I was going down Hamilton today and noticed this large telescoping crane. I caught the last piece of a crane being hauled away. It was the Hamilton south crane.
It's interesting, in this pic from two weeks ago you can see that the crane they took down (just right of centre) was not directly attached to the tower.
It's interesting, in this pic from two weeks ago you can see that the crane they took down (just right of centre) was not directly attached to the tower.
I'd noticed that. I don't think any of them are/were. I'm guessing the availability of that huge welded steel frame 'podium' gave them a very secure location to fix the crane bases, and with the towers not being super-tall, the cranes were able to withstand the lifts involved without needing to be attached to the concrete frames as the towers were built. When they were installed, they were unusually tall.
I can't wait till the rest of the heritage building is scrubbed, I am looking forward to that the most. It bothers me some elevations are still covered in grime, I know they will clean it, but it always bothers me seeing it, especially because the Georgia elevation is all redone by comparison. Also really getting excited for what the retail base is going to be like inside
September 2, 2021
For the next two weeks: Level 23 floor slab on the East side of the North Tower will be formed
Level 21 floor slab of the North Tower, which is the last full floor, will be complete Curtain wall glass installation will continue on Level 15 of the North Tower
Block wall will continue on various floors throughout the South and North Tower
Drywall will continue on floors up to level 20
Exterior wall framing and glass installation will continue along Homer Street
Exterior column granite installation will continue along Hamilton Street
Façade restoration will continue along Homer Street for the next 3 months
Landscaping will continue along West Georgia Street
Painting will continue on various floors up to Level 18
Washroom floor and wall tile will continue up to Level 18 in the South Tower
Permanent power including energization of lights will be complete on the South Tower
Energization of mechanical systems will commence within the South Tower
The Hamilton Street sidewalk adjacent to the building will be closed for the duration of the project
The Hamilton Street southbound curb lane will be closed daily from 7:00 am to 8:00 pm (Monday – Saturday)
The Homer Street curb lane will be closed for the duration of the project
Noise exemption permits will be applied for all weekends and concrete pour days until further notice