Originally Posted by wave46
It depends.
If that 4 lane highway is through farmland/prairie and will likely need 6 lanes in the future, sure.
If it's a 4 lane highway blasted through a mountain of rock, you need to blast that big median too. If there's no foreseeable need for 6 lanes eventually, why bother? Sure, you have to account for fill in other areas of the project, but still.
|
That's what I used to think too, until someone who works in road building (not sonysnob aka AsphaltPlanet this time lol) told me that rock blasting is actually a matter of economy of scale. Let me find that quote.
Granted, it's a bit technical and even I have a hard time following. These are replies to my post too.
Quote:
|
So it's just a question of width of your cut. Which is less of a factor than the question of whether you need to do it in the first place
|
Quote:
|
Originally Posted by me
Oh, is it like, if rock blasting needs to happen anyway, a shorter width won’t significantly reduce cost?
|
Quote:
|
Yes once you've got the crews deployed it's an economy of scale.
|
I looked that up a few days later just to verify, and the stuff that I read actually backed up what he said.
Now, I need sonysnob to take over the mic.