When they revealed the rendering for Cleary in February 2018, it was a major bummer. I was super excited about having one underground urban station and that was taken away.
In Toronto, Montreal and Vancouver, urban stations are underground. Heck, in Toronto they spend billions for underground subways with mega huge stations in empty fields (Vaughn extension). At the very least, we should have buried the stations along the urban stretch of the line (Dominion, Cleary, New Orchard, Lincoln Fields).
I hope to see the Scott Street trench covered overtime. We constantly hear City planners and suburban Councillors talk about how the city's core lacks parks. Well, that's a way to add parks for a relatively affordable cost.
As for the length of the platforms, it seems all over the place. I'm not sure where you got your numbers
OCCheetos, I'm measuring 100 meters for the three east end stations you mentioned, both Byron Strip stations at 120 meters and Lincoln Fields at 100 meters. A few 90 meter stations (such as Place d'Orleans) show a 10 meter future extension.
Here's a complete list:
100 meters:
- Orleans
- Jeanne d'Arc
- Montreal
- Lincoln Fields
90 meters with 10 meter future extension:
- Trim
- Place d'Orleans
- Westboro
- Dominion
- Iris
- Queensview
- Pinecrest
- Bayshore
- Moodie
120 meters:
- Cleary
- New Orchard
Stage 1 stations are all 90 meters with 10 meter future extensions, except for the three Downtown tunnel stations that are 120 meters.
Initially, when Stage 1 contract was awarded, the plan was to have 90 meters for above ground stations, expandable to 120 meters in the future. The City has now figured out that, with the Alstom Citadis, you can have your future 118 meter trains dock at 100 meter platforms with the ends sticking out. This will be an issue if one day we buy trains that are not Alstom Citadis. Maybe fully automated trains with doors closer to the ends. That might explain why they are still building out at 120 meters where future expansion could prove difficult (Byron strip).