Awe-inspiring for some, irritating for others, Queensway bridge replacement is the first of five
Rochester Street comes next, followed by the bridges at Percy Street, Bronson Avenue, Preston Street

Taylor Blewett, Ottawa Citizen
Aug 13, 2022 • 2 minutes ago • 2 minute read




Awe may not have been everyone’s reaction to the construction feat that required a nearly four-day Queensway closure, but for some Ottawans, there’s no entertainment quite like the complete replacement of a hulking highway bridge.

“It’s not like every day you see an overpass being taken out and … a new one (put) in there,” said 10-year-old Jenson, whose mom preferred not to provide last names. Unfortunately, he and all others who stopped by the construction site Saturday afternoon had missed the most dramatic part of the spectacle — the demolition of the old bridge, and insertion of the new one, moved from a staging area by self-propelled modular transporters. Still, “cool” is how Jenson characterized it.

For his mom May, the appeal is “really to see humans are so small in the universe but able to create, like big things. That’s what’s amazing, it amazes me.”

It wasn’t Bob Birnbaum’s first taste of construction entertainment. He’s had a daily view of the construction of an apartment building across the street from his own. “And that’s fascinating,” he said. “It started with watching them build the crane, which – I’ve never seen a crane built. And just to watch how they build the crane with another crane, and then the guys are walking out there … It was really quite something. It’s been great fun.”

A retired physician, he’d paused his Saturday afternoon bike ride at a public viewing area set up for the bridge swap.

“They told me when I did aptitude tests not to go anywhere near engineering. So that’s why I find this fascinating. I have no idea what they’re doing.”

Painting contractor Dan Joly stopped by on his way home from a job, hoping to see the installation of the bridge he’s watched under construction in its nearby staging area. He’s always been a fan of large machinery, and “I’m in awe of how they can do it so quickly and have it stable in time for traffic,” he said. “I’m really sorry I missed the move though, holy 🞵🞵🞵🞵.”

There’s something sufficiently riveting about highway bridgework that for previous projects, the MTO set up bleachers. In addition to the designated public viewing area just north of the bridge on Booth Street, a livestream of the weekend’s project was also available online.

For those who didn’t get a chance to see the action – or those eagerly anticipating its conclusion – take note that it’s the first of a series of 417 highway rigid-bridge replacements, using the rapid replacement method and full 82-hour highway closures.

Rochester Street comes next (date TBD, according to the project website) followed by the bridges at Percy Street and Bronson Avenue next summer – “I won’t miss that one,” said Joly – and at Preston Street in July 2024.

Closed in both directions between Metcalfe Street and Kirkwood Avenue since 8 p.m. Thursday, Highway 417 is slated to reopen Monday at 6 a.m.

https://ottawacitizen.com/news/local-new...-bridge-replacement-is-the-first-of-five
Reply With Quote
     
     
  #1322  
Old Posted Aug 15, 2022, 3:33 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,689
Sunday @ 11:31pm. Practically done:

Reply With Quote
     
     
  #1323  
Old Posted Aug 15, 2022, 10:05 PM
cityguy's Avatar
cityguy cityguy is offline
Registered User
 
Join Date: Jun 2005
Location: Windsor
Posts: 756
Have they started the extension of the 417 to Renfrew yet?
Reply With Quote
     
     
  #1324  
Old Posted Aug 26, 2022, 1:39 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,689
Ottawa HWY 417 Booth St Bridge Replacement Time-lapse

• Video Link
Reply With Quote
     
     
  #1325  
Old Posted Aug 26, 2022, 5:20 PM
Mulder Mulder is offline
Registered User
 
Join Date: Mar 2013
Posts: 124
Quote:
Originally Posted by feckless View Post
AFAIK the Calabogie interchange is to be completed Dec 2023 and then the widening continues after that...
Ya, likely separate construction contracts - to slip under the $50 million so IO doesn't get involved. lol
Reply With Quote
     
     
  #1326  
Old Posted Aug 26, 2022, 6:21 PM
Innsertnamehere's Avatar
Innsertnamehere Innsertnamehere is offline
Registered User
 
Join Date: Jan 2010
Location: Hamilton
Posts: 12,891
Quote:
Originally Posted by Mulder View Post
Ya, likely separate construction contracts - to slip under the $50 million so IO doesn't get involved. lol
the cutoff for IO is far higher than that, MTO still does most of it's work through traditional contracts with only the largest programs going to IO Procurement. Probably closer to a $500 million cutoff for IO procurement.

The only MTO projects I know of going the IO route are the 401 widening in Mississauga, 413, Bradford Bypass, 417 extension, and Garden City Skyway projects. Everything else is traditional procurement.

MTO breaks contracts down often to allow smaller companies to bid and increase competition. There are only so many firms who can do $100 million + contracts.

Calabogie itself was likely split off so the province could show early progress on the project before the election. They did the same thing with the Bradford Bypass by bidding out a single bridge overpass early.
Reply With Quote
     
     
  #1327  
Old Posted Aug 26, 2022, 6:37 PM
Dengler Avenue's Avatar
Dengler Avenue Dengler Avenue is offline
Road Engineer Wannabe
 
Join Date: Sep 2017
Location: Côté Ouest de la Rivière des Outaouais
Posts: 8,683
https://skyscraperpage.com/forum/showthread.php?t=229872&page=80 #1595
Just gonna advertise my thread a bit here
__________________
My Proposal of TCH Twinning in Northern Ontario
Disclaimer: Most of it is pure pie in the sky, so there's no need to be up in the arm about it.
Reply With Quote
     
     
  #1328  
Old Posted Sep 19, 2022, 6:02 PM
Mulder Mulder is offline
Registered User
 
Join Date: Mar 2013
Posts: 124
Quote:
Originally Posted by Innsertnamehere View Post
the cutoff for IO is far higher than that, MTO still does most of it's work through traditional contracts with only the largest programs going to IO Procurement. Probably closer to a $500 million cutoff for IO procurement.
My old firm had the detailed design assignment for 3 structures along a 400 series highway.

It was originally planned as 2 separate construction contracts, 2 bridges in one contract (with grading, highway widening, etc) and 1 interchange in the second contract.

Because the contract for the 2 bridges came out to well over 50 million, MTO opted to for 2 seperate contacts to avoid consultation with IO.

Quote:
Originally Posted by Innsertnamehere View Post
MTO breaks contracts down often to allow smaller companies to bid and increase competition. There are only so many firms who can do $100 million + contracts.
Yes, this too.

Quote:
Originally Posted by Innsertnamehere View Post
Calabogie itself was likely split off so the province could show early progress on the project before the election. They did the same thing with the Bradford Bypass by bidding out a single bridge overpass early.
No, the interchange was always planned as a design/build contract with no associated widening/twinning. There was additional work /detours that need to be completed first. Locha Creek Culvert (at Miller and Anderson). And Miller is going to be reconstructed parrel of 417 twinning to calabogie. This assess has to be provided prior to opening the twinning.

Miller/Anderson will not have an interchange.
Reply With Quote
     
     
  #1329  
Old Posted Sep 26, 2022, 3:51 PM
AuxTown's Avatar
AuxTown AuxTown is offline
Registered User
 
Join Date: Apr 2006
Location: Ottawa, Canada
Posts: 4,650
417 closure, once again, this weekend for the Rochester bridge replacement. Those of you in the know, is this the final closure for this project or is there another bridge to replace still? The narrowing at Parkdale and beyond for the last couple years has resulted in significantly worse congestion coming from the west every morning and I look forward to everything being open again!
Reply With Quote
     
     
  #1330  
Old Posted Sep 26, 2022, 4:48 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,131
Not 417 related, but something to fear may one day show up in Ottawa.

Quote:
Ontario's first diverging diamond interchange opens today. Here's how it works

Ontario's first-ever diverging diamond interchange opens to drivers Monday morning, the Ministry of Transportation confirmed.

The new interchange, located at Glendale Avenue and the Queen Elizabeth Highway (QEW) in Niagara, will open to drivers on the morning of Sept. 26.

According to the Ministry of Transportation, the interchange has been installed to reduce gridlock and improve traffic flow for motorists getting on and off the QEW at Glendale Avenue.

It is supposed to accomplish this by reconfiguring traffic lanes to allow for direct access to all four directional highway ramps.

The diverging diamond interchange eliminates the need for motorists to make any left-hand turns when entering or exiting the highway by using a series of interconnected crossover lanes controlled by traffic lights and highway signage.

"A diverging diamond interchange provides easier access and flow for traffic, cyclists, and pedestrians,” the ministry said in a statement to CTV News Toronto earlier this month.

"This interchange design will reduce the number of vehicle conflict points and allow unrestricted access to the QEW."





While diverging diamond interchanges will be new to drivers in Ontario, they have been used in other places, like the U.S., for years. There are currently two diverging diamond interchanges in Canada, one in Calgary and the other in Regina.

The Ontario government held an in-person public education session to learn "how to navigate" the new interchange.

At that time, an animated drive-through video was released showing how Ontario's interchange works.

https://toronto.ctvnews.ca/ontario-s-first-diverging-diamond-interchange-opens-monday-1.6083490
• Video Link
Reply With Quote
     
     
  #1331  
Old Posted Sep 26, 2022, 5:10 PM
LRTeverywhere LRTeverywhere is offline
Registered User
 
Join Date: Oct 2018
Posts: 326
Quote:
Originally Posted by AuxTown View Post
417 closure, once again, this weekend for the Rochester bridge replacement. Those of you in the know, is this the final closure for this project or is there another bridge to replace still? The narrowing at Parkdale and beyond for the last couple years has resulted in significantly worse congestion coming from the west every morning and I look forward to everything being open again!
Last one for this year, 3 more to go on the project over the next couple of years, Bronson ramp closure lasts until 2025 I believe.

Then after this project is complete they will start the next project of 7 (technically 14 since the bridges are doubled up) bridge replacements from Kent to Main St.

Then probably like a 20 year gap before they start replacing bridges again
Reply With Quote
     
     
  #1332  
Old Posted Sep 26, 2022, 5:15 PM
Innsertnamehere's Avatar
Innsertnamehere Innsertnamehere is offline
Registered User
 
Join Date: Jan 2010
Location: Hamilton
Posts: 12,891
Quote:
Originally Posted by J.OT13 View Post
Not 417 related, but something to fear may one day show up in Ottawa.



• Video Link
MTO is also planning a much larger Diverging Diamond Interchange in Barrie at Mapleview Drive on the 400. As far as I know that's the only officially planned interchange I've seen elsewhere in Ontario.

Honestly I wouldn't mind it becoming the new standard interchange design, it's far cheaper than MTO's standard Parclo A4 and can be basically just as high capacity.
Reply With Quote
     
     
  #1333  
Old Posted Sep 30, 2022, 12:44 AM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,689
Queensway downtown closes both ways this weekend, starting Friday night

Staff Reporter, Ottawa Citizen
Sep 27, 2022 • 11 hours ago • 1 minute read


Queensway travellers should get ready for another weekend shutdown on and around Highway 417.

A five-kilometre section of Highway 417 is set to close in both directions Friday evening and remain closed until Monday morning as crews replace the bridge over Rochester Street.

The City of Ottawa says the closure is expected to result “in significant traffic impacts.”

All eastbound and westbound lanes of Hwy. 417 between Metcalfe Street and Carling Avenue/Kirkwood Avenue will be closed from Sept. 30 at 8 p.m. until Tuesday, Oct. 4 at 6 a.m. for the work.





Some related work has already begun.

Officials said the Hwy. 417 westbound and Rochester Street on-ramp closed Sept. 20, while Rochester Street will be closed from Aberdeen Street to Gladstone Avenue until Oct. 11.

During the construction work, eastbound on-ramps at Maitland, Carling and Parkdale avenues will be closed, while westbound on-ramps at O’Connor Street, Bronson Avenue, Lyon Street, Rochester Street and Parkdale Avenue will be closed. The Bronson Avenue and Lyon Street westbound on-ramps are closed already for construction.

The Rochester Street Bridge replacement was originally scheduled for Aug. 12-14, but work was delayed due to a strike in the construction sector.

In August, Hwy. 417 was closed between Metcalfe and Carling/Kirkwood avenues for 76 hours while crews replaced the Booth Street Bridge.

A construction site livestream has been set up to check out the construction and traffic.

As of Friday morning, you can check it out here:

• Video Link


https://ottawacitizen.com/news/local-new...dge-replacement-set-for-sept-30-to-oct-4
Reply With Quote
     
     
  #1334  
Old Posted Sep 30, 2022, 4:29 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by Innsertnamehere View Post
MTO is also planning a much larger Diverging Diamond Interchange in Barrie at Mapleview Drive on the 400. As far as I know that's the only officially planned interchange I've seen elsewhere in Ontario.

Honestly I wouldn't mind it becoming the new standard interchange design, it's far cheaper than MTO's standard Parclo A4 and can be basically just as high capacity.
Cheaper, safer, and more traffic capacity. They are more confusing for motorists who haven't used them before though. Some might argue that they aren't very good for pedestrians, but I would argue that other types of "freeway" interchanges are just as bad if not worse for pedestrians.
Reply With Quote
     
     
  #1335  
Old Posted Oct 13, 2022, 5:17 PM
rocketphish's Avatar
rocketphish rocketphish is offline
Planet Ottawa and beyond
 
Join Date: Feb 2009
Location: Greater Ottawa
Posts: 14,689
The time-lapse of the Rochester Street Bridge relocation project has finally been posted:

• Video Link
Reply With Quote
     
     
  #1336  
Old Posted Apr 3, 2023, 7:37 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,131
I hear the Queensway was quite the 🞵🞵🞵🞵-show this morning. I wonder if the media will have stories of how the 417 is an utter failure and how cars never work in winter.

Reply With Quote
     
     
  #1337  
Old Posted Apr 3, 2023, 8:04 PM
Dengler Avenue's Avatar
Dengler Avenue Dengler Avenue is offline
Road Engineer Wannabe
 
Join Date: Sep 2017
Location: Côté Ouest de la Rivière des Outaouais
Posts: 8,683
By that standard, LRT has failed the winter test too though.
What if companies and the federal government simply show some leeway and allow people to work remotely more often during winter months?
This is Ontario, not California or B.C., after all.

(Meanwhile, due to the same snowstorm, there was a fatal head-on crash on the 17 up at Petawawa.)
__________________
My Proposal of TCH Twinning in Northern Ontario
Disclaimer: Most of it is pure pie in the sky, so there's no need to be up in the arm about it.
Reply With Quote
     
     
  #1338  
Old Posted Apr 3, 2023, 8:12 PM
DarthVader_1961 DarthVader_1961 is offline
Registered User
 
Join Date: Jun 2009
Posts: 478
Quote:
Originally Posted by J.OT13 View Post
I hear the Queensway was quite the 🞵🞵🞵🞵-show this morning. I wonder if the media will have stories of how the 417 is an utter failure and how cars never work in winter.

I suspect some people forget how to drive when it’s bad weather.
Reply With Quote
     
     
  #1339  
Old Posted Apr 3, 2023, 8:14 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,131
Quote:
Originally Posted by Dengler Avenue View Post
By that standard, LRT has failed the winter test too though.
What if companies and the federal government simply show some leeway and allow people to work remotely more often during winter months?
This is Ontario, not California or B.C., after all.

(Meanwhile, due to the same snowstorm, there was a fatal head-on crash on the 17 up at Petawawa.)
That's what I was going with. The media and many people in the general population (often people who've never used the train) qualify the Confederation Line as an complete failure anytime something happens. My comment was meant as satire, turning the criticism towards the train around in the direction of the highway and car culture in general.
Reply With Quote
     
     
  #1340  
Old Posted Apr 3, 2023, 8:56 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by J.OT13 View Post
I hear the Queensway was quite the 🞵🞵🞵🞵-show this morning. I wonder if the media will have stories of how the 417 is an utter failure and how cars never work in winter.

LOL. Agreed! The conversion of the Renfrew Sub to a highway was a failure. We should convert the Queensway back to a railway.
__________________
Pronouns: He/Him/His
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 12:40 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.