Fencing is now up on east side both north and south of tracks. Equipment and piping on site as well. Looks like they are starting the utilities moves.
Reply With Quote
     
     
  #82  
Old Posted Aug 26, 2020, 3:04 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
Slowly working on the utility moves. Tunnelling the temporary watermain on east side of Adelaide. Fencing now around the car wash as it has closed. Gas Bar was demolished a while ago. No sign of the house being demolished yet or any other utility relocates. That would need to happen to shift Adelaide road traffic over to east side.
Reply With Quote
     
     
  #83  
Old Posted Aug 26, 2020, 8:31 PM
Djeffery's Avatar
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,292
Quote:
Originally Posted by jammer139 View Post
Slowly working on the utility moves. Tunnelling the temporary watermain on east side of Adelaide. Fencing now around the car wash as it has closed. Gas Bar was demolished a while ago. No sign of the house being demolished yet or any other utility relocates. That would need to happen to shift Adelaide road traffic over to east side.
Last I heard, traffic was going to be moved to the west side. Was that changed in a later plan?
Reply With Quote
     
     
  #84  
Old Posted Aug 27, 2020, 7:51 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
Always thought the bypass traffic was on being rerouted east side. Hopefully the answer will be shown early next year.
Reply With Quote
     
     
  #85  
Old Posted Aug 27, 2020, 9:48 PM
Djeffery's Avatar
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,292
I guess it was changed. Went back through the thread and looked at the public meeting slides. PIC 2 showed west side, PIC 3 a year later showed it switched to east side to better work with the favoured utility corridor.
Reply With Quote
     
     
  #86  
Old Posted Sep 2, 2020, 11:13 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
Some legal moves ahead of the work involving transferring some land to CPR.


https://pub-london.escribemeetings.com/filestream.ashx?DocumentId=74170
Reply With Quote
     
     
  #87  
Old Posted Sep 17, 2020, 8:22 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
Car wash being demolished today. No signs that the house on the SE corner has been vacated yet so it can be demolished.
Reply With Quote
     
     
  #88  
Old Posted Oct 9, 2020, 11:32 AM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
Car wash is now gone. This is were the sewer management systems will be located. The work on east side appears to be complete for the moment. Not sure what they buried there for the utility moves but they have stopped working.
Reply With Quote
     
     
  #89  
Old Posted Oct 16, 2020, 7:51 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
The old autobody shop on SW corner was taken down today. CP rail crews have been clearing the land on north side of tracks this week for their installation of temporary track(s). Not clear yet if they will build a single or double temp bypass track(s). Still to come is the old building on SE corner at Central and Adelaide.
Reply With Quote
     
     
  #90  
Old Posted Oct 25, 2020, 6:22 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
The house on the SE corner is now down. Clearing the rubble and filling the basement hole is left.
Reply With Quote
     
     
  #91  
Old Posted Oct 27, 2020, 6:16 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
CPR crew installing new track on north side of existing twin tracks.
Reply With Quote
     
     
  #92  
Old Posted Nov 6, 2020, 9:03 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
Adelaide closing this weekend for next phase of CPR track realignment.


https://london.ca/newsroom/road-closure-...etween-central-avenue-pall-mall-street-0
Reply With Quote
     
     
  #93  
Old Posted Nov 11, 2020, 4:50 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
Adelaide at CPR to be closed again this weekend Nov 14-15.


Also the Frank and Gus Pizza will be demolished in the near future it seems.
Reply With Quote
     
     
  #94  
Old Posted Jan 8, 2021, 4:39 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
Fencing now up around Frank and Gus Pizza and the 2 homes immediately north. CP Rail is doing work along the park edge now.
Reply With Quote
     
     
  #95  
Old Posted Feb 1, 2021, 9:58 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
North bound Adelaide street has been down to one lane for over a week now as they are installing underground utility conduits south of Central Ave. Would expect work to start on the east side temporary roadway in the coming months. Should see the piling machines after that to sink the support pilings for the bypass rail line.
Reply With Quote
     
     
  #96  
Old Posted Mar 14, 2021, 9:25 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
Frank and Gus Pizza building is now gone. The two homes immediately to the north are also fenced off and may also be going to be demolished soon.
Reply With Quote
     
     
  #97  
Old Posted Mar 15, 2021, 2:36 PM
MolsonExport's Avatar
MolsonExport MolsonExport is offline
Touching grass everyday.
 
Join Date: Oct 2003
Location: Otisburgh
Posts: 51,422
one of the best pizza joints in London (Frank & Gus). Also, Cyprus Pizza in Lambeth.

way, way better than the cardboard crap sold at Dominos, PizzaPizza and Little Caesars
__________________
The whole problem with the world is that fools and fanatics are always so certain of themselves, and wiser people so full of doubts. (Bertrand Russell). Sweet Loretta fart thought she was a cleaner, but she was a frying pan. (John Lennon)
Reply With Quote
     
     
  #98  
Old Posted Mar 16, 2021, 3:36 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
Now removing the Frank and Gus basement walls. Should be backfilled within the next day or two.
Reply With Quote
     
     
  #99  
Old Posted Mar 29, 2021, 10:15 AM
Djeffery's Avatar
Djeffery Djeffery is online now
Registered User
 
Join Date: Oct 2017
Location: London
Posts: 6,292
Reply With Quote
     
     
  #100  
Old Posted May 2, 2021, 12:34 PM
jammer139 jammer139 is online now
Registered User
 
Join Date: Jun 2016
Location: London
Posts: 9,298
Based on mtg on April 21st the tender isn't being awarded now until the Fall 2021. This is a delay if I'm not mistaken.


https://getinvolved.london.ca/adelaide
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > London > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 2:23 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.