Thanks for posting those resources.

MOT - Highway-1-main-street-dollarton-highway-interchange
"The Main Street/ Dollarton Interchane works includes some exciting new upgrades for pedestrians and cyclists which includes:

Widening of the Main Street On-Ramp to accommodate two travel lanes and a 3.0 m multi-use path (MUP);"

How will the two lanes work? Will the they just merge or will the light alternate (between the two lanes AND the Dollarton on ramp)? Or something else? Youtube video just shows one lane from Main street.

Does anyone besides us and Ministry of Transportation staff care about this stuff?
     
     
  #742  
Old Posted Sep 15, 2021, 12:22 AM
madog222 madog222 is offline
Moderator
 
Join Date: Jan 2014
Posts: 4,184
Quote:
Originally Posted by Jimbo604 View Post
Thanks for posting those resources.

MOT - Highway-1-main-street-dollarton-highway-interchange
"The Main Street/ Dollarton Interchane works includes some exciting new upgrades for pedestrians and cyclists which includes:

Widening of the Main Street On-Ramp to accommodate two travel lanes and a 3.0 m multi-use path (MUP);"

How will the two lanes work? Will the they just merge or will the light alternate (between the two lanes AND the Dollarton on ramp)? Or something else? Youtube video just shows one lane from Main street.

Does anyone besides us and Ministry of Transportation staff care about this stuff?
I think “widening to two lanes” refers to just the section being built now, the on ramp from Main will remain one lane.

The only information we have on how it will operate is from the video which shows the configuration at PM peak. The two lanes will just merge when the signal phase is green to traffic from Main St and the bus lane.

During non-peak times we don’t really know the configuration or even if it is different.
     
     
  #743  
Old Posted Sep 17, 2021, 9:21 PM
Jimbo604 Jimbo604 is offline
Registered User
 
Join Date: Jan 2012
Posts: 1,888
Quote:
Originally Posted by madog222 View Post
I think “widening to two lanes” refers to just the section being built now, the on ramp from Main will remain one lane.

The only information we have on how it will operate is from the video which shows the configuration at PM peak. The two lanes will just merge when the signal phase is green to traffic from Main St and the bus lane.

During non-peak times we don’t really know the configuration or even if it is different.
Yes, that sounds right.. just some ambiguous language in the gov web page there. So Main street on-ramp users will have to contend with a merge and a traffic light. Too bad they can't glue another lane to the bridge.

So it says 3.0m path in that webpage and the graphic posted says "Reinstate 2.5m Sidewalk" so what is it, 2.5 or 3, we need to know!
     
     
  #744  
Old Posted Sep 17, 2021, 10:21 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,713
Quote:
Originally Posted by Jimbo604 View Post
Yes, that sounds right.. just some ambiguous language in the gov web page there. So Main street on-ramp users will have to contend with a merge and a traffic light. Too bad they can't glue another lane to the bridge.

So it says 3.0m path in that webpage and the graphic posted says "Reinstate 2.5m Sidewalk" so what is it, 2.5 or 3, we need to know!
It's probably 3 at the new section and narrows to match the 2.5 of the actual bridge.

The excavator has been doing a lot of work on the section near Main Street now so you assume they'll be ready to pave it soon. And the grading around the Mountain Highway new merge seems close so maybe another 2-3 weeks there.
     
     
  #745  
Old Posted Sep 20, 2021, 9:32 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,713
They installed a set of signals for the metered ramp at the overpass today.
     
     
  #746  
Old Posted Sep 24, 2021, 3:18 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,713
They were installing lighting next to the Main Street onramp so it seems like they'll be ready to pave soon.
     
     
  #747  
Old Posted Sep 24, 2021, 4:20 PM
djmk's Avatar
djmk djmk is offline
victory in near
 
Join Date: Sep 2008
Location: North Vancouver
Posts: 1,795
the lights look installed and they are paving this morning

Maybe next week it will be open!
__________________
i have no idea what's going on
     
     
  #748  
Old Posted Sep 24, 2021, 8:04 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,713
Quote:
Originally Posted by djmk View Post
the lights look installed and they are paving this morning

Maybe next week it will be open!
Seems like it's raining heavily next week so not sure if that will cause any delays. I guess they'll want to test out the system as well so 2 weeks if I'm optimistic.
     
     
  #749  
Old Posted Sep 25, 2021, 1:50 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,713
Update: They removed the concrete barriers on Main Street overnight. They also paved over the pavement under the old barriers this morning.

Last edited by jollyburger; Sep 25, 2021 at 7:48 PM.
     
     
  #750  
Old Posted Sep 27, 2021, 7:59 PM
Jimbo604 Jimbo604 is offline
Registered User
 
Join Date: Jan 2012
Posts: 1,888

DriveBC Webcam

A lot of dump trucks today and movement.. Opening should be soon!!
     
     
  #751  
Old Posted Sep 27, 2021, 8:01 PM
Jimbo604 Jimbo604 is offline
Registered User
 
Join Date: Jan 2012
Posts: 1,888

DriveBC Webcam

Still working on concrete forms on the east side of the green bridge (formerly orange bridge). Then they have to pour concrete, backfill and pave. So going to be a bit here but getting close.
     
     
  #752  
Old Posted Sep 27, 2021, 10:18 PM
chowhou's Avatar
chowhou chowhou is offline
Registered User
 
Join Date: Sep 2019
Location: East Vancouver (No longer across the ocean!)
Posts: 3,795


Traffic has shifted to the newly paved section, and the area between the new overpass and the highway is being cleared.
     
     
  #753  
Old Posted Sep 29, 2021, 8:07 PM
Jimbo604 Jimbo604 is offline
Registered User
 
Join Date: Jan 2012
Posts: 1,888

DriveBC

Just a little paving and stuff left!
     
     
  #754  
Old Posted Sep 29, 2021, 11:02 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,713
Looks like they finished pouring concrete into those forms by the Lynn Creek bridge.
     
     
  #755  
Old Posted Oct 2, 2021, 9:07 PM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,713
After a few days of no work they had an excavator doing something on the Main Street ramp last night. They dropped off a compactor so maybe we'll see it paved by Monday.

They also installed more wood froms by Lynn Creek so it seems that will still need a bit more work before they pave it.
     
     
  #756  
Old Posted Oct 5, 2021, 10:02 PM
Jimbo604 Jimbo604 is offline
Registered User
 
Join Date: Jan 2012
Posts: 1,888

https://www.drivebc.ca/mobile/pub/webcams/id/763.html

They did have a fair amount of fill here. Hopefully paving soon!

And... did they plan a wider 3.5m MUP here just to have a wider path for walkers/cyclists or was the unspoken benefit that this would provide an alternate lane to keep traffic moving while they dug up the existing lane. Inquiring minds want to know.
     
     
  #757  
Old Posted Oct 6, 2021, 2:30 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,713
Quote:
Originally Posted by Jimbo604 View Post
They did have a fair amount of fill here. Hopefully paving soon!

And... did they plan a wider 3.5m MUP here just to have a wider path for walkers/cyclists or was the unspoken benefit that this would provide an alternate lane to keep traffic moving while they dug up the existing lane. Inquiring minds want to know.
I never use the Main Street onramp but is it just me or is there only a single merge light signal on the far left lane? That might be the best indicator of their plans. And I doubt they're going to build another retaining wall on the outside of where they placed that divider.

There's no road closures for the holidays so looks like it will be next week or the week after before we get to see this in action.
     
     
  #758  
Old Posted Oct 6, 2021, 11:32 PM
aberdeen5698's Avatar
aberdeen5698 aberdeen5698 is offline
Registered User
 
Join Date: May 2010
Posts: 4,790
How North Vancouver's Highway 1 project helps cyclists and pedestrians

North Shore News article about some of the lesser-seen improvements that have been made as part of the Highway 1 upgrade:

Quote:
Here's a look at how North Vancouver's Highway 1 project helps cyclists and pedestrians
A tangle of fresh active transportation paths wind between Brooksbank to the west, Seymour Boulevard to the east, Keith Road to the South and above the highway to the north. These new multi-use paths represent some excellent new links to get around this area more directly and safely.

Above Keith, the new path to the west extends the Salop Trail, which runs up the (really steep) hill from Shavington to Brooksbank Elementary. People living in the new town centre at Seylynn can access this path via a new, wide, well-lit tunnel under Mountain Highway. Above Shavington, the trail remains gravel and is steep, so whereas it is great for people walking, people on bikes might not be able to take advantage. The same entrance from Bridgman Park leads under the new Keith Road and Highway 1 bridges to join up with the gravel path on the west side of Lynn Creek. Which again is gravel, so not a super choice for people cycling, but excellent for people on foot.
...
     
     
  #759  
Old Posted Oct 8, 2021, 6:16 AM
jollyburger jollyburger is online now
Registered User
 
Join Date: Dec 2015
Posts: 15,713
They had an excavator at the side of the road with a trench box doing something for the past week or two.

Answer: It was a footing for a new sign that's getting installed right now:



https://images.drivebc.ca/bchighwaycam/pub/html/www/852.html

They're doing work over at Lynn Creek and what appears to be paving on the Main Street onramp



https://images.drivebc.ca/bchighwaycam/pub/html/www/763.html
     
     
  #760  
Old Posted Oct 8, 2021, 6:09 PM
NicholasHui NicholasHui is offline
Registered User
 
Join Date: Oct 2020
Posts: 39
They finished the paving just before sunrise. It could be in a matter of weeks before the new highway ramp meter for the Dollaration Highway to Highway 1 eastbound is opened fully
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 4:38 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.