Very interesting to see such significant changes to move traffic to permanent road in the 22X area. Makes me wonder if the portion of the SW ring road that gets fully opened this year will be significantly more than Sarcee-Fish Creek Blvd section that was reported earlier. I'm not very familiar with the status of the section between Fish Creek Blvd and James McKevitt though.
|
Went through there yesterday when I went out to visit the folks outside Millarville. Not sure, if it will open earlier or not, though I suspect it might by year end.
Here are the observations:
- the at grade intersections at 6th/Sheriff King, McKevitt/Spruce Meadows and 37th have to be eliminated. What I mean, they need to separate the eastbound and westbound crossings. Would not expect this will take much effort.
- the need to get the grade and resurface done at McKevitt and 37th. Approximately the distance is 100m or so.
- westbound lanes between 53rd and 69th St, needs to be finished. The sub grade looks done.
- as Pegasus has mentioned, bridge 19 needs a bit of work (westbound overpass to 22X as Stony turns north). The work platform is still on the bridge.
- did see areas where hydroseeding was taking place, predominantly along steeper slopes.
- gantries with signs have been erected but there were some stored on the westbound lanes near McKevitt. (probably for signage for southbound McKevitt)
- between 22X and Fish Creek, signs and pavement is done, though not sure if this is the top lift.
- when I was out getting some food for the outlaws in Silverado last Thursday night, I talked with an KGL worker, mentioned to him the progress was great and asked when it was to open. He mentioned they are opening to 162nd, but I think he was mistaken as I would think payment schedules would be set by segment completion.