T&T article regarding the
ASEC, based on the public presentation the other evening:
https://tj.news/times-and-transcript/102002155 (paywall)
A few renderings were included in the article:
Interior atrium featuring the whale skeleton hanging from the rafters
Panoramic rendering as seen from the NW
Exterior rendering of the northern part of the front of the building
Although listed as a $700M project, the actual building itself will cost $300M (still 2.5x the cost of the Avenir Centre).
Initial site prep starts "before the end of the year" and will focus on realigning roadways around the site. Major construction will begin next year.
Final building design is not expected to be completed until next summer, when final tenders are issued.
Construction will occur in three phases:
- Phase one is site prep, starting this fall.
- Phase two is construction of the annex to the north of the current building, and this will start next summer.
- Phase three will be deconstruction of the current Gulf Fisheries Centre, and it's replacement with the remainder of the science complex, and restoration of the original facade. This will begin in 2027. This phase will continue until completion in 2031.