It’s been interesting to see some of the recent developments coming up in the Surrey/South Fraser Updates thread, and I’ve been thinking a lot about how “Inexperience” doesn’t just seem to excuse how weirdly things progressed on this project.
It would be great if forumers with more development experience could weigh in… In retrospect, I think there were some inexplicably bad management decisions being made.
That post about Belvedere selling out in 72 hours inspired me to look into that file more on Cosmos. Based on the Cosmos file, the building permit for that site was submitted back in Oct. 2020, and is probably still processing. So the lag time from going from sales to construction start will be minor probably.
But in this topic, the Avani Centre unit selling seems to start around May/June 2018. But I know for a fact that the consultants only got their building permit documentation completed in December 2018, and this is corroborated by the COSMOS file, which says the BP intake date was Dec 6 2018.
So that’s already a departure from the norm - selling for 6 months before even applying for the building permit in one of the slowest municipalities in the province to approve building permits? Very odd. Plus, if Gummo’s quotes are correct, they were telling their clients about a potential fall 2018 construction start…months before even applying for permit?
Compare this to other projects in Surrey City Centre – two of which seem to be headed up by equally “inexperienced” developers:
(Incidentally, this may be a good indicator that we should start seeing movement on Brightside and Thind Towers very soon…)
Spring-ish of 2019 was when I started working with the psycho who I talked about in earlier posts. We were working on value engineering about $2 million off of the project, including cutting an entire level of parking out of the basement, and reducing the size of the rooftop crown.
So that’s another major departure from the norm – trying to value engineer $2 million or so out of the project after you’ve been selling for 9 months? And trying to remove whole levels of parking after having an approved development permit and an in-stream building permit?
The whole thing is just bizarre.
I guess when the inevitable lawsuits start flying, the truth will come out…