  #161  
Old Posted Jan 17, 2018, 12:34 AM
Proof Sheet Proof Sheet is offline
Registered User
 
Join Date: May 2009
Posts: 2,985
Quote:
Originally Posted by waterloowarrior View Post
City will be considering site-specific criteria for minor variances on the Salvation Army site. Basically they would not be able to expand the shelter use beyond 801 sq m without going to Council instead of CofA... and any applications for a variance must include a desription of the layout and number of beds within the 801 sq m. Basically this tries to avoid what happened for the Hard Rock Casino and some student housing projects.
http://app05.ottawa.ca/sirepub/agdocs.aspx?doctype=agenda&itemid=372515
That 'student housing project' item in terms of the interim control by-law has an OMB date of May8/9.

I'm glad you can explain this C of A restriction. I couldn't figure it out.
Reply With Quote
     
     
  #162  
Old Posted Jan 17, 2018, 2:35 AM
kwoldtimer kwoldtimer is online now
Registered User
 
Join Date: Jan 2008
Location: La vraie capitale
Posts: 26,161
Do I understand correctly from that that over 90% of the facility's floor area will be for purposes other than temporary shelter?
Reply With Quote
     
     
  #163  
Old Posted Jan 17, 2018, 10:08 PM
downtown_eddie_brown downtown_eddie_brown is offline
Registered User
 
Join Date: Nov 2015
Posts: 76
Quote:
Originally Posted by kwoldtimer View Post
Do I understand correctly from that that over 90% of the facility's floor area will be for purposes other than temporary shelter?
According to the site plan, the building footprint is roughly 1542 square meters. Across all floors and basement, the building is 6159 square meters.

http://webcast.ottawa.ca/plan/All_Image%...06-20%20Site%20Plan%20D02-02-17-0062.PDF

It's strange that the bylaw specifies changing square footage usage as requiring council approval, and not changing the number of beds allocated. I don't know if this would happen, but I could see the SA increasing density within their 801 square meters to the point where it becomes a safety issue, at which point council will have no choice but to approve the usage change.
Reply With Quote
     
     
  #164  
Old Posted Feb 13, 2018, 3:42 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,540
Salvation Army not keen on bed restriction in future Vanier shelter

Jon Willing, Ottawa Citizen
Published on: February 12, 2018 | Last Updated: February 12, 2018 9:21 PM EST


The Salvation Army isn’t keen on the idea of the city’s regulating the number of shelter beds in a social services complex the organization plans to construct in Vanier.

Glenn van Gulik, spokesman for the Salvation Army, said the organization believes council has already addressed the planning questions through the November 2017 vote approving the necessary land-use changes for 333 Montreal Rd.

“We’ve already been down this path,” van Gulik said. “City council has already gone through the different options for limiting the space to emergency shelter.”

The Salvation Army is “comfortable” with the council-directed restriction of 801 square metres for the shelter, van Gulik said. Ideally, the Salvation Army won’t need to have 140 shelter beds, but it’s hard to predict what the social need will be in future years, he said.

Council actually reduced the shelter’s gross floor area from the staff-recommended 900 square metres.

Rideau-Vanier Coun. Mathieu Fleury has told council members that on Wednesday, he’ll ask them to support a cap of 140 emergency shelter beds in the shelter, which would be part of a larger complex.

Fleury said he wants the Salvation Army to “reaffirm” to the public that 140 will be the maximum number of shelter beds, while urging the city to hold the organization to that commitment.

City clerk and solicitor Rick O’Connor said that first it will take three-quarters of council members present to vote in favour of considering Fleury’s motion, since council already approved the zoning amendments for the Salvation Army.

Council voted 16-7 last November to change the zoning bylaw and official plan to allow the Salvation Army to build a shelter and social services complex at the Montreal Road property. The Salvation Army wants to relocate its Booth Centre from the ByWard Market.

Businesses have appealed council’s decision to the Ontario Municipal Board, with financial help from community group SOS Vanier.

Last month, council approved a motion that ensures any future attempt to expand the area of the shelter must come to planning committee and council, but opponents of the development worry council hasn’t gone far enough to regulate the Salvation Army’s bed count in the shelter.

Drew Dobson, the organizer of SOS Vanier, said the council-approved restriction on the size of the shelter would actually allow more beds under the city’s own shelter standards.

The standards say sleeping areas in a shelter must give each adult 3.5 square metres of space, not including the 0.75-metre separation distance from the edges. An 801-square-metre shelter could provide up to 228 beds under those guidelines.

Dobson also flagged a letter from the Salvation Army’s lawyer suggesting the 140-bed figure in the original planning application is a “demonstration” and that the actual number will vary over time.

“That disappointed me and made me very concerned,” Dobson said.

It’s in the Salvation Army’s interests to commit to the 140-bed cap for the shelter, according to Dobson. “I think they run at a danger that, if they don’t support it, they look hypocritical,” he said.

At the same time, Dobson said he has asked the city to give the Salvation Army flexibility to add beds in the shelter under critical circumstances, such as during a cold snap when homeless people need somewhere warm to sleep.

Opponents of the Salvation Army’s plan have been eagerly awaiting a housing and homelessness report for council’s community and protective services committee to provide feedback on how the city funds shelters. City staff are gathering input before they undertake a review of the 10-year homelessness plan at the halfway point in 2019. The plan was implemented in January 2014.

Coun. Diane Deans, who chairs the community and protective services committee, agreed with a request from Mayor Jim Watson on Monday to put off the report one month until a meeting in March so it aligns with a separate report coming from Coun. Mark Taylor, who’s the mayor’s liaison on housing and homelessness issues.

[email protected]
twitter.com/JonathanWilling

http://ottawacitizen.com/news/local-news...bed-restriction-in-future-vanier-shelter
Reply With Quote
     
     
  #165  
Old Posted Feb 13, 2018, 7:30 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by rocketphish View Post
At the same time, Dobson said he has asked the city to give the Salvation Army flexibility to add beds in the shelter under critical circumstances, such as during a cold snap when homeless people need somewhere warm to sleep.
That was my first thought. Imagine the headlines if the Salvation Army has to turn someone away during a cold snap because they reached the 140 bed maximum the city set and that person dies of exposure on the street. Maybe grant an exemption if Environment Canada issues a weather advisory or the city declares a State of Emergency.
Reply With Quote
     
     
  #166  
Old Posted Feb 15, 2018, 12:38 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,540
Council softens order to limit shelter beds in Salvation Army complex

Jon Willing, Ottawa Citizen
Published on: February 14, 2018 | Last Updated: February 14, 2018 5:04 PM EST


Council just wants the Salvation Army’s word that the organization will have a maximum of 140 beds in a new emergency shelter, rather than writing the measure into the land-use bylaw for the Vanier property.

The softer motion, unanimously endorsed by council, replaced a proposal by Rideau-Vanier Coun. Mathieu Fleury to write into a bylaw the maximum number of shelter beds in the Salvation Army’s complex planned for 333 Montreal Rd.

Mayor Jim Watson said the city couldn’t enforce the number of shelter beds, so he worked with Fleury and Alta Vista Coun. Jean Cloutier on a replacement motion.

“We didn’t believe you could put that kind of restriction in a zoning bylaw. That was the staff report back to us,” Watson said after the council meeting.

Watson said asking the Salvation Army to commit to a maximum of 140 shelter bids achieves the same goal.

“I’m a little bit disappointed because this motion has no teeth and it doesn’t prevent them from five years from now saying things have changed and we need additional beds,” SOS Vanier organizer Drew Dobson said.

Dobson said a bylaw restriction would have at least forced the Salvation Army to apply to council for any changes to the number of shelter beds.

Land-use changes that allow Salvation Army’s development plan are under appeal at the Ontario Municipal Board.

<snip>

[email protected]
twitter.com/JonathanWilling

http://ottawacitizen.com/news/local-news...t-shelter-beds-in-salvation-army-complex
Reply With Quote
     
     
  #167  
Old Posted Aug 10, 2018, 11:45 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,540
'It's not NIMBY, it's nowhere': Opposition to Salvation Army shelter complex remains strong in Vanier

Matthew Pearson, Ottawa Citizen
Updated: August 10, 2018


A 1992 Chevrolet van rumbles up to a home on Richelieu Avenue.

Out springs Bruce McConville, his shirt already a darker shade of blue thanks to the sweat seeping through it on this muggy, grey morning. He’s here to collect some furniture for an upcoming garage sale intended to raise money for SOS Vanier’s legal fight.

The community group needs $200,000 to cover the cost of appealing to the Ontario Municipal Board to prevent a 350-bed Salvation Army homeless shelter complex from opening on Montreal Road. It may be Vanier’s only hope to halt the controversial project.

“I don’t need the money for this, so why not donate it for that cause?” says Diane Irwin, as her husband Brian helps McConville carefully load the family’s dining room table and chairs into the van.

Irwin grew up in Vanier and raised her children here. She never feared walking down the Montreal Road of her youth at night, but she wouldn’t dare these days. Like many, she worries the situation will only get worse if the shelter opens.

For three long days last fall, Irwin watched as a steady stream of residents appealed, cajoled and downright begged members of the city’s planning committee not to approve the project, which had already won a thumbs-up from bureaucrats.

It didn’t feel like the community’s concerns were actually heard, she recalls, and the final vote confirmed as much. Six votes for, three votes against the shelter. Council endorsed the plan five days later by a vote of 16-7.

“We feel betrayed by the city because they didn’t listen,” Irwin says.

That feeling runs deep in Vanier, yet the enduring opposition to the Salvation Army’s plan may run ever deeper. The shelter proposal isn’t just wrong for this neighbourhood, opponents say. It’s wrong, period.

Wrong location, wrong size, wrong model.

“It’s not NIMBY, it’s nowhere,” says McConville, who decided at the last minute to enter the mayor’s electoral race (he’s run and lost twice previously in Rideau-Vanier ward). “There is no doubt such a huge concentration of homeless people will turn any area into a ghetto.”

Now that council’s decision has sunk in and both sides gird for battle at the OMB, a hearing that could be at least another year away, Vanier finds itself in a purgatory of sorts.

While signs of investment and renewal along Montreal Road are elusive, a strong housing market continues to bring new people to the area who are attracted by urban living at a reasonable price.

**

Drew Dobson takes a seat on the new patio outside Finnigan’s Pub, which is less than a 100-metre dash east of where the Salvation Army wants to put its $50-million shelter complex.

The man who launched the SOS Vanier movement has put his money where his mouth is by investing in his business in hopes of improving the look and feel of Montreal Road.

Dobson spent about $30,000 to build the 80-seat patio and hopes it may prompt other landowners and businesses to do the same. “I still have faith in this neighbourhood,” he says.

Montreal Road is a long way from reaching its full potential as a thriving, attractive traditional mainstreet.

Boarded-up buildings, overgrown lots, crumbling sidewalks and a virtual lack of shops and cafés that serve as both a destination and gathering place for residents make it hard to think of the road as anything but a thoroughfare.

Sure, you can mail a letter or buy diapers at Jean Coutu or eat a flaky almond croissant at Quelque Chose Pâtisserie, but then what? Pot shops, payday lenders and pawn shops.

The city’s ultimate vision, according to its website, is to “construct a vibrant and welcoming main street with a well-balanced transportation network that will allow residents and businesses to thrive.”

But many fear the arrival of the shelter will extinguish any spark created by the road revitalization project set to begin next spring. “It will choke economic development,” Dobson says.

Since council approved the shelter plan, landlords have had a hard time filling vacant commercial and office space, says Mark Kaluski, chair of the Quartier Vanier Business Improvement Area.

On the housing front, Vanier remains attractive to buyers, says real estate agent Natalie Belovic.

Housing sales in the second half of 2017, which was after the Salvation Army’s plan was revealed, were actually stronger than in the first half. The market remains strong this year, but Belovic says it’s not as much of a slam-dunk as it was several years ago.

If you exclude higher-end infill from the equation, the average selling price in 2018 is $377,000 and properties are spending a month on the market.

Closer to the proposed site on Montreal Road is a tougher sell, Belovic says. Houses are still turning over, but not as quickly as they were and perhaps for not as much money as they might have just two years ago.

Like Dobson and McConville, Belovic says opposition to the proposal is not about residents being against services for vulnerable populations. It’s about the proposed size and location on a community’s main street. That construction of another large emergency shelter contradicts the city’s espoused commitment to housing-first is icing on the cake.

“No community nowhere would like to have a 350-bed shelter in their neighbourhood,” Belovic says. “There’s not a single place where people would lie down and let that happen.”

**

Some think the SOS Vanier campaign is a waste of time and money because a deal was struck behind closed doors between politicians and the Salvation Army long before council’s vote last November.

Dobson and McConville both say they hear this from people all the time. “You’re up against too much,” McConville recalls one person saying.

Dobson doesn’t disagree council acted partially when it ruled in the Salvation Army’s favour. But he’s got confidence in the strength of the OMB appeal and the impartiality of the board, a quasi-judicial body with the power to quash council’s wishes.

He’s also bolstered by the support of MP Mona Fortier, MPP Nathalie Des Rosiers, Rideau-Vanier Coun. Mathieu Fleury and the BIA. “This is not a community divided,” he says.

SOS Vanier has raised more than $150,000, much of it from residents. “We’re getting it from people who need the money and that saddens me,” Dobson says.

The funds will be used to pay the group’s lawyer Michael Polowin and hire expert witnesses to pick apart the case made by city planners.

Part of what could be fuelling SOS Vanier’s fundraising efforts is anger with Mayor Jim Watson and some city councillors.

The mayor caught many by surprise when he publicly announced his support for the Salvation Army’s plan, even going so far as to challenge opponents to suggest another location if not Montreal Road.

After the council vote, he told reporters: “I wish we didn’t need shelters. I wish there were no shelters in any community, but the reality is there is going to be a need for shelters and they have to go somewhere.”

Why Watson feels so strongly Vanier is that “somewhere” remains unclear.

Because he’s dug in his heels, it seems the Salvation Army has followed suit, refusing to budge an inch on its proposal and shrugging off the community’s concerns, Dobson says. “They wouldn’t do that unless they knew there was political cover.”

Making matters even murkier is speculation Alta Vista Coun. Jean Cloutier may have switched his vote in the final minutes of the planning-committee meeting to side with the majority.

Cloutier, Dobson says, appeared sympathetic to the SOS Vanier cause when the two met previously.

“Vendu Cloutier!” shouted a man from the public gallery that night (“vendu” can be a slang word in French for a sell-out).

The backstory Dobson’s heard is that Cloutier, a first-term councillor facing a strong opponent in Raylene Lang-Dion, was told to either tow the mayor’s line or face a strong opponent without Watson’s support.

In a written statement, Cloutier says such suggestions were “absolutely wrong and 100% not true.”

Cloutier claims to be one of few councillors who met with SOS Vanier members and Fleury in advance of the planning committee and council meetings to hear all sides before making a decision.

“Ultimately, I supported the proposal because I believe that it was the right decision for the City. I understand and I am empathic to the concerns of the local community — I conveyed as much during the meetings I took with them but on balance the decision of the Planning Committee and City Council was the right one for the City,” his statement says.

**

Neither Dobson nor McConville seem to let the spectre of backroom politics dissuade them from their mission, even though both lead the charge while simultaneously running small businesses.

McConville owns an eponymous garage a stone’s throw from where the proposed shelter would be built. He’s grown his business over nearly four decades from a wooden shack on Gardner to a busy hub.

Driving back to the garage after collecting the furniture on Richelieu Avenue, McConville — “a Vanier boy, for better or worse” — quiets for a moment as he considers the chance of things not going their way. Then he rejects the possibility.

“I believe we are going to win. I don’t believe anything differently,” he says. “Maybe that’s what keeps me going.”

The SOS Vanier garage sale is Sunday from 9 a.m. to 4 p.m. at Centre Pauline Charron (164 Jeanne-Mance St.).

[email protected]
twitter.com/mpearson78

https://ottawacitizen.com/news/local-new...shelter-complex-remains-strong-in-vanier
Reply With Quote
     
     
  #168  
Old Posted Aug 10, 2018, 11:59 AM
acottawa acottawa is offline
Registered User
 
Join Date: Aug 2009
Posts: 18,825
How many of these people were claiming a shelter is the "wrong model" when it was in somebody else's neighbourhood?
Reply With Quote
     
     
  #169  
Old Posted Aug 10, 2018, 12:00 PM
kwoldtimer kwoldtimer is online now
Registered User
 
Join Date: Jan 2008
Location: La vraie capitale
Posts: 26,161
$200,000 for an OMB appeal?
Reply With Quote
     
     
  #170  
Old Posted Jan 14, 2019, 6:52 PM
waterloowarrior's Avatar
waterloowarrior waterloowarrior is offline
National Capital Region
 
Join Date: Nov 2005
Location: Eastern Ontario
Posts: 9,254
@dobsondrew
14m14 minutes ago
https://twitter.com/dobsondrew/status/1084880930521710593

The OMB will hear the appeal of the @ottawacity changes to the official plan allowing for a @Salvation_Army 350 bed mega shelter on Vanier’s traditional Main Street. The 13 day hearing will be held Oct. 15th - 18th, Oct. 21st - 25th and Nov. 5th to 8th. #sosvanier @SOSVanier

here's a December 21, 2018 LPAT decision relating to a previous motion.

http://www.omb.gov.on.ca/e-decisions/pl180060-Dec-21-2018.pdf
Reply With Quote
     
     
  #171  
Old Posted Jan 15, 2019, 2:30 AM
waterloowarrior's Avatar
waterloowarrior waterloowarrior is offline
National Capital Region
 
Join Date: Nov 2005
Location: Eastern Ontario
Posts: 9,254
This is an interesting case for planning wonks, since the OPA was adopted during the Bill 139 (new appeals process) transition period, but the Zoning Amendment wasn't passed until after Bill 139 came into effect. Post-Bill 139 LPAT appeals are supposed to be prioritized under new timing standards, but in this case the zoning has to wait until the OPA is heard under the old rules.


@dobsondrew
7h7 hours ago
https://twitter.com/dobsondrew/status/1084891958416470018
LPAT - Zoning appeal of the @Salvation_Army 350 bed mega shelter has been postponed (frozen) for now. The time table of the LPAT appeal will be determined on Feb 11th. Probably a fast tracked LPAT appeal heard after the OMB - official plan case has been adjudicated. #sosvanier
Reply With Quote
     
     
  #172  
Old Posted Jun 12, 2019, 11:36 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,540
SOS Vanier wants new council to vote on the Salvation Army's plan in light of ownership questions

Jon Willing, Ottawa Citizen
Updated: June 12, 2019




The community group fighting the Salvation Army and the City of Ottawa over the location of a shelter and social services complex in Vanier says city council should take a new vote on the issue because of a land-use technicality.

According to SOS Vanier leader Drew Dobson, many councillors went into a November 2017 vote on the Salvation Army’s proposal to build at 333 Montreal Rd. were concerned about refusing the charity’s development application. Dobson said councillors with whom he spoke brought it up as a concern, worried the Salvation Army would be saddled with land, but not the project-dependent zoning.

However, Dobson’s group says ownership of the property hasn’t changed since the application first arrived at city hall.

Council last term voted 16-7 to allow the necessary rezoning and official plan amendments for the Salvation Army project.

The current council took office on Dec. 1, 2018. An appeal of council’s decision on the land-use change is scheduled for a multi-day hearing at the Land Planning Appeal Tribunal (formerly the Ontario Municipal Board) in the fall.

During the pre-hearings, project opponents learned that the Salvation Army has an agreement of purchase and sale for the land, but the charity hasn’t made available the record. The opponents last fall asked the LPAT to rule if the Salvation Army needs to produce the documentation. LPAT hasn’t yet released a decision on that issue.

The report to council in 2017 listed the owner as the Governing Council of the Salvation Army in Canada. The land registry still identifies a numbered company as the owner of the main parcel of land where the Concorde Motel is.

Asking this council to weigh in on an explosive planning file — one that’s in the middle of an appeal process — could be a long-shot, considering it’s been one of the most controversial land development cases in Ottawa.

The Salvation Army wants to relocate its operations from the ByWard Market to a new purpose-built facility on Montreal Road. SOS Vanier has been fighting the project.

Dobson said the current council should listen to the community’s concerns about locating a large homeless shelter on the main street.

“I guess this is an opportunity for council to right what we view is a wrong,” Dobson said.

Glenn Van Gulik, the Salvation Army’s spokesman, couldn’t be reached for comment by phone or email on Tuesday.

Michael Polowin, the lawyer representing the project opponents, said council should vote on the land-use in light of questions about the Salvation Army’s acquisition status of the Vanier property.

Polowin said Salvation Army “misled” the city in suggesting it owned the property.

“I’ve done enough work for charitable institutions to know that there is a different point of view taken by members of council when they believe that there’s an investment by an important charitable institution in land that will come to nothing if they don’t get what they’re asking for,” Polowin said.

“If you remember the vote, it was relatively close. All that would have to happen is a shift of a couple of votes and this rezoning and the official plan amendment never happens.”

Polowin said opponents learned the agreement of purchase has amendments and drafts, suggesting the agreement has been “in flux” and raising questions about the Salvation Army’s rights to the land.

According to Polowin, council could repeal the bylaws that changed the land-use rules for the Montreal Road property and put an end to the LPAT appeal.

[email protected]
twitter.com/JonathanWilling

https://ottawacitizen.com/news/local-new...mys-plan-in-light-of-ownership-questions
Reply With Quote
     
     
  #173  
Old Posted Jun 21, 2019, 2:34 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,540
Salvation Army denies misleading council over shelter
Charity sets out to correct 'misinformation' over ownership of Montreal Road site

CBC News
Posted: Jun 19, 2019 1:21 PM ET | Last Updated: June 20


The Salvation Army says it's been entirely transparent with Ottawa city councillors about who owns the Montreal Road property where it wants to build a 350-bed facility.

The previous council approved the charity's plan for 333 Montreal Rd. in November 2017. It includes a 140-bed emergency shelter, an emergency medical clinic and space for other programming aimed at vulnerable clients.

Last week, Coun. Mathieu Fleury urged his colleagues on the current council to reverse that decision, citing the recent discovery that the Salvation Army didn't actually own the property when the application was approved.

Fleury argues the previous council made its decision without having all the facts. The current council, which has five new members, could reverse the decision with a simple majority vote.

Last week, a Salvation Army spokesperson acknowledged the "oversight," but said the documents indicated there was a conditional offer to buy the property pending rezoning approval.

The rezoning is now on hold while the province's Local Planning Appeal Tribunal (LPAT) hears an appeal from community members.

On Wednesday, the Salvation Army issued an open letter to "address a number of accusations … and misinformation presented by Coun. Fleury and reported by Ottawa media."

Spokesperson Glenn van Gulik said Fleury was told at a public planning meeting that the Salvation Army doesn't own the site, but has made a "firm conditional offer."

He said a staff report to the planning committee was updated to reflect the conditional purchase.

"Planning Committee, City Council and the public had the clear facts," van Gulik wrote, calling the Montreal Road facility "an important place of hope and transformation" that will provide health care, education, jobs and shelter to vulnerable citizens.

Opponents who prefer to focus on permanent housing say the proposed facility is the wrong service model in the wrong location.

Fleury's motion is expected to be discussed June 26.

https://www.cbc.ca/news/canada/ottawa/salvation-army-vanier-letter-vote-1.5181408
Reply With Quote
     
     
  #174  
Old Posted Jun 21, 2019, 11:01 PM
waterloowarrior's Avatar
waterloowarrior waterloowarrior is offline
National Capital Region
 
Join Date: Nov 2005
Location: Eastern Ontario
Posts: 9,254
13 day hearing scheduled for Oct/Nov 2019 for the OPA.
http://www.omb.gov.on.ca/e-decisions/pl180060-Mar-15-2019.pdf

Here is the motion. Not sure why the ownership matters, as the Planning Act regulations do not require the owner's authorization for OPAs and ZBLAs and zoning is based on use not ownership (properties can be flipped at any time)

Quote:

MOTION

Moved by Councillor M. Fleury
Seconded by Councillor R. King

WHEREAS on November 22 2017, City Council approved an Official Plan Amendment to permit development of a shelter, residential care facility and surface parking by the Salvation Army at 325, 327 and 333 Montreal Road, 334 Montfort Street and 273 Ste. Anne Avenue; and

WHEREAS on August 29, 2018, City Council approved a zoning amendment to permit development of a shelter and residential care facility at 325, 327, and 333 Montreal Road, 334 Montfort Street and 273 Ste. Anne Avenue; and

WHEREAS at that time the Salvation Army signed a declaration that it was “the owner of” the Montreal Road properties proposed for development; and

WHEREAS the Salvation Army is not the owner of the property but is only a prospective purchaser under a signed Agreement of Purchase and Sale (APS) for the Montreal Road properties and the Ward Councillor has been advised that the Agreement of Purchase and Sale is currently being renegotiated; and

WHEREAS the Salvation Army has refused to produce a copy of the Agreement of Purchase and Sale to give evidence of its right to purchase, and in fact has engaged in substantial litigation to prevent that production; and

WHEREAS the Salvation Army may not gain the right to purchase the property in question;

THEREFORE BE IT RESOLVED THAT By-law No. 2017-413 and By-law No. 2018-301 be repealed.
Reply With Quote
     
     
  #175  
Old Posted Jun 25, 2019, 11:42 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,540
Council decision on Salvation Army shelter has potential to be closer, but votes still favour the charity

Jon Willing, Ottawa Citizen
Updated: June 25, 2019


Opponents hoping to reverse a council decision on the Salvation Army shelter project in Vanier are facing an uphill battle at city hall.

But, judging by the answers to a municipal election questionnaire last year, the vote Wednesday has the potential to be closer than the 2017 council decision on project.

Coun. Mathieu Fleury will ask council to repeal the zoning and official plan amendments that would allow the Salvation Army to build the shelter and social services complex at 333 Montreal Rd.

The Salvation Army wants to construct a multi-service facility that replaces the aging Booth Centre building in the ByWard Market. Much of the controversy involves the 801-square-metre shelter component of the 6,159-square-metre complex.

In the 16-7 vote on Nov. 22, 2017, the current council members who supported the rezoning and official plan amendments were: Jim Watson, Eli El-Chantiry, George Darouze, Jan Harder, Jean Cloutier, Keith Egli, Scott Moffatt, Stephen Blais, Allan Hubley and Tim Tierney.

Returning councillors who voted against the Salvation Army project were: Riley Brockington, Diane Deans, Catherine McKenney, Jeff Leiper and Fleury.

Coun. Rick Chiarelli declared a conflict of interest because his daughter at the time worked at the Shepherds of Good Hope, which is in the same funding category as the Salvation Army.

The October 2018 municipal election and April 2019 byelection changed the makeup of council, with eight new faces around the table.

One of the questions on a survey from this newspaper to election candidates asked if they thought council made the right decision on the Salvation Army’s development application.

The responses reveal that some new councillors were skeptical of council’s decision.

Councillors Matthew Luloff of Orléans ward, Glen Gower of Stittsville, Theresa Kavanagh of Bay and Shawn Menard of Capital expressed explicit concern.

Luloff said in his response that the “decision is unhelpful and overburdens a single neighbourhood instead of taking a multifaceted approach to ending homelessness,” and Gower decried building a “mega shelter” that doesn’t contribute to Vanier’s revitalization. Kavanagh said she believed the scale of the project is too large for the community.

The viewpoints of those three councillors in particular don’t align with the votes cast in 2017 by the former councillors of those wards.

Other new councillors, like Jenna Sudds in Kanata North and Carol Anne Meehan in Gloucster-South Nepean, expressed concern in their questionnaire responses about the project consultation, but didn’t outright indicate their support or opposition of council’s decision.

In her questionnaire response, Innes Coun. Laura Dudas said she thought council made the right decision.

There was no similar questionnaire for the Rideau-Rockcliffe byelection, but Coun. Rawlson King is seconding Fleury’s motion to repeal the zoning and official plan amendments.

As for Chiarelli, he indicated he’s no longer in a perceived conflict of interest, making him eligible to vote. He hasn’t made a final decision, but at last check he was leaning in opposition to Fleury’s motion.

According to the published council agenda, two councillors have indicated to the clerk’s office that they’ll be away for Wednesday’s council meeting: Cloutier and Gower.

Meanwhile, the legal wrangling continues ahead of the Wednesday council meeting.

City clerk and solicitor Rick O’Connor has warned council that repealing the zoning and official plan amendments could result in costs to the city if the Salvation Army asks the Local Planning Appeal Tribunal to weigh in.

On Monday, an outside lawyer, Michael Polowin, provided an opinion to Fleury saying such an appeal by the charity would be “entirely without legal merit.”

Opponents represented by Polowin are already appealing council’s 2017 decision at the tribunal. Hearing dates are scheduled in the fall.

[email protected]
twitter.com/JonathanWilling

https://ottawacitizen.com/news/local-new...loser-but-votes-still-favour-the-charity
Reply With Quote
     
     
  #176  
Old Posted Jun 25, 2019, 11:42 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,540
Salvation Army open to changing controversial shelter project
Community consultation comes 2 days before project goes before city council again

Kate Porter · CBC
Posted: Jun 25, 2019 4:00 AM ET | Last Updated: 3 hours ago


The Salvation Army now says it is open to changing the size of the controversial shelter it wants to build on Vanier's main commercial strip, but critics question the timing and sincerity of the charity's latest overture, just days before a crucial Ottawa city council debate.

The charity held a closed meeting Monday afternoon for representatives from Vanier's business and community associations, social service agencies and city housing staff, two days before Vanier Coun. Mathieu Fleury is to put the project to a vote with a new city council.

Spokesperson Glenn van Gulik said Monday's meeting was to "bounce ideas" off community groups, just as the Salvation Army had promised to do during when city council approved its zoning a year and a half ago after heated debate that lasted days.

The proposed facility at 333 Montreal Rd. was to have 350 beds, including 140 for emergency shelter, but critics argued the model was wrong and should focus on housing people permanently.
Since the zoning was approved, the housing landscape has changed in Ottawa, van Gulik explained, and the charity might look at introducing supportive housing as it has in Halifax and Vancouver.

It might also look at whether units should be open to women and children, as well as the men they traditionally serve.

Asked if the community meeting had anything to do with the council debate Wednesday, spokesperson Glenn van Gulik said, "Absolutely not."

He pointed out the Salvation Army sent its invitations on May 31, and was surprised when Fleury signalled a couple of weeks later he would try to get the new council to repeal the zoning.

Van Gulik promised to have "something tangible that we can make some commitments on to adjust the project" within 24 to 48 hours of Monday's meeting.

"It sure felt like a PR exercise at times," said Drew Dobson, founder of SOS Vanier, a group that marshalled opposition to the shelter in 2017.

Dobson is also one of a handful of Vanier business owners who have appealed city council's decision to the Local Planning Appeal Tribunal, or LPAT.
Because of that appeal, the shelter's zoning remains in limbo awaiting a hearing scheduled this fall.

Coming out of Monday's meeting, Dobson said the Salvation Army appeared open to making significant changes, and said he urged them to withdraw their zoning application. Van Gulik said the Salvation Army will not.

"If they're not serious about building a 350-bed mega shelter, then why are we all going to the [LPAT] and why are we fighting? They should withdraw their proposal, go back to the drawing board and put a new proposal on the table," Dobson said.

Until then, the two sides remain adversaries, Dobson said.

Fleury attended Monday's session as well, but would only say the meeting felt like a distraction and that he was focused on Wednesday's council meeting.

Fleury hopes a new council will repeal the zoning approved last term in a 16-7 vote.

Last term, current councillors Riley Brockington, Diane Deans, Jeff Leiper and Catherine McKenney joined Fleury in voting against it. New councillors Rawlson King and Theresa Kavanagh have also told CBC News they intend to support Fleury. He needs a majority vote of the 24-member council to overturn the zoning.

Fleury had argued council should reverse the decision because of what he said was the recent discovery that the Salvation Army didn't actually own the property when the application was approved.

In a memo sent Friday to the mayor and city councillors, the city solicitor said the shelter zoning applies only to the Salvation Army, and if that purchase doesn't go through, no other operator could run a shelter in its place.

https://www.cbc.ca/news/canada/ottawa/salvation-army-community-meeting-june-2019-1.5187805
Reply With Quote
     
     
  #177  
Old Posted Jun 25, 2019, 4:02 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,637
Now that they were busted for lying on their application, they want to work with the community two-three years later?
Reply With Quote
     
     
  #178  
Old Posted Jun 25, 2019, 9:10 PM
kwoldtimer kwoldtimer is online now
Registered User
 
Join Date: Jan 2008
Location: La vraie capitale
Posts: 26,161
The revised proposal apparently keeps addiction services downtown, reduces the emergency shelter by 40 to 70 beds, and adds supportive housing for women and children.
Reply With Quote
     
     
  #179  
Old Posted Jun 25, 2019, 10:05 PM
phil235's Avatar
phil235 phil235 is offline
Registered User
 
Join Date: Sep 2006
Location: Ottawa
Posts: 4,565
Quote:
Originally Posted by kwoldtimer View Post
The revised proposal apparently keeps addiction services downtown, reduces the emergency shelter by 40 to 70 beds, and adds supportive housing for women and children.
Wasn't part of the point to move some of the addiction services out of the cluster in the Market?
Reply With Quote
     
     
  #180  
Old Posted Jun 26, 2019, 2:08 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,540
Salvation Army reducing number of shelter beds in Vanier project as council considers repeal Wednesday

Jon Willing, Ottawa Citizen
Updated: June 25, 2019


The Salvation Army says it will reduce the number of emergency shelter beds planned for its controversial Vanier project and provide supportive housing for men and women.

The announcement on Tuesday came a day before Rideau-Vanier Coun. Mathieu Fleury asks city council to repeal the 2017 zoning and official plan amendments that allow the Salvation Army to build its facility on Montreal Road.

The Salvation Army said last week it would be willing to quickly “adjust” the project after hearing feedback from stakeholders at a meeting on Monday. The charity released its plan to tweak the project early Tuesday afternoon.

SOS Vanier leader Drew Dobson said he’s disappointed that the Salvation Army is still keeping the emergency shelter as part of the complex, especially after he felt a modicum of hope during the Monday meeting that the charity would make a major change to the development.

“It’s just an exercise in public relations,” Dobson said. “We’re not willing to concede a shelter belongs on a main street.”

The Salvation Army says it will make changes in three areas: the emergency shelter, supportive housing and the addictions program.

Where the charity was planning to have 140 emergency shelter beds for men in a new complex at 333 Montreal Rd., it now says there will be 70-100 beds “to fall within best practices.”

There would be a new supportive housing component to the development, one that sees the Salvation Army partner with a provider to help a wide range of clients, including men, women, families, seniors and military veterans.

The charity was planning a 50-bed addictions rehabilitation program for men in the new facility. Now, it will keep the addictions program in existing leased space on George Street in the ByWard Market.

Salvation Army spokesman Glenn van Gulik said the charity made the changes after listening to feedback from the community.

“It became very clear that moving forward with some updates to this plan was the right thing to do,” van Gulik said.

Van Gulik said the changes could impact the size of the facility, since the Salvation Army is reducing the number of shelter and rehabilitation beds.

However, the supportive housing component would involve apartment-style lodging.

Van Gulik said the Salvation Army’s architects and planners will work on the design tweaks over the coming months.

The changes won’t require further land-use amendments from council, he said.

As for the emergency shelter, van Gulik said there’s a need in the city for the beds.

“I think there’s a significant commitment moving forward to reducing the size of that,” van Gulik said.

Council voted 16-7 in November 2017 to approve the Salvation Army’s development application for the Montreal Road property, currently home to the Concorde Motel. The charity has a conditional offer to purchase the property, as long as the zoning and official plan rules for the site are amended and upheld.

SOS Vanier supporters are challenging council’s decision at the Local Planning Appeal Tribunal.

“We’re more determined than ever to oppose this,” Dobson said.

[email protected]
twitter.com/JonathanWilling

https://ottawacitizen.com/news/local-new...ct-as-council-considers-repeal-wednesday
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Downtown & Urban Ottawa
Forum Jump



Forum Jump


All times are GMT. The time now is 1:30 AM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.