Quote:
Originally Posted by Vancouver_Highrise
Overheard: they are a year behind schedule.. Trains will run every 15 mins for the Langley stretch for around 2 years because there are supply issues with the trains and they are more focused on getting stations and tracks built.
|
Even if it were true that there would be a shortage of trains around the time SLS opens, is this not the SkyTrain system???
Like, we might just be the most flexible system as far as train running/combinations on earth. I feel like we have numerous options available, including delaying retirement of the 90s-delivered Mark I trains, or even running a relay service with 2-car Mark II trains between Surrey Central and Langley until enough trains are available to run them all full-length.
AFAIK the Mark Vs are set to be delivered constantly from next year, with the base order supplemented by options that could theoretically keep coming all the way through to 2036. Here's the delivery schedule from the
Mark V thread on CPTDB:
Quote:
Base order: 205 cars 41 sets
2021: 30 cars 6 sets, 2025 delivery
2024: 70 cars 14 sets, 2028 delivery
2026: 100 cars 20 sets, 2032 delivery
2028: 100 cars 20 sets, 2034 delivery
2030: 100 cars 20 sets, 2036 delivery
|
Apparently the first option for an additional 30 cars (6 sets) was exercised in July of last year.
SLS opens in 2028, so barring any issues, by then we'd have received the entire base order of 205 cars and chunks of the additional orders.