This is fairly pricey, but apparently is the cheapest option. According to the CBC article, the current facility is beyond repair.
Quote:
Moncton councillors gave early approval to a plan to overhaul the city's public works facility estimated to cost $16 million instead of building at a new location for more than double the cost.
The 21.5 acre site beside the Coliseum consists of city fleet maintenance and storage buildings, fuel pumps, salt dome and office space for municipal staff.
City staff say the buildings are deteriorating, there's no longer enough space and they want to mitigate noise and dust concerns from residents to the north.
|
Quote:
Moving the whole operations centre facility to a new site was estimated to cost $35.9 million.
Moving some of the facility elsewhere was estimated to cost $22.4 million.
A four-phase overhaul of the existing site to allow it to be used for another 25 years was estimated to cost $16.6 million.
|
from CBC
I love that "phase 1" constitutes the erection of a new sign (and nothing else).
The multiphase construction timeline would allow for continuous use of the facility during the construction period, which will commence in 2023, and be complete by 2025.
In addition to the new buildings, the entire site will be paved, and this is to allow for dust mitigation, which is a major nuisance for neighbouring residents right now. An earthen berm will also be created to hide the public works facility from the adjacent residential neighbourhood.