I went onto Trinity's site (https://www.trinity-group.com/news/)

Their Q4 2021 report estimates possession in Q4 2025 (https://mailchi.mp/7825b334aeed/trinity-q1-e-blast-draft-15224980); however, if you read their Q1 2022 report, for whatever reason, it is no longer identified as one of their upcoming projects (https://mailchi.mp/e3e22ecd05ac/trinity-q1-e-blast-draft-15350660).

Another bit of information to add to the puzzle.
Reply With Quote
     
     
  #1142  
Old Posted May 19, 2022, 6:10 PM
sgera sgera is offline
Registered User
 
Join Date: Apr 2002
Posts: 207
Quote:
Originally Posted by Ottawacurious View Post
I went onto Trinity's site (https://www.trinity-group.com/news/)

Their Q4 2021 report estimates possession in Q4 2025 (https://mailchi.mp/7825b334aeed/trinity-q1-e-blast-draft-15224980); however, if you read their Q1 2022 report, for whatever reason, it is no longer identified as one of their upcoming projects (https://mailchi.mp/e3e22ecd05ac/trinity-q1-e-blast-draft-15350660).

Another bit of information to add to the puzzle.
in the earnings fo rInter-Rent's REIT ..they still list it as a future project with an earliest planned start date of 1Q23
Reply With Quote
     
     
  #1143  
Old Posted Jul 27, 2022, 10:23 PM
originalmuffins originalmuffins is offline
Registered User
 
Join Date: Jun 2018
Location: Ottawa
Posts: 877
🞵🞵🞵🞵🞵🞵🞵 Trinity is just letting this go into development hell. If they aren't interested - find a buyer and just off the project like they did with Gladstone. What a waste, this project should have shovels in the ground even before the other stages of Lebreton to get the ball rolling for the area....

Everything is approved, retail tenants are found, it's directly attached to two major lines of our LRT.... it's not like the demand wouldn't be there.
Reply With Quote
     
     
  #1144  
Old Posted Jul 27, 2022, 10:28 PM
Harley613's Avatar
Harley613 Harley613 is offline
Registered User
 
Join Date: Jun 2009
Location: Aylmer, QC
Posts: 6,896
The most likely explanation I can think of is that they pushed this to the backburner immediately when Lansdowne 2.0 became a discussion. They probably don't have the resources to tackle two megaprojects at once, and only one of them has a limited timeframe. Trinity Centre would be a sure success, but that's not going to change over the next few years.
__________________
Instagram: https://www.instagram.com/the.harleydavis/
Reply With Quote
     
     
  #1145  
Old Posted Jul 27, 2022, 11:06 PM
bikegypsy's Avatar
bikegypsy bikegypsy is offline
Registered User
 
Join Date: Aug 2006
Posts: 985
Quote:
Originally Posted by Harley613 View Post
The most likely explanation I can think of is that they pushed this to the backburner immediately when Lansdowne 2.0 became a discussion. They probably don't have the resources to tackle two megaprojects at once, and only one of them has a limited timeframe. Trinity Centre would be a sure success, but that's not going to change over the next few years.
I will add to your comment that there's a limited amount of city wide resources, both human and in terms of equipment. Someone could correct me, but I'm pretty sure that the city is nearing full crane capacity.
Reply With Quote
     
     
  #1146  
Old Posted Jul 28, 2022, 1:26 AM
Harley613's Avatar
Harley613 Harley613 is offline
Registered User
 
Join Date: Jun 2009
Location: Aylmer, QC
Posts: 6,896
Very good point. I work in construction, and at my company we have been searching high and low the past couple of months for 12 labourers at $22 an hour with fast track training to higher paid specialties, but we have only managed to fill 3 spots so far.
__________________
Instagram: https://www.instagram.com/the.harleydavis/
Reply With Quote
     
     
  #1147  
Old Posted Jul 28, 2022, 1:39 AM
acottawa acottawa is offline
Registered User
 
Join Date: Aug 2009
Posts: 18,918
I have been sceptical of this project since it was announced (including this thread).

Trinity is a developer of big box stores and mid sized residential buildings. There is little evidence they can pull of a project of this scale or have a backer or partner that has that capacity.
Reply With Quote
     
     
  #1148  
Old Posted Jul 28, 2022, 1:50 AM
Harley613's Avatar
Harley613 Harley613 is offline
Registered User
 
Join Date: Jun 2009
Location: Aylmer, QC
Posts: 6,896
Quote:
Originally Posted by acottawa View Post
I have been sceptical of this project since it was announced (including this thread).

Trinity is a developer of big box stores and mid sized residential buildings. There is little evidence they can pull of a project of this scale or have a backer or partner that has that capacity.
Doesn't InterRent, a REIT with a massive portfolio of rental properties nationwide, have a significant stake in this project?
__________________
Instagram: https://www.instagram.com/the.harleydavis/
Reply With Quote
     
     
  #1149  
Old Posted Jul 28, 2022, 1:54 AM
acottawa acottawa is offline
Registered User
 
Join Date: Aug 2009
Posts: 18,918
Quote:
Originally Posted by Harley613 View Post
Doesn't InterRent, a REIT with a massive portfolio of rental properties nationwide, have a significant stake in this project?
Have you seen InterRent’s portfolio? It’s mostly commie blocks and crappy walkups.

https://www.interrentreit.com/communities/portfolio/
Reply With Quote
     
     
  #1150  
Old Posted Jul 28, 2022, 4:33 AM
Ottawacurious Ottawacurious is offline
Registered User
 
Join Date: Mar 2022
Location: Ottawa
Posts: 569
Do you think the lawsuits are part of the reason for the delay?
Reply With Quote
     
     
  #1151  
Old Posted Jul 28, 2022, 12:35 PM
waterloowarrior's Avatar
waterloowarrior waterloowarrior is offline
National Capital Region
 
Join Date: Nov 2005
Location: Eastern Ontario
Posts: 9,255
Quote:
Originally Posted by Ottawacurious View Post
Do you think the lawsuits are part of the reason for the delay?
It may be - the two companies that own the site (801 Albert Street Inc. and TIP Albert Limited Partnership) are caught up in this lawsuit
https://www.canlii.org/en/on/onsc/doc/2022/2022onsc2657/2022onsc2657.html
Reply With Quote
     
     
  #1152  
Old Posted Jul 28, 2022, 2:24 PM
Dzingle Bells Dzingle Bells is offline
Registered User
 
Join Date: Feb 2019
Posts: 158
Has the SPA been approved for this project or just the Zoning and OP amendments? I was speaking with a friend the other day that is working on this project and they said they were working through comments from the city to prepare for a 3rd submission for SPA. Sounded like the project was still very much on from what I gathered.
Reply With Quote
     
     
  #1153  
Old Posted Jul 28, 2022, 2:35 PM
Harley613's Avatar
Harley613 Harley613 is offline
Registered User
 
Join Date: Jun 2009
Location: Aylmer, QC
Posts: 6,896
Quote:
Originally Posted by Dzingle Bells View Post
Has the SPA been approved for this project or just the Zoning and OP amendments? I was speaking with a friend the other day that is working on this project and they said they were working through comments from the city to prepare for a 3rd submission for SPA. Sounded like the project was still very much on from what I gathered.
That sounds promising....and scary at the same time. What if they are chopping it down? Even worse...imagine they sent it to RLA for a Minecraft redesign?
__________________
Instagram: https://www.instagram.com/the.harleydavis/
Reply With Quote
     
     
  #1154  
Old Posted Jul 28, 2022, 2:40 PM
originalmuffins originalmuffins is offline
Registered User
 
Join Date: Jun 2018
Location: Ottawa
Posts: 877
I guess there is obviously a limitation to the resources needed to get a project done - but I don't think Trinity is currently trying because as acottawa said. I think they're in over their heads because currently they have zero projects in any of the current Lebreton phases (we have Sens, Claridge, Dream, Archives Canada+OPL) so it's probably better off if they sell their portion off to big developer who can actually get the resources to get this done. Frankly don't trust them after Rideau+Chapel but that's just my opinion I guess lol.

And if they are chopping it down... that really angers me even more lol.
Reply With Quote
     
     
  #1155  
Old Posted Jul 28, 2022, 2:42 PM
ServiceGuy ServiceGuy is offline
Registered User
 
Join Date: Dec 2009
Posts: 335
Quote:
Originally Posted by Harley613 View Post
I work in construction, and at my company we have been searching high and low the past couple of months for 12 labourers at $22 an hour...
Sounds like your company is coming in a little light on pay for the current market (depending on the kind of work you do) The company I work for is offering $25 for general labour but of course they need to be good workers and not just time clock punchers. At that income level a buck or two makes a difference to someone but it's still a struggle. Often times I have hired someone only to have them quit by morning break because they found a dollar / hour more somewhere else. Trying to get skilled workers is even worse these days.
Reply With Quote
     
     
  #1156  
Old Posted Jul 28, 2022, 2:55 PM
waterloowarrior's Avatar
waterloowarrior waterloowarrior is offline
National Capital Region
 
Join Date: Nov 2005
Location: Eastern Ontario
Posts: 9,255
It has site plan approval (https://skyscraperpage.com/forum/newreply.php?do=newreply&p=9041076) but the docs don't seem to be on the City devapps page anymore. However, there would be lots of conditions attached to the approval and other drawings to be submitted.
Reply With Quote
     
     
  #1157  
Old Posted Jul 28, 2022, 2:58 PM
Harley613's Avatar
Harley613 Harley613 is offline
Registered User
 
Join Date: Jun 2009
Location: Aylmer, QC
Posts: 6,896
Quote:
Originally Posted by ServiceGuy View Post
Sounds like your company is coming in a little light on pay for the current market (depending on the kind of work you do) The company I work for is offering $25 for general labour but of course they need to be good workers and not just time clock punchers. At that income level a buck or two makes a difference to someone but it's still a struggle. Often times I have hired someone only to have them quit by morning break because they found a dollar / hour more somewhere else. Trying to get skilled workers is even worse these days.
Our company has a really clear and rapid path to $28 and beyond for those who succeed at least
__________________
Instagram: https://www.instagram.com/the.harleydavis/
Reply With Quote
     
     
  #1158  
Old Posted Jul 28, 2022, 3:40 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,131
If this project is on hold, I would think (and frankly hope) that Trinity loses credibility with potential tenants by signing leases and then not building.
Reply With Quote
     
     
  #1159  
Old Posted Jul 31, 2022, 9:02 AM
originalmuffins originalmuffins is offline
Registered User
 
Join Date: Jun 2018
Location: Ottawa
Posts: 877
Quote:
Originally Posted by J.OT13 View Post
If this project is on hold, I would think (and frankly hope) that Trinity loses credibility with potential tenants by signing leases and then not building.
Agreed, this bait and switch with failing to deliver on multiple projects really irks me with Trinity. 2018 me was excited to see all what they had in the pipeline, only to not deliver on any project and completely fail with Rideau+Chapel.. sorry "tHE sToRy OF". Lol.
Reply With Quote
     
     
  #1160  
Old Posted Aug 10, 2022, 1:00 AM
sgera sgera is offline
Registered User
 
Join Date: Apr 2002
Posts: 207
Well, according to Inter-rent REITs quarterly investment deck (slide 21) that came out last week, it seems like 900 Albert isn’t a dead venture but they no longer list a target completion date … building rendering and unit count still match old plan which is a good sign. They now
own 47% of the joint venture with Trinity.

https://interrentreit.com/documents/ip/2022_Q2_IP.pdf
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Downtown & Urban Ottawa
Forum Jump



Forum Jump


All times are GMT. The time now is 4:45 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.