Quote:
Originally Posted by Corndogger
It's really unfortunate that the construction expert dude was forced out. He seemed to know what he was talking about and didn't sugarcoat things. I'm pretty sure he said it would cost $7.7 billion to do this right and nothing I've seen since then makes his estimate look wrong. With the huge downturn we might be able to get some good deals and could save hundreds of millions of dollars. I'd rather spend the extra money and do this right than spend $5+ billion on a project that benefits very few.
|
It’s going to cost a lot more than $7.7 billion to build out North and South or are you just talking North? If we’ve learned anything, it’s the Green Line estimates have been grossly lowballed.
Reading the Green line financing document:
Phase 1 is now budgeted to cost $5.5 billion dollars ($640 million in financing costs + $4.9 billion in construction costs).
Over $500 million has already been spent on the Green Line (a new arena’s worth of paper shuffling).
Capital spending ends in 2028, I’m assuming the EPC and Commissioning of Phase 1 is going to be 7 years. Anyone seen a Phase 1 schedule? Any bets on when Phase 1 is opened to the public to ride on?
A reminder of how the City is funding its portion of the project, by borrowing against future property tax room out to 2044. There’s no budget money for phase 2 expansion regardless of how we build stage 1 (i.e. cross the bow or not to cross the bow). But hey, why worry we don’t have a budget for phase 2 expansion, just get on with it and hope the piecemeal expansion of 15 stations and 26 km of track happens before we are all dead. Hint: Maybe we should build one good line now in Phase 1!
Total funding for the Stage 1 Program is $5,544 million from all sources (2015-2044), including $4,903 million for capital and $639.9 million for financing costs, with contributions from The City ($2,200 million), the Government of Alberta ($1,702 million) and Government of Canada ($1,640 million) across multiple grant programs.
As of 2020 April 30, the actual Program spend year-to-date is $19.1 million and the cumulative Program spend is $543.8 million. Total Program commitments as of 2020 April 30 are $673.7 million. The budget currently approved is $803.9 million.
The City of Calgary approved up to $2,200 million (or up to $75.7 million per year) of property tax dollars for funding the Stage 1 Program, including the:
1. 2013 tax room (2015-2044) - $1,560 million (or $52 million per year for 30 years)
2. 2017 tax room (2018-2044) - $640 million (or $23.7 million per year for 27 years)
The City is solely responsible for any financing costs associated with the Program.
https://pub-calgary.escribemeetings.com/filestream.ashx?DocumentId=131783
https://pub-calgary.escribemeetings.com/filestream.ashx?DocumentId=131780