Does TBM gonna have to spend a month or two before it can continue to next station?
They are stopping here for some maintenance so it will probably be longer than at Main which was 6 weeks.
Also, they have only done the concrete slab on the eastern portion east of Yukon, between Yukon and Cambie sill needs to be done before the TBM can progress.
Quote:
Elsie, the first tunnel boring machine (TBM), will be arriving at Broadway-City Hall Station soon and will undergo regular maintenance below the traffic deck in the station area. Concurrently, Phyllis, the second TBM, will be starting her second leg of tunnelling, from Mount Pleasant Station towards Broadway-City Hall Station.
Phone through the construction fence and about 3 inches off the ground. Otherwise everything is blocked by that wall extension feature on the building.
If the second TBM matches the first and takes 47 days to reach Alberta, that means an arrival before the end of May
The first will already be tunneling to Oak street and the second, after a few weeks for refurb, will be doing the same.
The box in front of no frills is a simple lane switching box so they could start closing it up soon after the second tbm starts up again. Maybe as early as July.