Quote:
Originally Posted by GoTrans View Post
Ottawa would have made a better choice with the Siemens vehicles used by Edmonton and Calgary and high level platforms.
For what we spent, we could have gone even better and built something closer to REM. It is what it is. No use crying over spilled milk now. We should be thinking of how to make the best of this.
     
     
  #15622  
Old Posted Jun 20, 2022, 3:16 PM
OTSkyline OTSkyline is offline
Registered User
 
Join Date: Jun 2012
Posts: 2,826
At least the recent stats seem promising. Really hope we've ironed out the kinks by now and can offer frequent and reliable service as intended.
     
     
  #15623  
Old Posted Jun 20, 2022, 4:29 PM
swimmer_spe swimmer_spe is offline
BANNED
 
Join Date: Apr 2014
Posts: 10,743
Quote:
Originally Posted by Catenary View Post
The existing facilities can likely handle a 59m car, the existing 48m cars with an added module. Considering the platforms are 90m long with room to extend a bit, you're still left with 1/2 length trains if you build them to maximum maintenance length.

Look at the existing MSF - there's no room on that site to double the length of the maintenance bays. While the trains may be due for replacement after 30-40 years of use, the maintenance facility will have a longer lifespan than that, so replacing it so soon would be wasteful.
So then accept the cars as is and build the PSD for them.
     
     
  #15624  
Old Posted Jun 21, 2022, 11:32 AM
Catenary Catenary is offline
Registered User
 
Join Date: Dec 2012
Posts: 1,403
Quote:
Originally Posted by swimmer_spe View Post
So then accept the cars as is and build the PSD for them.
Our current train design is incompatible with PSDs though, as each unit is asymmetrical. There are also issues created by running the system in manual mode - it's harder to ensure alignment each time the train stops.

Regardless, I'm not sure what problem PSDs are expected to solve in our system. Track incursions aren't much of an issue with low platforms.
     
     
  #15625  
Old Posted Jun 25, 2022, 4:57 AM
ponyboycurtis's Avatar
ponyboycurtis ponyboycurtis is offline
Cigritbutt enthusiast
 
Join Date: Apr 2021
Location: Blahttawa
Posts: 1,679
I got off the train at Bayview the other day and couldn't help but be immediately drawn towards this.





As of June 23rd we still have salt caked all over the platform? That is as surprising as it is painful. The lack of enclosed platforms and... are ALL the platform heaters broken or is that just Hurdman?

Anyhow. Here is a good snapshot of how some of our brand new infrastructure is going to age. I've noticed a lot of columns and railing bases and staircase edges showing a decent amount of rust already at many stations.
     
     
  #15626  
Old Posted Jun 25, 2022, 5:01 AM
swimmer_spe swimmer_spe is offline
BANNED
 
Join Date: Apr 2014
Posts: 10,743
Quote:
Originally Posted by ponyboycurtis View Post
I got off the train at Bayview the other day and couldn't help but be immediately drawn towards this.





As of June 23rd we still have salt caked all over the platform? That is as surprising as it is painful. The lack of enclosed platforms and... are ALL the platform heaters broken or is that just Hurdman?

Anyhow. Here is a good snapshot of how some of our brand new infrastructure is going to age. I've noticed a lot of columns and railing bases and staircase edges showing a decent amount of rust already at many stations.
One would expect that it would be cleaned up by now.
     
     
  #15627  
Old Posted Jun 25, 2022, 5:21 AM
ponyboycurtis's Avatar
ponyboycurtis ponyboycurtis is offline
Cigritbutt enthusiast
 
Join Date: Apr 2021
Location: Blahttawa
Posts: 1,679
I should make a phone call eh? Rather than just sucking my teeth at it.
     
     
  #15628  
Old Posted Jun 25, 2022, 5:25 PM
Athens Athens is offline
Registered User
 
Join Date: Dec 2015
Posts: 56
Quote:
Originally Posted by ponyboycurtis View Post
I should make a phone call eh? Rather than just sucking my teeth at it.
Who cares? The morons at RTG will have to pay for it anyways, given that they are maintaining it for 30 years. If they are stupid enough to destroy the buildings this rapidly, then they deserve to go under
     
     
  #15629  
Old Posted Jun 25, 2022, 6:23 PM
PHrenetic PHrenetic is offline
Registered User
 
Join Date: Jun 2016
Location: Ottawa
Posts: 1,029
Quote:
Originally Posted by ponyboycurtis View Post
I should make a phone call eh? Rather than just sucking my teeth at it.
Good Day.

Better would be to send it to any or all of CBC / CTV / LRT Inquiry .

Because any way you count it, we all will end up paying for it - one way AND another.

NoJoy!
     
     
  #15630  
Old Posted Jun 26, 2022, 8:12 PM
Hybrid247 Hybrid247 is offline
Registered User
 
Join Date: Oct 2009
Posts: 1,320
I'm no construction expert, but couldn't some kind of protective layer be placed around the base of the steel columns to protect against corrosion?

Last edited by Hybrid247; Jun 26, 2022 at 8:27 PM.
     
     
  #15631  
Old Posted Jun 26, 2022, 9:00 PM
vtecyo vtecyo is offline
Registered User
 
Join Date: Feb 2015
Posts: 329
Quote:
Originally Posted by Hybrid247 View Post
I'm no construction expert, but couldn't some kind of protective layer be placed around the base of the steel columns to protect against corrosion?
I'd guess it's already coated with rustproofing, but it's damaged. And/or the concrete isn't protected inside the concrete - so the salt and water absorbed into the concrete has gotten to work on it.
     
     
  #15632  
Old Posted Jun 29, 2022, 1:36 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,064
Been biking the Blair station the last few days and man, is it unpleasant. They have a decent bike parking plaza, but no cycling infrastructure improvements were made in any way, shape or form. Ditto for St. Laurent, which now has a bike locker (but you have to get a key and pay? Charge for bike parking, but no charge for massive, maintenance heavy park-and-rides) but zero cycling connections.

https://www.google.com/maps/@45.4318214,...itch%3D0%26thumbfov%3D100!7i16384!8i8192
     
     
  #15633  
Old Posted Jun 29, 2022, 2:32 PM
OTownandDown OTownandDown is offline
Registered User
 
Join Date: Jul 2018
Posts: 1,632
I've tweeted the councilor, RTG, the mayor, Ottawa Riverkeeper, and a biking twitter account about Hurdman Station several times.

The amount of salt caked on everything is absolutely astounding. On top of all the park benches, out into the fields/watershed surrounding the station, inside and up and down the elevator components, filling all of the surface drains, up and down all the stairs.

Of course nothing is galvanized, some of the stainless steel supporting the glazed panels is sh*tty stainless from a country that shall go unnamed, and is already corroding as well.

Not to mention the 'art' is covered in cobwebs, and some of the 'wood' panelling is also loose and/or corroded. Should age great.

The City isn't paying RTG for their maintenance contract, RTG claims that they SHOULD be paid despite ongoing deficiencies, and now nobody is there to clean up anything, ever.

Most stations look like a third-world country. Filth, urine, dirty glass, smells.
     
     
  #15634  
Old Posted Jun 29, 2022, 2:45 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 29,064
Quote:
Originally Posted by OTownandDown View Post
I've tweeted the councilor, RTG, the mayor, Ottawa Riverkeeper, and a biking twitter account about Hurdman Station several times.

The amount of salt caked on everything is absolutely astounding. On top of all the park benches, out into the fields/watershed surrounding the station, inside and up and down the elevator components, filling all of the surface drains, up and down all the stairs.

Of course nothing is galvanized, some of the stainless steel supporting the glazed panels is sh*tty stainless from a country that shall go unnamed, and is already corroding as well.

Not to mention the 'art' is covered in cobwebs, and some of the 'wood' panelling is also loose and/or corroded. Should age great.

The City isn't paying RTG for their maintenance contract, RTG claims that they SHOULD be paid despite ongoing deficiencies, and now nobody is there to clean up anything, ever.

Most stations look like a third-world country. Filth, urine, dirty glass, smells.
I agree. It's a pretty sorry state. You'd think they would design for the climate. i though the point of heated platforms was to remove the need for salt.

Even the "O" pylons (I assume those are OC's responsibility). The light at the Lyon Podium entrance has been out for years. The "O" had fallen, It was replaced, but not the light, nor the blue accessible entrance square.
     
     
  #15635  
Old Posted Jul 1, 2022, 5:03 AM
ponyboycurtis's Avatar
ponyboycurtis ponyboycurtis is offline
Cigritbutt enthusiast
 
Join Date: Apr 2021
Location: Blahttawa
Posts: 1,679
It occurred to me to perhaps make an entire post or thread about maintenance or lack of or altogether just piss poor planning and implementation.

We are all aware of the salt infiltration and rusting etc as discussed not more than a page ago.



Walking down the stairs at Hurdman today. I can assure you that this did not look like this last year.

I think we should document all of this degradation of our near and dear transit system in such a short order. Maybe all our photos and Exif data could be used one day in a court case.





It hurts my brain to think about all the engineering that went into fitting all of these pieces together so nicely but without any thought to how it will perform/function/weather.

A devoted thread to LRT deficiencies in any way shape or form could be helpful.

Sidenote.

Any of the fellas over here ever try to take a leak at Hurdman? why is there no urinal.. and why is the toilet seat geared only towards accessibility?

I'm not trying to piss on the seat.. but good lord you make it so hard.
     
     
  #15636  
Old Posted Jul 1, 2022, 3:17 PM
DarthVader_1961 DarthVader_1961 is offline
Registered User
 
Join Date: Jun 2009
Posts: 477
Quote:
Originally Posted by ponyboycurtis View Post
It occurred to me to perhaps make an entire post or thread about maintenance or lack of or altogether just piss poor planning and implementation.

We are all aware of the salt infiltration and rusting etc as discussed not more than a page ago.



Walking down the stairs at Hurdman today. I can assure you that this did not look like this last year.

I think we should document all of this degradation of our near and dear transit system in such a short order. Maybe all our photos and Exif data could be used one day in a court case.





It hurts my brain to think about all the engineering that went into fitting all of these pieces together so nicely but without any thought to how it will perform/function/weather.

A devoted thread to LRT deficiencies in any way shape or form could be helpful.

Sidenote.

Any of the fellas over here ever try to take a leak at Hurdman? why is there no urinal.. and why is the toilet seat geared only towards accessibility?

I'm not trying to piss on the seat.. but good lord you make it so hard.
Send pics like this to the press
     
     
  #15637  
Old Posted Jul 1, 2022, 4:13 PM
PHrenetic PHrenetic is offline
Registered User
 
Join Date: Jun 2016
Location: Ottawa
Posts: 1,029
Quote:
Originally Posted by PHrenetic View Post
Good Day.

Better would be to send it to any or all of CBC / CTV / LRT Inquiry .

Because any way you count it, we all will end up paying for it - one way AND another.

NoJoy!
Quote:
Originally Posted by DarthVader_1961 View Post
Send pics like this to the press
Good Day.

Yes - Agreed - ESPECIALLY right now during the active phase of the LRT inquiry,
while the attention of everyone is focused on the continuing FUBAR that is now revealed to us that we will have to live with, endure with, and PAY for.

NoJoy!
     
     
  #15638  
Old Posted Jul 2, 2022, 1:05 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is offline
Busy Beaver
 
Join Date: Nov 2005
Location: Ottawa
Posts: 4,692
Anyone take the LRT or buses last night after last night’s Canada Day show and fireworks? I was on my bike but from the looks of it, it seemed Pimisi station was a s#!tshow, they only had the east side entrance open. The Booth street bridge was a mess of barricades and people had little idea of where they were being funnelled to. Getting to buses on Albert was equally confusing, it did not seem like an efficient operation. Riding my bike along Scott, the rate of buses going through seemed low.
     
     
  #15639  
Old Posted Jul 2, 2022, 4:13 PM
DarthVader_1961 DarthVader_1961 is offline
Registered User
 
Join Date: Jun 2009
Posts: 477
     
     
  #15640  
Old Posted Jul 2, 2022, 5:15 PM
OCCheetos OCCheetos is offline
Registered User
 
Join Date: Aug 2017
Posts: 2,113
Quote:
Originally Posted by DarthVader_1961 View Post
They closed Pimisi shortly before the fireworks at the request of OPS and event organizers because the venue had reached capacity.

They reopened the station for Eastbound travel after the fireworks were over.
https://twitter.com/OC_Transpo/status/1543054307179872257
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 8:15 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.