Quote:
Originally Posted by OldDartmouthMark
Wow... how can this happen? Aren't the drawings supposed to be finalized and checked before approval is given to start building?
|
Some of the drawings yes. Those consist of structural and architectural (why architectural in this city i have no clue, nobody seems to follow them anyway). However mechanical and electrical do not have to be. Electrical have to be submitted to NS power before any service entrance or major work is done. Mechanical i am not sure about.
However i know for a fact that electrical plans were long delayed and i am guessing that mechanical was in the same boat. You cannot finalize electrical plans all the while not knowing where said air exchanger or AC unit is positioned within the building.
There are other reasons for this delay as well that i can't really get into on here. Some of the stories i've been hearing are mind-numbing.....