Construction Update
Week of December 14
Paving occurs on the Preston Street detour
Preston Street Detour / Booth Street Closure
Construction nears completion along the Preston Street detour with asphalt paving, and curb and sidewalk construction.
Waterproofing installation in the Lyon Station cavern
Lyon Station
Lyon Station cavern support continues with rebar and waterproofing installation. Jawbreaker is continuing to mine in drifts.
Parliament Station
Parliament Station cavern tunnel support continues and includes backfilling, pouring and construction of a lower level support wall.
Rideau Station cavern excavation
Rideau Station
Crocodlie Roughe continues to excavate within the Rideau Station cavern. Tunnel reinforcement is ongoing with shotcrete and rockbolt installation.
Ongoing Scotiabank building demolition on Rideau Street
Rideau Station
Preliminary works continue with abatement of the existing Scotiabank building in advance of building demolition scheduled to begin in early January 2015.
Concrete box in place at the VIA Rail tracks
Belfast Yard Administration and Maintenance Building
Ongoing long-term closure of Belfast Road, south of Tremblay Road to Trainyards Drive and north of Tremblay Road to Coventry Road. Masonry work, cladding and panel installation for the building envelope, glazing and roofing on the shed continue. Construction of the internal components and pouring of mud slabs are ongoing.
Belfast Yard Connector
Works on the Belfast Yard connector, which will allow vehicles to travel to and from the Light Rail Transit track to Belfast Yard, are ongoing. The removal of the temporary steel bridge under the VIA Rail tracks was completed.
Pouring of concrete caissons north of the existing Hurdman Station
Hurdman Station
Elevated guideway work for the future Hurdman Station is ongoing until early 2015 with caisson drilling and concrete curing north of the existing Hurdman Station.
Paving near the Coventry Pedestrian Footbridge
Highway 417
Drilling median foundations, installing electrical and light poles, and sewer works continue from Cyrville Road to Nicholas Street. Paving works conclude this week until spring at St. Laurent Boulevard and Lemieux Street, and Vanier Parkway.
Girder installation at Hurdman Bridge
Hurdman Bridge
Girder installation, part of the reconstruction of the bridge’s median span, continues and will be ongoing during the winter months. The east and west multiuse pathways are scheduled to remain open until the end of the year.
Demolition of removed Vanier Parkway overpass
Vanier Parkway Overpass
Demolition of the old Vanier Parkway overpass is almost complete at the staging area. Final works on the overpass wrap up for winter.
Electrical works continue on the Coventry Pedestrian Footbridge
Coventry Pedestrian Footbridge
Installation of railings, electrical works and concrete pours on the stairs continue on the north and south sides until the end of the year. General site cleanup is ongoing in anticipation of substantial completion of the footbridge by end of January 2015.
Sidewalk paving between Preston and Rochester streets
Albert Street Works
Complete sidewalk reinstatement on south side of Albert Street between Preston and Broad streets. Please note: Work at Booth Street north scheduled to begin January 6, 2015.
Upcoming Construction Activities
In the coming weeks, the following construction activities will advance:
- Preston Street detour to open on December 21, 2014 and works to begin on Booth Street. The detour will allow transit, commuters, pedestrians and cyclists to use Preston Street during the Booth Street closure and construction of the Combined Sewer and Storage Tunnel (CSST), the Booth Street Bridge and Pimisi Station.
- Demolition of the Scotiabank building at William and Rideau streets will begin in early January.
- Girder installation at Hurdman Bridge will continue through January/early February.
- Coventry Pedestrian Footbridge works continue.
http://www.confederationline.ca/en/construction/construction-update-4/