City eyes $8-million expansion to gallery plan
Additional parking, space for growth proposed for facility
Read more:
http://www.thestarphoenix.com/travel/Cit...an+plan/3410874/story.html#ixzz0x3eVAlwO
The City of Saskatoon is eyeing an $8-million expansion of the Art Gallery of Saskatchewan, less than six months after releasing its plan for a $58-million downtown project.
A proposal going before city council tonight asks councillors for $510,000 to fund design fees for an architect to add a second level of underground parking, which would create 94 more parking spaces and an 800-square-metre "shell space" -- an empty space intended for future gallery use.
Architectural firms KPMB and Smith Carter begin their contract in September, and the city wants to ensure everything the gallery needs for future expansion is included in the final plan, said city special projects manager Sandi Schultz.
"It's important to build into the design now, because we won't be able to go in afterwards," Schultz said. "We want to be able to, over the long-term, meet the needs of a growing city."
Construction of the two additions could cost $8 million, preliminary estimates show. Cost approval won't be debated tonight, but an estimate will eventually come to council for approval.
If council funds the $510,000 cost of the new design work -- $210,000 for the shell space, $300,000 for the underground parking -- the money will be borrowed, as was the city's $26-million share of the project.
The gallery's budget "has no capacity to fund an expansion," the report to council said. The administration recommends borrowing $510,000 from a recreational and cultural facilities fund.
In April, city council approved the functional program plan -- the instructions for the project's architects -- for the gallery, which will form the River Landing destination centre with an expanded Remai Arts Centre.
"As we put together all of the needs, it became evident we couldn't meet all the dreams and aspirations within the existing budget," Schultz said.
"We identified the budget in advance of having a detailed functional program plan, and that's where there was a disconnect."
Once the design is done, city officials would have a more accurate cost of the expansion and could develop a funding strategy, Schultz said.
The new gallery replaces the Mendel Art Gallery. Construction is expected to start in 2012.
The original functional program plan -- which details the configuration of the gallery, who might use it and for what purpose -- included one level of underground parking.
The second level would add 94 new parking spaces in the downtown area, the report says.
The gallery expansion would add floor space on the centre's third floor, which would remain empty until the city provides more funding to bring the room up to gallery standards, the report said.