New subdivision developments


http://www.cyberpresse.ca/le-droit/...-urbain-ambitieux-dun-milliard-a-gatineau.php

This proposed $1-billion project in Aylmer between the Rivermead and Chateau Cartier golfcourse as well as near the Champlain Bridge would see 2500 units including possibly four 15-story towers as well as some commercial and office space but no big box stores planned. The developer said it would resemble somewhat the Tremblant village.

Is that along Lucerne or Aylmer Road? If it is along Lucerne (and the river corridor), it would be in an ideal location for a long-term LRT corridor (the old railway line).
 
http://www.cyberpresse.ca/le-droit/...-urbain-ambitieux-dun-milliard-a-gatineau.php

This proposed $1-billion project in Aylmer between the Rivermead and Chateau Cartier golfcourse as well as near the Champlain Bridge would see 2500 units including possibly four 15-story towers as well as some commercial and office space but no big box stores planned. The developer said it would resemble somewhat the Tremblant village.

What I like about the article is when they say that “people will be able to live, shop and dine, and EVEN work on site, in certain cases” (les gens pourront résider et consommer, et même travailler sur place dans certains cas). Nothing like managing expectations guys.

But I shouldn’t be too much of a killjoy. It nonetheless sounds miles ahead of most of what’s being built elsewhere in this region.
 
That's an interesting point from Peter Hume, I didn't really consider that part of Bill 51, but it would be interesting to see how it turns out. I doubt it will make a difference though - "have regard to" is a pretty weak statement in my opinion. The old PPS used the same language, which was generally considered to be too weak and was strengthened to "shall be consistent with".

It is interesting... because it would be on a point of law in that the OMB failed to follow the provincially-set terms guiding its mandate in coming to its decision.

My guess is that if the City prevails at divisional court - which they could in this case on that specific point of law - then the entire thing gets dumped back to the OMB for a rehearing in which the OMB has to consider the City Council direction in its decision. The ultimate decision could still go against the City, but the OMB would have to spell out more explicitly why - i.e. "You [idiots] sent a pipe down there, which is a defacto violation of your own stated policy. Now that it's there, this development application is consistent with all other policies." I suspect the City will still lose this one, but it may well be that in the future (and for other municipalities as well) that the OMB might start to make fewer pro-development rulings. This would be good for, say, that other Manotick development on the east side of the river.
 
Cre47 said:
http://www.cyberpresse.ca/le-droit/a...a-gatineau.php

This proposed $1-billion project in Aylmer between the Rivermead and Chateau Cartier golfcourse as well as near the Champlain Bridge would see 2500 units including possibly four 15-story towers as well as some commercial and office space but no big box stores planned. The developer said it would resemble somewhat the Tremblant village.

wow I knew they were going to open that up for development, but I thought it was going to be more like the Plateau area with it's neverending maze of non linear streets.

edit.. here's a map..

http://www.brigil.com/fr/emplacements/pdf/ac/plansite_ambassade.pdf
 
wow I knew they were going to open that up for development, but I thought it was going to be more like the Plateau area with it's neverending maze of non linear streets.

edit.. here's a map..

http://www.brigil.com/fr/emplacements/pdf/ac/plansite_ambassade.pdf

The “secteur commercial” on the map looks awfully small and, in spite of what they say about no big-boxes, looks like it has two big boxes on the east side of it.

BTW, people who know the industry say that Brigil boss Gilles Desjardins, who has made millions, has now evolved (as many businesspeople do) to the ego/legacy phase of his career, and is apparently more conscious about building nice (or at least nicer) stuff that people will remember him by.
 
Is that along Lucerne or Aylmer Road? If it is along Lucerne (and the river corridor), it would be in an ideal location for a long-term LRT corridor (the old railway line).

Well it's between the two roads, basically with that development, every area between Aylmer Road and Lucerne Road from downtown Aylmer to the Champlain Bridge will be developped. As for light-rail, I'm not sure they would like to see the trails replaced by rapid transit (we see that in the Ottawa River Parkway that the NCC don't really want rail), though replacing Lucerne by rail wouldn't bother at all. Although any rapid transit corridor in Aylmer will likely use the Hwy 148 corridor connecting to the Rapibus, although in the roundabout area could be tricky if they want transit separately from regular traffic.
 
... though replacing Lucerne by rail wouldn't bother at all. Although any rapid transit corridor in Aylmer will likely use the Hwy 148 corridor connecting to the Rapibus, although in the roundabout area could be tricky if they want transit separately from regular traffic.

From what I remember reading somewhere (think it was the Bulletin d'Aylmer) the people of Val-Tetrault put up an enormous stink at the idea of a rapid transit line going down Lucerne (the now defunct Via-bus idea)... and you're right, if any rapid transit comes to Aylmer it will likely be along that Allumettières corridor.

Acajack - I didn't have time to finish my post earlier.. looking at that map from Brigil it looks more suburban than I realized. I think that map has been up for a while now, maybe they've made some revisions (hope so).
 
Mattamy Richmond

Mattamy unveils the numbers
Up to 2300 new homes
April 18, 2009
BY JOHN CURRY
http://www.yourstittsville.com/StittsvilleNews/article/12127

The numbers have now been revealed. There will be between 1800 and 2300 new homes built on the lands controlled by Mattamy Homes on the western edge of the village of Richmond. But it is also anticipated that the earliest that any construction could happen is the year 2011 and that it could take years for the new development to be completed.

Jim Constantine of LRK Consultants, which has been involved in the development of visioning principles governing Richmond’s development and has been working on a concept plan for the 365 acre Mattamy lands, explained at a meeting of the Richmond Village Plan Steering Committee on Wednesday, April 8 how these visioning principles developed through community involvement are being applied in the case of the Mattamy concept plan.

The concept plan advocates planned managed growth, a more vital village core at Perth and McBean Streets, pedestrian linkages between the new and existing areas as well as throughout the whole village, continuation of the historic grid system for streets, creation of a gateway feature involving a roundabout, a water vista and greenspace at the western end of Perth Street, preservation of existing hedge rows to provide green buffers, accessible local parks, creation of a green corridor along the Van Gaal Drain all the way from the Jock River to the northern edge of the village, open space and a trail system along the Jock River and emphasis on views of the adjacent agricultural lands to emphasize the historic relationship of the village to its surrounding landscape.

The 1800 to 2300 new homes would include both single family homes and attached housing, although the exact breakdown of these housing styles is not yet publicly available.

Mattamy Homes last week submitted its Official Plan Amendment application to the city of Ottawa regarding the development of its lands in Richmond. The submission was accompanied by a myriad of technical reports and support studies, some of which apply to the whole village for inclusion in the Richmond Community Design Plan which is now under development by the Richmond Village Plan Steering Committee and city of Ottawa planning staff. The Mattamy Homes reports and studies include a master servicing study for the whole village, a village-wide transportation study, a natural environment report, a geo technical study, an agricultural assessment study and a storm water drainage plan. All of these reports are going to be posted on the city’s website and a copy of each will be available at the Richmond branch of the Ottawa Public Library.

Susan Murphy, the Mattamy Homes project manager for these Richmond lands, said that the aim is for city approval of the Official Plan Amendment as well as the Richmond Community Design Plan this fall. If this happens, then the process of getting approval for a plan of subdivision and related zoning will take about 10 months, she said. With detailed engineering and other factors, it will be 2011 at the earliest before any actual building permits for the Mattamy lands are issued by the city, she said.

She said that while phasing of the Mattamy development in Richmond is still being worked on, it is probable that the lands just south of Perth Street at the western edge of the village will be the first ones developed by Mattamy. She said that a definitive phasing plan will be determined once the various servicing aspects of the development are finalized.

Sean Moore, a planner with the city of Ottawa, told those at the April 8th meeting that the city will be putting up signs in the community about the Mattamy Official Plan Amendment application and will be circulating the application to various agencies and city departments for review and comment. He said that there will be a public open house community information session at some point in the process as the Official Plan Amendment and its related studies are reviewed.

Despite filing an Official Plan Amendment for its lands, Mattamy Homes is continuing its involvement with the Richmond Village Plan Steering Committee and its work at developing a Community Design Plan for the village.

[email protected]
 
A couple more Mattamy Richmond stories

Neighbourhood commercial in Richmond
April 24, 2009
BY JOHN CURRY
The proposed new Mattamy development in Richmond may not have a neighbourhood commercial hub.
Such a hub has been proposed in Mattamy’s initial planning for the development on the west side of the existing village but this may change if increased neighbourhood commercial sites are included along the west end of Perth Street in the Community Design Plan which is now being developed for Richmond.

At the most recent meeting of the Richmond Village Plan Steering Committee, city of Ottawa planner Don Morse suggested that an expanded neighbourhood commercial area could be designated around the site of the current Richmond Home Hardware.

This suggestion brought forth a comment from Sue Murphy, the project manager for Mattamy for Richmond, that if this enlarged neighbourhood commercial area were put on Perth Street, there would be no market for such a commercial area within the future Mattamy subdivision south of Perth Street and it would be removed.

She said that Mattamy had thought that such a neighbourhood commercial area should be located internally in the new subdivision but that if the desire now was for more such neighbourhood commercial along the west end of Perth Street, then such an area would be removed from the subdivision plan.

A neighbourhood commercial land use would be meant to create a vibrant, mixed use pedestrian oriented area centred on the provision of goods and services and acting as a focal point for a neighbourhood. Such an area would include a wide range of small scale commercial, leisure, institutional and residential uses serving local needs.
Walkway to connect the old and the new
Planning in Richmond
April 06, 2009
BY JOHN CURRY
The Mattamy Homes lands on the west side of Richmond and south of Perth Street may be linked to the existing village by a pedestrian walkway that would extend all the way to a neighbourhood centre in the new area.
Planning consultant Jim Constantine, who has been involved with Mattamy Homes’ community design efforts in Richmond through the LRK consulting firm, told those at the recent open house dealing with the sewer, water and transportation plans for Richmond which are needed before any new development happens that this walkway at the west end of the existing Martin Street would cross the nearby drain and environmental area, creating a special focal area which he referred to as “The Crossing.”

The idea would be for both existing village residents and residents of the new area to the west to both use this new recreational and open space area, with its boardwalk across the waters of the drain. This walkway would become a special promenade that would lead to a neighbourhood centre. This would be a small commercial area that would feature such services as a day care centre and a café, all meant to serve village residents.

He said that the planning of this landmark pedestrian walkway area is still underway as is the preparation of a draft neighbourhood plan for the proposed Mattamy Homes development in Richmond.

“The Crossing” is meant to respond to one of the big challenges facing Mattamy Homes in its proposed development in Richmond and that is how to connect the new development with the existing village community, particularly since a drain and surrounding environmental area prevent street connections in the Hamilton Street/Martin Street area.

Mr. Constantine, in his remarks at the meeting, made it clear that he understood that existing Richmond residents do not want typical suburban development to happen in their village.

He said that in last April’s planning workshops and last September’s follow-up workshops about the future of Richmond, one of the things that was made absolutely clear from the comments of residents is that people move to Richmond to get away from the typical suburbs.

“You made that 100% crystal clear,” he told those at the meeting.

He reminded those at the meeting of the principles which were established through a survey and resulting input last year. These visioning principles were that Richmond be a liveable and sustainable community, that its historic village character be protected and enhanced, that open spaces and recreation and community services be created, that the natural environment be protected and that the transportation infrastructure be expanded.
 
Minto homes in on city lawsuit
By DEREK PUDDICOMBE
Last Updated: 9th May 2009, 2:15am
http://www.ottawasun.com/news/ottawa/2009/05/09/9402761-sun.html

Local developer Minto is suing the city for $1.4 million.

City councillors learned on Thursday that Minto is looking to recoup all its legal costs spent on defending its right to build 1,400 homes in Manotick.

Council rejected the plan under the Secondary Official Plan Amendment last year, which forced the developer to take the matter to the Ontario Municipal Board.

"Minto's claim for costs is for approximately $1,474,000 it states to have been incurred since the date of council's refusal of the amendment," said city solicitor Rick O'Connor in an e-mail to councillors.

The OMB recently ruled in favour of allowing Minto to move ahead with its development project that would almost double the size of the village in the southern portion of the city.

O'Connor told councillors he's confident Minto won't get what it's asking for. "It is the opinion of the city's external counsel and legal services staff that the course of conduct of the city in this matter is not such as would warrant an award of costs."
 
Minto homes in on city lawsuit
By DEREK PUDDICOMBE
Last Updated: 9th May 2009, 2:15am
http://www.ottawasun.com/news/ottawa/2009/05/09/9402761-sun.html

Local developer Minto is suing the city for $1.4 million.

City councillors learned on Thursday that Minto is looking to recoup all its legal costs spent on defending its right to build 1,400 homes in Manotick.

Council rejected the plan under the Secondary Official Plan Amendment last year, which forced the developer to take the matter to the Ontario Municipal Board.

"Minto's claim for costs is for approximately $1,474,000 it states to have been incurred since the date of council's refusal of the amendment," said city solicitor Rick O'Connor in an e-mail to councillors.

The OMB recently ruled in favour of allowing Minto to move ahead with its development project that would almost double the size of the village in the southern portion of the city.

O'Connor told councillors he's confident Minto won't get what it's asking for. "It is the opinion of the city's external counsel and legal services staff that the course of conduct of the city in this matter is not such as would warrant an award of costs."

Besides the fact that being awarded costs at the OMB is basically unheard of - defending an existing plan against a proposed amendment is hardly grounds for costs, after all - does anyone else find it more than a little disturbing that the developer with whom the City is negotiating for Lansdowne Live! is suing the City for something else?
 
eport revives Kanata West projects

More water storage capacity would guard against flooding, consultant advises

BY PATRICK DARE, THE OTTAWA CITIZENMAY 11, 2009 10:14 PMBE THE FIRST TO POST A COMMENT


Ottawa – The controversial Kanata West development is back on the planning track after the planning and environment committee approved the work of an independent consulting engineering firm Monday.

The committee approved the report, which calls on developers in the Kanata West area — 725 hectares around Scotiabank Place — to create 85,600 cubic metres of additional water storage capacity to guard against flooding.

The consulting engineer, Don Moss of Greenland International, was brought in to review the stormwater modelling after errors were discovered in some of the work of other consultants working on various development projects.

Moss’s solution is to create about 120 cubic metres of additional water storage capacity per hectare of development as a flood insurance policy. Even the worst possible flood scenario for the Carp River and its tributaries would not result in flooding of homes or businesses if this is done, councillors are being told.

The planning committee agreed, on condition that the 40 property owners of the Kanata West Owners’ Group pay for the facilities. The city’s consultant, Greenland, will oversee the measures and control the modelling system for measuring water flow and storage.

The planning committee also voted to permit several developments on land near the Kanata West property to proceed. These projects, including Huntley Medical Centre, Huntley Centennial Public School and several housing subdivisions, were delayed due to the freeze on the Kanata West development.

“It’s a good step forward,” said Kanata North Councillor Marianne Wilkinson.

Rob Mackay, the city manager charged with clearing up the Kanata West file, said winning the planning committee’s approval, then city council’s in two weeks, would be “a big hurdle” passed.

But he said that the huge development — including residential subdivisions, office buildings and stores — must still make it through more reports and studies, including one by the federal government.

A key step will be getting approval from Ontario Ministry of the Environment officials.

City water resources engineer Ted Cooper told councillors that the development should not get the green light yet because there still had not been properly calibrated computer modelling of the water in the area. He noted that Glencairn had seen flooding in the past. As well, the flood scenario used in the report should have been based on urban modelling, rather than the rural model used by the consultants, he said.

But councillors approved the review, saying it ended years of costly delays in the approvals process. One of the benefits of the Kanata West development will be the restoration of the Carp River, a project now estimated to cost $8.5 million and will take three to six years.

© Copyright (c) The Ottawa Citizen
 
moffat farm - southfacing
3564565832_5c31836cbe.jpg
 
Panel OKs new suburb in west end
http://www.ottawacitizen.com/news/Panel+suburb+west/1679428/story.html
One day, 31,000 people could live between Kanata, Stittsville

BY JAKE RUPERT, THE OTTAWA CITIZENJUNE 10, 2009 12:01 AM


STORYPHOTOS ( 1 )

1679429.bin


Locator
Photograph by: Dennis Leung, The ottawa Citizen
OTTAWA-Large-scale plans for a massive suburban development connecting Kanata and Stittsville passed the planning committee Tuesday over the concerns of neighbours and some of the developers involved.

The suburb is to be built on 674 hectares between Fernbank and Hazeldean roads and could contain up to 11,000 residences, 2,650 jobs, and have a population of 31,000 when fully constructed.

The area is largely made up of land the city initially refused to open for development, but the owners appealed the city’s decision

to the Ontario Municipal Board, which can overturn city council planning decisions, and won in 2005. The properties include that land and closely connected property expected to be approved for development by council today. Now the city government is working out how new neighbourhoods there should be designed and serviced.

“Nobody wanted this project on Day 1, in terms of the city, or the council, or the community at the time,” said Shad Qadri, the councillor for Stittsville-Kanata West.

“The community might still not want this project, but the OMB made this decision … it’s time to move forward on it and develop this community to the best of our ability.”

The land would be developed by a group including Richcraft, Metric Homes, Fernbank Properties, Urbandale and Mattamy Homes, which will have to get specific approvals for their projects based on the rules city council is setting now.

The council committee approved plans developed by city staff, with input from

area residents and the landowners, for the kind of development the city would like to see, including where the roads, sewers, parks, community centres, public transit routes and schools will be.

Most of the land would be used for low-density housing, but with medium- and high-density residential units on the major roads.

The plans call for 76 kilometres of watermains, sanitary sewers and storm sewers.

There would also be a series of stormwater containment ponds. Altogether, the water system should cost the city about $1.3 million a year.

Representatives from the developers group agreed with the bulk of the plans developed by city staff, however, they disagreed with where the city wanted the district’s main park to go — in the eastern portion of the property, a little west of the current intersection of Terry Fox Drive and Castlefrank Road. The committee opted to go with their staff’s plan, on the grounds that it had been approved by the public through a long process of consultations. City council must give final approval on the project before it can go ahead, and it will be dealt with later this month.

With files from Katie Daubs

© Copyright (c) The Ottawa Citizen
 
City lawyer asks court to clarify planning law

Unclear who controls development: councils or OMB

BY PATRICK DARE, THE OTTAWA CITIZENJUNE 25, 2009 11:06 PM


OTTAWA — A lawyer acting for the City of Ottawa argued Thursday that the courts must decide who makes development decisions in Ontario: elected city councils or the Ontario Municipal Board.

At stake is a massive development that could double the population of Manotick, one the board approved over Ottawa city council’s objections.

Lawyer Paul Webber told Superior Court Justice Robert Maranger that the Ontario government’s recent changes to planning law required that the municipal board — which hears appeals of city decisions — “shall have regard for” any decision of an elected council. But he said that “magic phrase” hasn’t been defined in law and cities like Ottawa need a judicial ruling as to what it means.

The city is asking the justice for the chance to have an appeal hearing in Divisional Court on a municipal-board decision that the city lost and Minto Developments won. City council voted against a proposed major Minto Developments expansion of Manotick. Minto appealed the council decision, pointing out that the city’s own planning staff had recommended the development be approved.

Council’s recent decision to try to appeal the board decision was unusual, but councillors said they need to have a legal interpretation of what the new provincial law on land-use planning, Bill 51, means.

Webber said that municipal governments, which used to be simply creatures of the provincial government, have seen their powers and role strengthened by Ontario through changes such as a revised Municipal Act. Webber said that with these changes, the municipal board should be able to overturn a council decision only when that decision is unreasonable or unlawful.

Webber said there has been an “incoherence” in recent municipal board hearings that shows “need for judicial guidance.”

The lawyer for Minto, Robert Doumani, said there’s no confusion at all over the roles and responsibilities of elected councils and the municipal board in Ontario. He said the phrase “have regard to” is commonly used in planning matters and it doesn’t mean that the municipal board must show deference to councils. Doumani said that if the provincial government wanted to significantly change the power of municipal councils it would have spelled out those changes.

Besides, he said, the city’s own planning documents, including a 91-page report by the city’s planning staff, supported the Manotick expansion.

Webber said the city’s secondary plan for Manotick limited growth to 250 houses by 2020 and the municipal board decision failed to spell out how that plan was unreasonable.

The municipal board decision is to allow Minto to build 1,400 houses. Minto owns about 430 acres in Manotick bounded by Century Road, First Line Road and Manotick’s Main Street and would build about 150 houses a year.

There are risks for the city, which spent $637,000 in direct legal and planning costs for the municipal board hearing. If the city loses the appeal bid, it could be on the hook for costs for both parties.

When councillors voted to try to appeal the Manotick decision, some said the case was about standing up to the municipal board. Council voted 13-5 to pursue the appeal.

Maranger reserved his decision on whether to allow an appeal.

© Copyright (c) The Ottawa Citizen
 