city officials are aware of the issue and have confidence in Garfield Traub’s recommendation for a fix. Although the plan was to have the new entry completed in time for February’s Gem & Mineral Shows, the delay will not impact events at the site, Obermaier said. “The reality is, neither gem show we have lets people use that entrance,” he said. “They forced people to use the west entrance.
Despite the added expense, Moffett said that it doesn’t look as if the city will be on the hook to pay it. Instead, the repair money likely will come from Garfield Traub’s “guaranteed maximum price” budget that includes allowances for unforseen expenses. “Some positives have actually come of this,” Moffett said. “We’ve already identified a Tucson contractor as our preference to do the repair.” And they’re also “proactively looking” for other possible structural defects around the building. Garfield Traub has a $200 million contract with the city to construct the new south entry, demolish the west entrance, develop a 525-room hotel, and build a 950-space parking garage.
Somebody forgot load-bearing pillars at TCC
By Roger Yohem
Inside Tucson Business
January 15, 2010
Tucson (Convention Center) we have a problem: Contractors working on the facilities’ new $4.3 million grand entrance have discovered that five weight-bearing pillar structures were never installed as required 20 years ago, despite the fact that city inspectors signed off on the project. Among other things, it will delay the project by at least two months into April. The good news, relatively speaking, is that contractors Garfield Traub have figured out a fix that shouldn’t cost any more than $280,000.
Stephen Moffett, division president for Garfield Traub, said case of the missing caissons, as they’re called, was discovered during excavation. “The as-built drawings from 20 years ago show five caissons there, in place, supporting the structure. The project was signed off by the city but the as-built drawings are not correct,” he said. As-built drawings are supposed to reflect all changes made during construction. In this case, instead of caissons, a load-bearing beam was installed. “We are adding weight to the building,” Moffett said. “We were counting on those caissons being there.”
Tommy Obermaier, deputy director of the convention center, said city officials are aware of the issue and have confidence in Garfield Traub’s recommendation for a fix. Although the plan was to have the new entry completed in time for February’s Gem & Mineral Shows, the delay will not impact events at the site, Obermaier said. “The reality is, neither gem show we have lets people use that entrance,” he said. “They forced people to use the west entrance.
Despite the added expense, Moffett said that it doesn’t look as if the city will be on the hook to pay it. Instead, the repair money likely will come from Garfield Traub’s “guaranteed maximum price” budget that includes allowances for unforseen expenses. “Some positives have actually come of this,” Moffett said. “We’ve already identified a Tucson contractor as our preference to do the repair.” And they’re also “proactively looking” for other possible structural defects around the building. Garfield Traub has a $200 million contract with the city to construct the new south entry, demolish the west entrance, develop a 525-room hotel, and build a 950-space parking garage.