Old Posted Apr 7, 2022, 4:45 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,262
An old planning document from Fall 2020 showing Talbot facade.



https://london.ca/sites/default/files/2021-02/Z-9250-Notice%20of%20Application.pdf
Reply With Quote
     
     
  #222  
Old Posted Apr 8, 2022, 2:06 PM
MolsonExport's Avatar
MolsonExport MolsonExport is offline
Touching grass everyday.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 51,360
the Talbot facade looks so cut-and-pasted.
Great density, though
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell). Sweet Loretta fart thought she was a cleaner, but she was a frying pan. (John Lennon)
Reply With Quote
     
     
  #223  
Old Posted Apr 8, 2022, 2:41 PM
johnnyhamont's Avatar
johnnyhamont johnnyhamont is offline
Registered User
 
Join Date: Dec 2015
Posts: 1,116
Quote:
Originally Posted by jammer139 View Post
An old planning document from Fall 2020 showing Talbot facade.

https://london.ca/sites/default/files/2021-02/Z-9250-Notice%20of%20Application.pdf


Reply With Quote
     
     
  #224  
Old Posted Apr 8, 2022, 2:44 PM
CanadianTalk's Avatar
CanadianTalk CanadianTalk is online now
Moderator
 
Join Date: Jun 2021
Location: London, Ontario
Posts: 1,298
Quote:
Originally Posted by MolsonExport View Post
the Talbot facade looks so cut-and-pasted.
Great density, though
Agreed.

Usually, I love it when new buildings incorporate old heritage elements/buildings. But this doesn't look right to me.

It does looks like, though, that Old Oak may have changed their design for the facade because those old houses fronting Talbot have been demolished, and Old Oak's website shows a different design for the facade: https://oldoakproperties.com/apartments/centro/
Reply With Quote
     
     
  #225  
Old Posted Apr 8, 2022, 4:22 PM
MolsonExport's Avatar
MolsonExport MolsonExport is offline
Touching grass everyday.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 51,360
demolished? Nothing old in Old Oak. New Oak?
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell). Sweet Loretta fart thought she was a cleaner, but she was a frying pan. (John Lennon)
Reply With Quote
     
     
  #226  
Old Posted Apr 8, 2022, 4:48 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,262
Forming now started for 7th floor walls in the SW corner of south tower.
Reply With Quote
     
     
  #227  
Old Posted Apr 8, 2022, 7:48 PM
GreatTallNorth2 GreatTallNorth2 is offline
Registered User
 
Join Date: May 2006
Posts: 1,754
I thought I saw that the facade was going to be moved to the inside of the middle building.
Reply With Quote
     
     
  #228  
Old Posted Apr 8, 2022, 8:49 PM
haljackey's Avatar
haljackey haljackey is offline
User Registered
 
Join Date: Apr 2010
Location: London, Ontario
Posts: 3,479
Quote:
Originally Posted by CanadianTalk View Post
Agreed.

Usually, I love it when new buildings incorporate old heritage elements/buildings. But this doesn't look right to me.
For once I am hoping the render doesn't look like the finished product
__________________
My Twitter

My Simcity Stuff
Reply With Quote
     
     
  #229  
Old Posted Apr 8, 2022, 10:57 PM
Djeffery's Avatar
Djeffery Djeffery is offline
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,280
Wasn't that the former builder's design (Rygar was it?). I thought Old Oak changed a few things.
Reply With Quote
     
     
  #230  
Old Posted Apr 9, 2022, 4:17 PM
crackiedog crackiedog is offline
Registered User
 
Join Date: Jan 2009
Posts: 97
Quote:
Originally Posted by jammer139 View Post
An old planning document from Fall 2020 showing Talbot facade.



https://london.ca/sites/default/files/2021-02/Z-9250-Notice%20of%20Application.pdf
The application to move the Camden Terrace facade from the interior to the exterior was subsequently withdrawn by Old Oak.

LFP Mar. 2, 2021:

"Centro application revoked
What was expected to be a fiery battle over two downtown heritage landmarks “collapsed” on Monday night as a developer withdrew proposed changes to a $245-million, twin tower project at the site of the old Camden Terrace. Old Oak had applied to rebuild the Victorian rowhouse facade on the outside of its Talbot Street development, instead of inside the lobby, and asked for permission to deconstruct and rebuild two walls of a heritage property at 93-95 Dufferin Ave., angering history buffs. The company withdrew both requests Monday night, saying it was looking forward to final planning approvals to restart “this vital and ambitious project” it’s calling Centro."

https://lfpress.com/news/local-news/city-council-committee-briefs-2
Reply With Quote
     
     
  #231  
Old Posted Apr 24, 2022, 2:59 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,262
Now forming for 8th floor slab in the south tower. Have a section of the L2 slab formed and steel rebar in the SE corner of pit. Could see that poured this week. Forming for L3 walls for the elevator/stairwell shaft in the north tower. Have crushed stone now in the NE corner and prepping to pour the NE corner L3 slab in the coming weeks.
Reply With Quote
     
     
  #232  
Old Posted May 28, 2022, 2:14 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,262
The 8th floor slab is now poured and they have started steel rebar for 8th floor walls and posts in the south tower. They have also begun removing the dirt ramp along the west side of the pit in the north end. They have also delivered 5 more sections of tower crane to the site in preparation for lifting the south tower crane. Should see that very soon.
Reply With Quote
     
     
  #233  
Old Posted Jun 1, 2022, 5:48 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,262
Some of the 8th floor walls and posts for the south tower are now poured.
Reply With Quote
     
     
  #234  
Old Posted Jun 4, 2022, 3:07 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,262
They have lifted the south tower crane now. Slightly taller now then the north tower crane.
Reply With Quote
     
     
  #235  
Old Posted Jun 6, 2022, 8:58 PM
Goldenamishplumber Goldenamishplumber is offline
Registered User
 
Join Date: May 2021
Posts: 44
Was able to take a different angle of it a few days ago.
Reply With Quote
     
     
  #236  
Old Posted Jun 6, 2022, 11:58 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,262
Excellent photo. Even timed the York King street project lifting their tower crane in the background.
Reply With Quote
     
     
  #237  
Old Posted Jun 7, 2022, 4:19 PM
MolsonExport's Avatar
MolsonExport MolsonExport is offline
Touching grass everyday.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 51,360
Great shot. London is growing up, finally. If only we could get a mass transit system to match.
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell). Sweet Loretta fart thought she was a cleaner, but she was a frying pan. (John Lennon)
Reply With Quote
     
     
  #238  
Old Posted Jun 8, 2022, 1:07 PM
johnnyhamont's Avatar
johnnyhamont johnnyhamont is offline
Registered User
 
Join Date: Dec 2015
Posts: 1,116
Some photos from Centro's social media this morning:



Reply With Quote
     
     
  #239  
Old Posted Jun 19, 2022, 4:26 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,262
The 8th floor walls and posts are now poured and the forming is up for the 9th floor slab in the south tower. They have excavated out the remaining soil on the west wall of pit. Excavator is still at bottom of pit to dig out the remaining footing islands for concrete forming along the west side. Sump pump pit for the north tower is now poured and prep is under way for the north L3 wall forming. Should see alot of forming and pouring in the north end of pit in the coming weeks.
Reply With Quote
     
     
  #240  
Old Posted Jun 25, 2022, 7:38 PM
jammer139 jammer139 is offline
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,262
Have poured the 9th floor slab and started the forming for 9th floor walls and posts on the south tower. Have poured the L3 perimeter wall along the north end. Steel rebar now up for the NW corner L3 perimeter wall. Getting closer to pouring the L3 floor slab along the east wall of pit into the NE corner. Footings being formed and poured now along the west wall.
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Projects & Construction Updates
Forum Jump



Forum Jump


All times are GMT. The time now is 2:56 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.