How many times do developers have to go before the Dev Review Committee? Does every project start with a Development Plan Review or something before that?
If the committee approves the development plan review, and the zoning change request, what then?
|
Yes, all major projects go to DPR, only projects or renovations can be administrative/staff level approvals.
DPR is essentially a preliminary design review / entitlement approval that really only reviews site design and building elevations.
Once you receive DPR Approval, the design / development team moves to full Construction Document design phase and will submit for full site and building permits. CD phase includes full structural, interior design, mechanical, electrical, plumbing, architectural, civil and landscape. The CD phase can easily take 3-4 months or more plus City review times which are about 2-3 months (pending the client hasn't released the team to start full deign at risk concurrently during DPR phase). Hope that makes sense!