- Form walls in place for the 2 elevators perpendicular to the eastern most 4 elevator bank.
- Polyguard and rubber type membrane applied to elevator exterior walls and mat floor. Gravel backfill as they go.
- 2nd tier of floor poured in the SE pit. Is this space for stormwater retention?
- Large floor drain and black tank placed in dug out area which will be the loading dock (east of crane 2). Lots of piping being worked.
- More electrical conduit buried with special 90 degree pre-made rigs bringing the conduit above grade
- Delivery of 2 section black tanks (bottom left of picture)
- More columns being prepared and poured including a large one just north of crane 2 on top of the pier I had named Yoko.
- Truss structures with a floor that exactly fit inside the 4 elevator cores lowered into at least 3 of the cores. I assume these will be part of the rising form structure as they climb.