Excavation commenced 8 months ago in May 2023, and to date, we have completed shoring, bulk, and detailed excavation.
Concrete forming is currently underway, with preparations for pouring the North side P3 deck by January 26, 2024.
Slab on grade for the entire site is scheduled for completion by mid-February 2024.
On the South side, progress is being made with footing, column, and wall installations, with waterproofing ahead of wall forming and footing install.
Plumbing work is ongoing, focusing on catch basins, sub-drains, perimeter drains, and sump pits.
Electrical work is progressing with in-slab rough-ins.
Underground Civil works on Sussex Avenue is ongoing, with the removal of existing overhead utility lines expected to be completed by March 2024.
Slab on Grade for the North section of the site was completed on January 6, 2024.
|