Project update e-mailed today:

http://app.webtrackz.com/?q=email/view/14U6K4yY9lOgsO0T9RrdVKbuJ6oOO-H1bNOEhqv0o8OJaegBPfBkxF2w

Quote:
Traffic decks approach finish line

With the completion of the South Granville traffic deck in late summer and the Oak-VGH traffic deck just this month, crews have now finished three of five traffic decks on Broadway. The remaining two are scheduled to be complete in winter. When complete, crews work on excavating the new stations underneath while people move above ground on the traffic decks.

Broadway remains open while we work to complete the traffic decks – and for the length of the project. While the streets and sidewalks may look a bit different where the future stations are being constructed, access to residences, businesses, health services and parking lots is being maintained for all abilities. If you visit Broadway for appointments, restaurants or shopping, you can look for directional signs on site or take a look at the parking and access maps available online before you go. Please plan extra travel time, watch for wayfinding information, and obey traffic control personnel and signs at all times.

Construction forecast

Our planned construction activities for the next three months include:
  • Continue constructing the elevated guideway between VCC-Clark Station and the future Great Northern Way-Emily Carr station;
  • Assembling Phyllis, the second TBM, for a planned launch in winter. Continue removing excavated material from boring the first tunnel;
  • Building the underground portion of the future Mount Pleasant Station and excavating the Broadway-City Hall, Oak-VGH, South Granville and Arbutus stations;
  • Completing the traffic decks for the Broadway-City Hall and Arbutus stations; and,
  • Finishing the relocation of major utilities at the Broadway-City Hall and Arbutus work sites.
We understand that construction is disruptive and are working hard to minimize impacts in the community – thank you to everyone for your ongoing patience as we work to build this project as quickly as possible.

Did you know?

At 2.4 meters in diameter, the new section of the Cambie combined storm and sewer system being built by the Broadway Subway Project is big enough to stand in!

This key utility is being relocated to make room for the new escalators that will connect the Canada Line outbound platform directly to the extended Millennium Line, creating a seamless underground connection between lines for passengers. This pipe carries both sewage and storm water runoff to wastewater treatment facilities. As part of that work, the sewer is being expanded to 2.4 meters from 1.8 meters previously, which will better prepare the system for increases in population and more heavy rainfall events due to climate change.
Reply With Quote
     
     
  #1582  
Old Posted Nov 3, 2022, 12:40 AM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,650
Yeah looks like it's still a ways off before they finish



https://trafficcams.vancouver.ca/cameraimages/BroadwayWest_Cambie.jpg
Reply With Quote
     
     
  #1583  
Old Posted Nov 3, 2022, 12:42 AM
chowhou's Avatar
chowhou chowhou is offline
Registered User
 
Join Date: Sep 2019
Location: East Vancouver (No longer across the ocean!)
Posts: 3,743
Quote:
Originally Posted by officedweller View Post
I was under the impression that whenever they did major infrastructure work the CoV wanted to convert combined sewer + storm water to separate utilities. No budget/no desire here?
Reply With Quote
     
     
  #1584  
Old Posted Nov 3, 2022, 1:41 AM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,650
Quote:
Originally Posted by chowhou View Post
I was under the impression that whenever they did major infrastructure work the CoV wanted to convert combined sewer + storm water to separate utilities. No budget/no desire here?
Might just be a simplification on the terminology in the newsletter. I think it's both CoV and Metro Vancouver trying to separate them.

Quote:
In implementing the 2010 Integrated Liquid Waste and Resource Management Plan, Metro Vancouver had to develop strategies to eliminate combined sewer overflows from the Vancouver Sewerage Area by 2050. To help Metro Vancouver achieve this goal, McElhanney completed numerous combined trunk sewer separations strategies over the past seven years, including the Glenbrook Trunk Sewer Separation Study (2013-2014), the Hastings-Cassiar Combined Trunk Sewer Separation (2015-2016), the Manitoba Street Combined Trunk Sewer Separation Strategy, (2016-2017), the Cambie Street & Canoe Creek Combined Trunk Sewer Separation (2018-2019) and the Manitoba Street Catchment Overland Flow and Green Infrastructure Assessment (2019 – 2020).
https://www.mcelhanney.com/project/metro-van-combined-trunk-sewer-separation/

Quote:
A little more than 2,100 kilometres of sewer pipe run through underground Vancouver, an infrastructure network valued at $6-billion. Almost 55 per cent has been upgraded to separated pipes for sewer and rain water.

In 2019, engineering reported that it had managed to replace 4.1 kilometres of sewer mains for $26.7-million. In 2018, it was 5.4 kilometres for $22.7-million. In 2017, only 4.6 kilometres were completed for $31.5-million, somewhat less than the 5.8 kilometres planned that year. In 2016, it was 7.5 kilometres for $37.9-million, 2.5 kilometres less than planned because “trunk size, arterial street and co-ordinated projects with higher unit rates resulted in higher expenditures per kilometre.” At those rates, the city is not on track to have its system completely separated by 2050, which the province has mandated it must.
https://www.theglobeandmail.com/canada/b...er-housing-leaves-infrastructure-behind/
Reply With Quote
     
     
  #1585  
Old Posted Nov 3, 2022, 3:09 AM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,622
Quote:
Originally Posted by chowhou View Post
I was under the impression that whenever they did major infrastructure work the CoV wanted to convert combined sewer + storm water to separate utilities. No budget/no desire here?
Yeah, I thought so too...
Reply With Quote
     
     
  #1586  
Old Posted Nov 3, 2022, 3:25 AM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,160
This is a sewer main (or trunk), it's going to be combined until everything feeding it is separated.
Reply With Quote
     
     
  #1587  
Old Posted Nov 3, 2022, 4:08 AM
chowhou's Avatar
chowhou chowhou is offline
Registered User
 
Join Date: Sep 2019
Location: East Vancouver (No longer across the ocean!)
Posts: 3,743
Quote:
Originally Posted by madog222 View Post
This is a sewer main (or trunk), it's going to be combined until everything feeding it is separated.
Hm I still don't see why they wouldn't put in a non-functional but ready-to-go stormwater main while the ground is ripped up.
Reply With Quote
     
     
  #1588  
Old Posted Nov 3, 2022, 4:58 AM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,650
This Broadway Plan document has a lot of information about the current state of the sewage/storm trunks around page 104

Quote:
The watersheds are serviced by both separate sanitary and storm sewers as well as combined sewers, which carry both stormwater and sanitary flows. Relative to some other locations in the city, there is a substantial number of separated sewers in the Broadway Plan area (approximately 67%), although there are still significant clusters of local combined pipes and many of the trunks are still combined. The regional Metro Vancouver interceptor system (which conveys flows from Burnaby and Vancouver to Iona Wastewater Treatment Plant) is also a combined system in the Broadway Plan
area.
Sewer separation in the area has occurred through renewal-based programs and
development, as well as through targeted separation in areas that historically contributed CSO to False Creek. Improved water quality in False Creek and the associated beaches has long been an objective in the planning and upgrading of the Vancouver sewer systems. Combined sewer overflow elimination by 2050 is also a requirement of the Integrated Liquid Waste and Resource Management Plan (2011). In recent years, council has passed motions asking staff to explore options to accelerate CSO elimination and to target continuous improvements over time. The planning in Broadway supports this objective while the city-wide Healthy Waters Plan is under development.
https://council.vancouver.ca/20220518/documents/pspc1REVISED.pdf
Reply With Quote
     
     
  #1589  
Old Posted Nov 3, 2022, 6:55 AM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,650
Mt Pleasant and & Oak stations

Video Link


Video Link
Reply With Quote
     
     
  #1590  
Old Posted Nov 3, 2022, 4:09 PM
WarrenC12's Avatar
WarrenC12 WarrenC12 is offline
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,608
Crews were out drilling at Broadway and Heather the other day, and they've put a temporary plate on the hole. I wonder what they are looking for?
Reply With Quote
     
     
  #1591  
Old Posted Nov 3, 2022, 4:14 PM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,650
Quote:
Originally Posted by WarrenC12 View Post
Crews were out drilling at Broadway and Heather the other day, and they've put a temporary plate on the hole. I wonder what they are looking for?
Quote:
Geotechnical investigations on W. Broadway at Heather and Burrard streets beginning on October 31 (click to view detailed notice)

BSPC will be conducting geotechnical investigations to collect information that will inform planning for tunnel construction.
Work will take place for about one week from 10 a.m. to 3 p.m. on W. Broadway at Heather Street beginning October 31. Work will commence at Burrard Street beginning on November 3.
Work activities will include removal of asphalt, excavation using a hydrovac truck, placing of road plates, installation of sensor equipment, and repaving the areas.
The #99 B-Line eastbound bus stop at Heather Street will move from the west side to the east side of Heather Street from October 31 for up to one week.
https://www.broadwaysubway.ca/construction/current-work/
Reply With Quote
     
     
  #1592  
Old Posted Nov 3, 2022, 5:20 PM
scottN scottN is offline
Registered User
 
Join Date: Mar 2019
Posts: 286
Quote:
Originally Posted by jollyburger View Post
This Broadway Plan document has a lot of information about the current state of the sewage/storm trunks around page 104



https://council.vancouver.ca/20220518/documents/pspc1REVISED.pdf
You can see the full sewer network on Vanmap. The stormwater sewers don't necessarily follow the same routes as the sanitary sewers. For instance Mt. Pleasant industrial area storm sewers go into false creek near the Olympic Village, while the sanitary sewers are pumped up Yukon Street into the 8th avenue interceptor that goes to Iona.
Reply With Quote
     
     
  #1593  
Old Posted Nov 3, 2022, 10:03 PM
Dave2 Dave2 is offline
Registered User
 
Join Date: Dec 2007
Posts: 542
Quote:
Originally Posted by WarrenC12 View Post
Crews were out drilling at Broadway and Heather the other day, and they've put a temporary plate on the hole. I wonder what they are looking for?
I wonder if it has anything to do with the underground creek at that location.

Four photos from a flood in 1909

https://www.reddit.com/r/vancouver/comme...r_street_creek_overflowing_ninth_avenue/
Reply With Quote
     
     
  #1594  
Old Posted Nov 3, 2022, 10:14 PM
WarrenC12's Avatar
WarrenC12 WarrenC12 is offline
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,608
Quote:
Originally Posted by Dave2 View Post
I wonder if it has anything to do with the underground creek at that location.

Four photos from a flood in 1909

https://www.reddit.com/r/vancouver/comme...r_street_creek_overflowing_ninth_avenue/
Wow great find, and probably.
Reply With Quote
     
     
  #1595  
Old Posted Nov 4, 2022, 12:34 AM
Tvisforme's Avatar
Tvisforme Tvisforme is offline
Registered User
 
Join Date: Sep 2014
Location: Metro Vancouver
Posts: 2,150
Quote:
Originally Posted by Dave2 View Post
I wonder if it has anything to do with the underground creek at that location.

Four photos from a flood in 1909

https://www.reddit.com/r/vancouver/comme...r_street_creek_overflowing_ninth_avenue/
It's not an issue, it's a feature for the extension:

Reply With Quote
     
     
  #1596  
Old Posted Nov 4, 2022, 12:45 AM
Migrant_Coconut's Avatar
Migrant_Coconut Migrant_Coconut is offline
Registered User
 
Join Date: Oct 2015
Location: Kitsilano/Fairview
Posts: 10,126
Would it be possible to rewild Heather once the subway's done? After the last week or so, methinks we could use all the flood control we can get.
Reply With Quote
     
     
  #1597  
Old Posted Nov 4, 2022, 1:28 AM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,160
Quote:
Originally Posted by Migrant_Coconut View Post
Would it be possible to rewild Heather once the subway's done? After the last week or so, methinks we could use all the flood control we can get.
Yes! Here is a long term vision for this throughout the city from the Vancouver Plan.

https://vancouverplan.ca/ (PDF page 54)
Reply With Quote
     
     
  #1598  
Old Posted Nov 4, 2022, 2:10 AM
chowhou's Avatar
chowhou chowhou is offline
Registered User
 
Join Date: Sep 2019
Location: East Vancouver (No longer across the ocean!)
Posts: 3,743
Quote:
Originally Posted by madog222 View Post
Yes! Here is a long term vision for this throughout the city from the Vancouver Plan.
Not sure if it makes a lot of sense to designate the False Creek Flats an ecologically sensitive area?

Reply With Quote
     
     
  #1599  
Old Posted Nov 4, 2022, 3:18 AM
swimmer_spe swimmer_spe is offline
BANNED
 
Join Date: Apr 2014
Posts: 10,743
Quote:
Originally Posted by chowhou View Post
Not sure if it makes a lot of sense to designate the False Creek Flats an ecologically sensitive area?

You could label it that which would mean that industry like that likely would move away as more regulations would shut them down.
Reply With Quote
     
     
  #1600  
Old Posted Nov 4, 2022, 4:34 AM
Changing City's Avatar
Changing City Changing City is online now
Registered User
 
Join Date: Nov 2016
Posts: 8,187
Quote:
Originally Posted by swimmer_spe View Post
You could label it that which would mean that industry like that likely would move away as more regulations would shut them down.
We're way off topic ... and, as you can read, that's a mini-storage warehouse and an artists studios. Only the tanker in the sidings might pose any sort of potential risk to an ecolgically sensitive zone, which would presumably only be viable if the railyards weren't there (which is not the current expectation).
__________________
Contemporary Vancouver development blog, https://changingcitybook.wordpress.com/ Then and now Vancouver blog https://changingvancouver.wordpress.com/
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 5:42 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.