Quote:
Originally Posted by SirLucasTheGreat
What do people here think is more likely to happen between the Greyhound redevelopment, Amacon, or 19th and Lawrence? Those are all massive projects along the same corridor
|
Probably Amacon will be first to cross the ground breaking finish line. They own the land, their approvals & permits are very far along and they already completed demolition of the prior structure. They've also established a Denver office and have been speaking to the press about groundbreaking this year.
19th Lawrence hasn't applied for construction permits or has an approved SDP and the land is still "under contract" with Geller. They are talking early next year, but I think that is optimistic.
Greyhound block is just starting demolition permits now, however, GORO did buy the land outright. No definitive site development plan other than a very high-level two 400ft towers and a plaza, so a lot of permitting and approval work ahead. That could change really fast given Golub & Rockfeller has a track record with massive development projects in Chicago and New York and probably the financial backing to move when they are ready to move.