Quote:
Originally Posted by foolworm
To be fair, Edmonton is infamously tight-fisted when it comes to capital spending (the arena being a notable recent exception). It's actually amazing how they've done a complete 180 and embarked on an LRT building spree - not only are they building both legs of the Valley Line back-to-back, they somehow managed to also wrangle cash for an extension to the old municipal airport, not to mention a mid-life refurbishment of their original line. On top of that the City is now requesting stimulus funding from the Provincial government for a second extension south, past the ring road (Anthony Henday Drive).
|
Yeah, the previous and current City Councils have been very pro-LRT thankfully.
The 2-station (one being a relocated NAIT station) Metro extension to Blatchford starts construction this year and Valley Line West next year I believe.
Five years from now (
assuming everything stays on schedule), we will see the current LRT system more than double in length, from 24.4 km to 52.3 km.
Looking to 2030, the Capital Line South extension to 41 Avenue SW will extend this to around 60 km (as long as funding for detailed design and construction becomes available within the next few years).