It's all the added highway and road works that inflate the prices.

If they were just adding the interchange, and not reconstructing the highway. $30-$60 million would do it. This is what they are doing in Edmonton on the Yellowhead. Some widening. But otherwise the road remains as is.
Reply With Quote
     
     
  #1522  
Old Posted Mar 13, 2023, 9:29 PM
optimusREIM's Avatar
optimusREIM optimusREIM is online now
There is always a way
 
Join Date: May 2014
Location: Winnipeg
Posts: 3,263
Quote:
Originally Posted by bomberjet View Post
It's all the added highway and road works that inflate the prices.

If they were just adding the interchange, and not reconstructing the highway. $30-$60 million would do it. This is what they are doing in Edmonton on the Yellowhead. Some widening. But otherwise the road remains as is.
Yeah the issue I guess is that there are a huge number of ancillary projects that are tacked on. To be fair, it's not like all they have to do is pile up dirt and build the structure. Basically the whole south perimeter needs to be reconstructed.

If they ever get around to upgrading some of the city roads to freeways, the projects are going to be collossally expensive given that the word forethought hasn't entered the vernacular of city planners for the last century.
__________________
"Enlightened statesmen will not always be at the helm."
Federalist #10, James Madison
Reply With Quote
     
     
  #1523  
Old Posted Mar 13, 2023, 10:05 PM
esquire's Avatar
esquire esquire is offline
Registered User
 
Join Date: Oct 2001
Posts: 37,480
Quote:
Originally Posted by bomberjet View Post
Pth 1, 3, 6, 15, 52, 59.

They had already released a lot of this information in their previous investment plan. This is the previous document: https://www.gov.mb.ca/mit/myhis/pdf/2022_multi-year_highways_investment_strategy.pdf

New document page: https://www.gov.mb.ca/mit/myhis/index.html
https://www.gov.mb.ca/mit/myhis/pdf/multi-year_highways_investment_strategy.pdf

Thank you for that. Yeah, the province does like to announce things over and over again, ha.

Three of those are reasonably ambitious projects (the ones > 10 km) but the others are pretty marginal. I guess the McGillivray project packs some punch too since it's basically in an urban area.

I was a little surprised to see 15 on the list, I thought the province was prioritizing the Oakbank corridor. But personally I'd be fine with twinning 15 and calling it a day, no need for a new highway there.

I still don't get how on earth even the simplest interchanges cost so much here. There is always some crazy curveball in every situation that ends up doubling the cost, or more. PTH 100/3, whoops, we discovered a leprechaun gold mine in the way and it will cost $100 million to buy out the leprechauns, total project cost for the diamond $220 million, or something wild like that. Is there never a simple, basic $30 million diamond scenario as there is in seemingly every other province? I used this new diverging diamond interchange in Ontario last week... it opened last year and it cost a measly $55 million.
Reply With Quote
     
     
  #1524  
Old Posted Mar 13, 2023, 10:50 PM
Wpgstvsouth94 Wpgstvsouth94 is offline
Registered User
 
Join Date: Aug 2020
Posts: 432
Quote:
Originally Posted by WildCake View Post
@Biff - Looks like we have to reset our expectations that a diamond costs 30-60 million in this province. They're essentially budgeting 130-150 mil per interchange.

McGillivray would be by far the easiest to build as both Perimeter and McGillivray are being rerouted (east and south, respectively), so they can build the overpass in a field for the most part. Yet 150 million is earmarked for that project.

I hope they come in way cheaper and they can use that cash for additional Perimeter improvements.
It includes the diamond and the rail over pass in that total amount.
Reply With Quote
     
     
  #1525  
Old Posted Mar 13, 2023, 10:53 PM
thebasketballgeek's Avatar
thebasketballgeek thebasketballgeek is offline
Registered User
 
Join Date: Nov 2013
Location: Rimouski, Québec
Posts: 1,672
Quote:
Originally Posted by wags_in_the_peg View Post
almost every city in NA has a system like that, why would we decide to be different? and it's much more than 5 minutes when you consider the # of lights.

bypass around Morris is much needed as well!
Following the model of every North American city in terms of urban development is not ideal especially when that model has been a factor in our city being broke. Also, it’s really not more then 5 minutes unless one is unlucky and hits all the red lights.

I’m not saying the freeway is unnecessary, it’s just that instead of investing $100s of millions for bypasses and interchanges so that truckers can avoid the city and move around the periphery faster, why not spend that money for people living in Winnipeg travelling through the city?
Reply With Quote
     
     
  #1526  
Old Posted Mar 13, 2023, 11:41 PM
WildCake WildCake is offline
Registered User
 
Join Date: May 2016
Posts: 1,064
Quote:
Originally Posted by thebasketballgeek View Post
Following the model of every North American city in terms of urban development is not ideal especially when that model has been a factor in our city being broke. Also, it’s really not more then 5 minutes unless one is unlucky and hits all the red lights.

I’m not saying the freeway is unnecessary, it’s just that instead of investing $100s of millions for bypasses and interchanges so that truckers can avoid the city and move around the periphery faster, why not spend that money for people living in Winnipeg travelling through the city?
I would agree that the Province has not prioritized transit infrastructure (or any municipal relations) until this last year. The PCs were happy with the austerity measures - needed to some degree - at the expense of new projects.

That being said, Winnipeg has no fricken idea what it's doing with rapid transit and is content with electrifying the fleet as its major capital project. There's no finalized plan for the next extension of BRT so the Province (or the feds) is not in position to approve or deny funds. The current proposal to run BRT to Transcona is an excuse to get money to rehab the Louise bridge and is not finalized. No definite plan for the Union Station conversion. Theres just nothing ready to be funded.

It's up to the city to request funding or these kinds of things. The Province doesn't just announce "hey here's 200 mil for rapid transit, have fun". They would provide funding for a defined municipal project if there was one.

Last edited by WildCake; Mar 13, 2023 at 11:43 PM. Reason: Addition
Reply With Quote
     
     
  #1527  
Old Posted Mar 14, 2023, 3:06 AM
thebasketballgeek's Avatar
thebasketballgeek thebasketballgeek is offline
Registered User
 
Join Date: Nov 2013
Location: Rimouski, Québec
Posts: 1,672
Quote:
Originally Posted by WildCake View Post
I would agree that the Province has not prioritized transit infrastructure (or any municipal relations) until this last year. The PCs were happy with the austerity measures - needed to some degree - at the expense of new projects.

That being said, Winnipeg has no fricken idea what it's doing with rapid transit and is content with electrifying the fleet as its major capital project. There's no finalized plan for the next extension of BRT so the Province (or the feds) is not in position to approve or deny funds. The current proposal to run BRT to Transcona is an excuse to get money to rehab the Louise bridge and is not finalized. No definite plan for the Union Station conversion. There's just nothing ready to be funded.

It's up to the city to request funding or these kinds of things. The Province doesn't just announce "hey here's 200 mil for rapid transit, have fun". They would provide funding for a defined municipal project if there was one.
Well it is certainly true that the municipal government has no idea what it's doing, the Provincial Government is also based in Winnipeg and more importantly Downtown Winnipeg. With the amount of authority provincial governments hold over municipal governments they could have a lot more influence on what type of infrastructure projects are prioritized.

If the party in power had enough political will to say we need more transit immediately instead of funding highway projects then I would bet there would be a lot more pressure on the city to get the ball rolling. Of course we don't have that currently with the PC's in power, and I'm not going to get my hopes up on the NDP making this move either.

That one graph showing the St. Anne's interchange being "climate resilient" is quite hilarious though.
Reply With Quote
     
     
  #1528  
Old Posted Mar 14, 2023, 12:44 PM
Biff's Avatar
Biff Biff is offline
What could go wrong?
 
Join Date: Jun 2004
Location: Winnipeg
Posts: 9,888
Quote:
Originally Posted by WildCake View Post
@Biff - Looks like we have to reset our expectations that a diamond costs 30-60 million in this province. They're essentially budgeting 130-150 mil per interchange.

McGillivray would be by far the easiest to build as both Perimeter and McGillivray are being rerouted (east and south, respectively), so they can build the overpass in a field for the most part. Yet 150 million is earmarked for that project.

I hope they come in way cheaper and they can use that cash for additional Perimeter improvements.
The difference in the projects is, St Mary's is $135m but includes a ton of new roadwork aligning the new overpass and how it connects to St Mary's south of the Perimeter.

The $150m cost of the McGillivray interchange includes a significant portion of new roadway with the perimeter alignment moving east.

The St Anne's diamond is very straight forward and doesn't include any new roadway alignments. Everything is supposed to fit within the existing right-of-way (there needs to be a couple of property acquisitions south of the Perimeter). The Aimes Rd access road and bridgework has already been completed. The bulk of the St Anne's project price is dedicated to the rail overpass.
__________________
"But a city can be smothered by too much reverence for its past. The skyline must keep acquiring new peaks, because the day we consider it complete and untouchable is the day the city begins to die." - Justin Davidson - May 2010 Issue of New York
Reply With Quote
     
     
  #1529  
Old Posted Mar 14, 2023, 4:46 PM
bomberjet bomberjet is offline
Registered User
 
Join Date: Nov 2012
Location: Winnipeg
Posts: 16,272
The costs aren't really that outrageous for the St. Anne's/St Mary's projects. $286 million for ~7km of reconstructed PTH 100, related roadworks and the interchanges/overpass.

Not cheap but not overly expensive IMO. PTH 100 will be brand new freeway when those are done.
Reply With Quote
     
     
  #1530  
Old Posted Mar 14, 2023, 5:09 PM
esquire's Avatar
esquire esquire is offline
Registered User
 
Join Date: Oct 2001
Posts: 37,480
I wonder how much more it would have cost to have made 100 6 lanes from the South Perimeter Bridge to Lagimodiere as part of these projects?
Reply With Quote
     
     
  #1531  
Old Posted Mar 14, 2023, 6:05 PM
bomberjet bomberjet is offline
Registered User
 
Join Date: Nov 2012
Location: Winnipeg
Posts: 16,272
Adding 50% more lanes. So probably not 50%, but maybe 25% to 30% more.

The actual structure part of the work is not that expensive compared to the overall budget. It's the concrete and gravel.
Reply With Quote
     
     
  #1532  
Old Posted Mar 14, 2023, 6:34 PM
optimusREIM's Avatar
optimusREIM optimusREIM is online now
There is always a way
 
Join Date: May 2014
Location: Winnipeg
Posts: 3,263
Quote:
Originally Posted by esquire View Post
I wonder how much more it would have cost to have made 100 6 lanes from the South Perimeter Bridge to Lagimodiere as part of these projects?
That would be a great idea. I hope that there are more announcements soon. The six lanes from Lag to Kenaston would be a smart move I think. They should just commit and get it done.
__________________
"Enlightened statesmen will not always be at the helm."
Federalist #10, James Madison
Reply With Quote
     
     
  #1533  
Old Posted Mar 14, 2023, 6:58 PM
Biff's Avatar
Biff Biff is offline
What could go wrong?
 
Join Date: Jun 2004
Location: Winnipeg
Posts: 9,888
I would gladly sacrifice the 6 lanes for now for additional grade separations. The bridge over the Red River will need to be replaced (or add another bridge) which isn't in any of the near future projects (costly). Two lanes of hwy that are grade separated are much safer and more efficient than 6 lanes with lights and uncontrolled access.

I would prefer if they grade separated the whole perimeter (all new separations would be built with 6 lane capacity though) and constructed the additional lanes in the future. Focus the money on safety first.
__________________
"But a city can be smothered by too much reverence for its past. The skyline must keep acquiring new peaks, because the day we consider it complete and untouchable is the day the city begins to die." - Justin Davidson - May 2010 Issue of New York
Reply With Quote
     
     
  #1534  
Old Posted Mar 14, 2023, 7:09 PM
esquire's Avatar
esquire esquire is offline
Registered User
 
Join Date: Oct 2001
Posts: 37,480
I was thinking 6 lanes from the east end of the bridge to Lagimodiere would be a nice, easy "phase 1" to an eventual 6 laning of the busiest stretch of the south Perimeter all the way to 330. Doing the western part of that from the bridge to 330 would be more expensive because of the structures that would be impacted, i.e. the bridge over the Red River, the interchange at Pembina and the rail overpass.
Reply With Quote
     
     
  #1535  
Old Posted Mar 14, 2023, 7:51 PM
Komatiite's Avatar
Komatiite Komatiite is offline
Registered User
 
Join Date: Feb 2013
Location: Manitoba
Posts: 136
Twinning highways 59 and 52 to Mitchell (Steinbach)? Cool, but dude... not placing any bets on that happening.
Reply With Quote
     
     
  #1536  
Old Posted Mar 14, 2023, 8:04 PM
WildCake WildCake is offline
Registered User
 
Join Date: May 2016
Posts: 1,064
Quote:
Originally Posted by esquire View Post
I was thinking 6 lanes from the east end of the bridge to Lagimodiere would be a nice, easy "phase 1" to an eventual 6 laning of the busiest stretch of the south Perimeter all the way to 330. Doing the western part of that from the bridge to 330 would be more expensive because of the structures that would be impacted, i.e. the bridge over the Red River, the interchange at Pembina and the rail overpass.
The South Perimeter Study only found that 6 lanes would be needed between Kenaston and the Red river bridges (essentially the eastern tail end the of Pembina interchange ramps) for the initial phase. The Red River crossing is maintained at 4 lanes which I found surprising.

Here's an exerp from page 4:

The Initial Stage includes four lanes (two per direction) on PTH 100, except the segment between Kenaston Boulevard and the Red River, which requires additional lanes.

https://www.gov.mb.ca/mit/hpd/pth100/pdf/south_perimeter_design_study_final_report.pdf

Now they don't define initial stage/ultimate stage but the traffic volumes were forecasted to 2048, so assuming about a mid-point between 2018 and 2048 where ultimate stage designs should be used would be roughly 2033.

I think we'll be greatly surprised when there's no more stop/go clusters of traffic and flow is a lot smoother, especially with heavy trucks.
Reply With Quote
     
     
  #1537  
Old Posted Mar 14, 2023, 8:21 PM
optimusREIM's Avatar
optimusREIM optimusREIM is online now
There is always a way
 
Join Date: May 2014
Location: Winnipeg
Posts: 3,263
Quote:
Originally Posted by WildCake View Post
The South Perimeter Study only found that 6 lanes would be needed between Kenaston and the Red river bridges (essentially the eastern tail end the of Pembina interchange ramps) for the initial phase. The Red River crossing is maintained at 4 lanes which I found surprising.

Here's an exerp from page 4:

The Initial Stage includes four lanes (two per direction) on PTH 100, except the segment between Kenaston Boulevard and the Red River, which requires additional lanes.

https://www.gov.mb.ca/mit/hpd/pth100/pdf/south_perimeter_design_study_final_report.pdf

Now they don't define initial stage/ultimate stage but the traffic volumes were forecasted to 2048, so assuming about a mid-point between 2018 and 2048 where ultimate stage designs should be used would be roughly 2033.

I think we'll be greatly surprised when there's no more stop/go clusters of traffic and flow is a lot smoother, especially with heavy trucks.
"The Ultimate Stage will likely happen well in the future (the Initial Stage was designed to accommodate
forecast 2048 traffic levels) in a gradual fashion. Due to the uncertainty in when the Ultimate Stage will
occur, an implementation plan has not been developed for it as part of this study"

From the report at page 18. Looks like they intend to hobble along with the "initial stage" indefinitely...
__________________
"Enlightened statesmen will not always be at the helm."
Federalist #10, James Madison
Reply With Quote
     
     
  #1538  
Old Posted Mar 14, 2023, 9:03 PM
Hockey Hockey is offline
Registered User
 
Join Date: May 2016
Posts: 102
Quote:
Originally Posted by Biff View Post
I would gladly sacrifice the 6 lanes for now for additional grade separations. The bridge over the Red River will need to be replaced (or add another bridge) which isn't in any of the near future projects (costly). Two lanes of hwy that are grade separated are much safer and more efficient than 6 lanes with lights and uncontrolled access.

I would prefer if they grade separated the whole perimeter (all new separations would be built with 6 lane capacity though) and constructed the additional lanes in the future. Focus the money on safety first.
^^^This
Reply With Quote
     
     
  #1539  
Old Posted Mar 14, 2023, 10:02 PM
bomberjet bomberjet is offline
Registered User
 
Join Date: Nov 2012
Location: Winnipeg
Posts: 16,272
Im thinking McGillivray will be somehwere in between the initial and ultimate designs. With McGillivray itself on the shortlist for twinning, it would make sense to build the ultimate stage twin bridge design. But go with the initial stage for the rest of the roadworks.

At some point, a North Perimeter program will come online as well. They either are or were going to be in the functional design stage. They did the safety plan and pre functional plan a couple years ago now.
Reply With Quote
     
     
  #1540  
Old Posted Mar 15, 2023, 3:00 PM
CoryB CoryB is offline
Registered User
 
Join Date: Mar 2012
Posts: 6,178
Quote:
Originally Posted by WildCake View Post
The South Perimeter Study only found that 6 lanes would be needed between Kenaston and the Red river bridges (essentially the eastern tail end the of Pembina interchange ramps) for the initial phase. The Red River crossing is maintained at 4 lanes which I found surprising.
That isn't accurate. Traffic counts have shown Portage and the Perimeter to have very similar traffic counts to St Marys and traffic is actually growing in volume there. The design of that stretch shows that even 6 lanes isn't sufficient and the plan is to have roughly 8 lanes of traffic between the Assiniboine and Portage, one lane each direction being to feed into the Portage diamond and 3 lanes of through traffic on both sides. Also it isn't an immediate six lanes but starting the process to move that direction. When the Roblin overpass went through it's overhaul shortly before the pandemic it was changed from 4 lanes to six lanes although two of them are currently ghost lanes. They took out the former middle pillar for the bridge and changed the walls under the bridge to be straight retaining walls instead of the slopes most underpasses have.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Manitoba & Saskatchewan
Forum Jump



Forum Jump


All times are GMT. The time now is 7:10 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.