Some more updates on the west leg of 201.
Bow River Bridge
Looking south at the bridge abutment and piers on the north side of the river
Looking north at one of the two bridge piers and abutment on the north side of the river
The start of in-river berm construction, April 8, 2020
In-river berm construction, April 10, 2020
North Project
Girder Installations on Basketweave Bridge North of Trans-Canada Highway
There are three "basketweave" bridges on the North project. Basketweave bridges are used to separate weaving traffic. Weaving is caused by vehicles merging and exiting in the same area which creates congestion. In this case, the traffic merging onto westbound Trans-Canada Highway is separated from the traffic exiting the Trans-Canada Highway to go north on Valley Ridge Blvd NW.
Preparing the first girder for installation