Starting In November
The first construction season for the North LRT to NAIT Project is wrapping up. Now that Kingsway
has been relocated and fully opened to traffic to make space for the future Kingsway Station,
foundation work on the station can begin in earnest. Foundation construction continues at MacEwan
Station and is now beginning on the NAIT Station, a full six months ahead of schedule thanks to the
co-operation of NAIT. In addition, city contractors will be installing equipment to monitor the ground
on 99th Street in preparation for the construction of a new LRT tunnel, which will run between
Churchill Station and 105 Avenue.
There was a flurry of activity last month as city contractors worked to meet key project milestones
for the first construction season. The City makes every effort to include construction activities in
monthly updates and quarterly newsletters; however, it’s the nature of construction that plans have
to be adjusted to accommodate the unexpected, such as poor weather. The City will continue
sending out construction bulletins to ensure that any unexpected changes are communicated.
Please see below for upcoming and ongoing construction activities, as well as recent project
milestones.
Roadworks – 99 Street Periodic Partial Closures
Activity Ground monitoring installation.
Reason To prepare for the construction of a new LRT tunnel, which will be built between
Churchill Station and 105 Ave.
Impacts 99 St. – Periodic partial closures from 103A Ave. to 102A Ave.
Dates November 2011
Construction – NAIT Station
Activity NAIT Station construction.
Reason The future NAIT Station will occupy the old NAIT Parking Lot F, which has been
relocated west of 109 Street on Princess Elizabeth Ave.
Impacts Periodic access changes to NAIT Campus from Princess Elizabeth Ave.
Dates November 2011 – Fall 2012
Ongoing Utility Relocations & Roadworks
Location Work Impact Approx. End
104 Ave. Service Road/99
St.-100 St. Ground monitoring
installation Periodic partial closures. November
2011
105 Ave./102 St.-103 St. Tunnel portal
excavation Total closure. No traffic
movements. Ongoing
105 Ave./103 St.-105 St. MacEwan Station
construction Total closure. No traffic
movements. Permanent
103 St./105 Ave.-106 Ave. Drainage & power
relocation Total closure of south half. No
traffic movements. Ongoing
103 St./107 Ave.-108 Ave. Drainage
relocation Partial closure of north half. November
2011
104 St./108 Ave.-Kingsway Track slab
construction Total closure. School board/Vic
access open from 108 Ave. Permanent
105 St./107 Ave.-108 Ave. Track slab
construction Total closure. No traffic
movements. Permanent
108 Ave./west of 104 St.-
105 St. Track slab
construction Total closure. No traffic
movements. Permanent
Kingsway/104 St.-106 St. Kingsway Station
construction Possible periodic partial closures. Fall 2012
111 Ave./105 St.-Kingsway Water relocation Periodic partial closures. November
2011
106 St./111 Ave.-Princess
Elizabeth Ave. Roadworks Periodic partial closures. November
2011
106 St. Service Road/112
Ave. intersection Roadworks Total closure. No traffic
movements. September
2012
Princess Elizabeth
Ave./106 St.-109 St. Drainage relocation Periodic partial closures. November
2011
NAIT Parking Lot F Drainage relocation &
roadworks Periodic access changes. November
2011
Recent Milestones
The North LRT project achieved several milestones in October, including:
101 Street/104 Avenue-106 Avenue ground monitoring installation.
105 Avenue/101 Street-103 Street soil stabilized in preparation for tunnelling.
105 Street/107 Avenue-108 Avenue adjacent alleyway rehabilitation completed.
Access to Prince of Wales Armouries relocated several metres west on 108 Avenue.
105 Street/110 Avenue-Kingsway roadworks completed.
Kingsway/102 Street-106 Street completely opened to traffic.
North LRT construction activities will be conducted during normal business hours as consistently as