Old Posted Feb 28, 2020, 7:52 AM
Pedestrian's Avatar
Pedestrian Pedestrian is offline
Elite Member
 
Join Date: Dec 2016
Location: San Francisco
Posts: 24,128
Quote:
Originally Posted by timbad View Post
getting back to the Van Ness theme
^^For some reason they decided to start by doing half the utilities on the west side (the southern half of Van ness) and half the utilities on the east side (northern half of Van Ness). On each half they've finished the side they started and are doing the other side with some bits already finished.

According to this schedule:


https://www.sfmta.com/projects/van-ness-improvement-project

they should actually be about to start work on the center BRT lanes (boarding islands, catenary, paving etc) any time now and winding up the utility work by fall.
     
     
  #10182  
Old Posted Feb 28, 2020, 7:58 AM
Pedestrian's Avatar
Pedestrian Pedestrian is offline
Elite Member
 
Join Date: Dec 2016
Location: San Francisco
Posts: 24,128


Where have all the corner boys gone?

As most of you know, I've been away from SF since October and looking at these pics plus those in such as sopas ej's travel photos, the city really looks cleaner to me with many fewer folks camped on the sidewalks and so on. Is my impression correct? Can we thank Mayor Breed (it's what she promised)?
     
     
  #10183  
Old Posted Feb 29, 2020, 5:32 AM
timbad timbad is offline
heavy user of walkability
 
Join Date: May 2008
Location: Mission Bay, San Francisco
Posts: 3,148
Quote:
Originally Posted by viewguysf View Post
...
Panoramic Interests' City Gardens at 333 12th Street (near The Eagle) was always being developed as student housing; I've gone on several hard hat tours through there.
this was the hearing notice I was reading (edit: the summarized version, of course; the kind that gets posted outdoors), which, when reading quickly, looks like a recent conversion request

Last edited by timbad; Feb 29, 2020 at 5:49 AM.
     
     
  #10184  
Old Posted Feb 29, 2020, 6:38 AM
timbad timbad is offline
heavy user of walkability
 
Join Date: May 2008
Location: Mission Bay, San Francisco
Posts: 3,148
Quote:
Originally Posted by Pedestrian View Post
I sure wish they'd "just build" the "Monster in the Mission" on that very corner but I've lost track of its status:

...
the answer
     
     
  #10185  
Old Posted Feb 29, 2020, 10:01 PM
timbad timbad is offline
heavy user of walkability
 
Join Date: May 2008
Location: Mission Bay, San Francisco
Posts: 3,148
Teatro Zinzanni

yay, Teatro Zinzanni finally got approvals

Quote:
Groundbreaking is planned for the fall, with a reopening targeted for 2022 as part of a larger project with a hotel and park. The whole project will cost about $145 million.

...
Teatro ZinZanni is partnering with Kenwood Investments LLC and Presidio Hotel Group on the project, and the venue will share the property with a 192-room hotel and a 14,000-square-foot park.

Last edited by timbad; Mar 5, 2020 at 5:05 AM. Reason: added article snip
     
     
  #10186  
Old Posted Mar 5, 2020, 2:25 AM
Iceman12 Iceman12 is offline
Registered User
 
Join Date: Nov 2019
Location: San Francisco, CA
Posts: 41
Quote:
Originally Posted by Iceman12 View Post
Does anyone have an update on 1629 Market Street? Strada closed on funding in April.

https://www.blaujournal.com/strada-inves...for-1629-market-street-in-san-francisco/
Answering my own question:

https://hoodline.com/2020/03/5-market-st...o-close-as-new-development-gets-underway
     
     
  #10187  
Old Posted Mar 5, 2020, 5:28 AM
timbad timbad is offline
heavy user of walkability
 
Join Date: May 2008
Location: Mission Bay, San Francisco
Posts: 3,148
Quote:
Originally Posted by Iceman12 View Post


I'm not enthused by the style on all the buildings, but am quite happy this block is being activated to contribute to the transformation of the neighborHub
     
     
  #10188  
Old Posted Mar 5, 2020, 7:31 PM
AndrewK AndrewK is offline
Registered User
 
Join Date: Mar 2008
Location: San Francisco
Posts: 459
This (along with 10 S. Van Ness) will aid greatly in improving the stretch of Market between Octavia and Van Ness. The three other projects either underway or recently completed on this stretch (Flax, Fast Frame, 1554 Market) have filled in the majority of the other gaps.

Now if only the project at 1740-1772 would get underway:
https://socketsite.com/archives/2016/07/...on-market-in-the-works-and-rendered.html
     
     
  #10189  
Old Posted Mar 7, 2020, 3:02 AM
AndrewK AndrewK is offline
Registered User
 
Join Date: Mar 2008
Location: San Francisco
Posts: 459
Quote:
Originally Posted by Pedestrian View Post
^^For some reason they decided to start by doing half the utilities on the west side (the southern half of Van ness) and half the utilities on the east side (northern half of Van Ness). On each half they've finished the side they started and are doing the other side with some bits already finished.

According to this schedule:


https://www.sfmta.com/projects/van-ness-improvement-project

they should actually be about to start work on the center BRT lanes (boarding islands, catenary, paving etc) any time now and winding up the utility work by fall.
Took a trip up and down Van Ness today to see how the progress is going.

They are at various stages of work on the east side between Mcallister and Geary (they have poured pretty much all the curbs but only a few blocks of sidewalk, and have only repaved the traffic lanes on the first couple blocks). Presumably they will get to the northernmost blocks of this portion (Geary to Sutter-ish) shortly.

On the northern portion of the west side of the street they look to be nearing completion on infrastructure work and should start pouring concrete soon.
     
     
  #10190  
Old Posted Mar 12, 2020, 6:18 PM
Pedestrian's Avatar
Pedestrian Pedestrian is offline
Elite Member
 
Join Date: Dec 2016
Location: San Francisco
Posts: 24,128
Quote:
SF Central Subway project rolling along

MARCH 11, 2020 BY MARK PRADO

The San Francisco Municipal Transportation Authority has shared a Central Subway project construction update via video.

Last year saw milestones for the project, including the reopening of Stockton Street through Chinatown and Union Square as well as some of the major final touches to the stations like escalators and public art, according to the agency.

The project aims to wrap-up most construction this summer followed by about a year of testing to make sure the trains run properly. After the testing period, the Central Subway is projected to begin service in the fall of 2021.
https://blog.bayareametro.gov/posts/sf-central-subway-project-rolling-along
     
     
  #10191  
Old Posted Mar 12, 2020, 10:00 PM
Jerry of San Fran's Avatar
Jerry of San Fran Jerry of San Fran is offline
Registered User
 
Join Date: Jun 2007
Location: San Francisco
Posts: 1,567
Pedestrian - thanks for posting the link. I've been wondering what was happening under the ground. I may yet live to ride on the new subway!
__________________
(Essex) Fox Plaza resident 54th year in 2025 - (the building everyone loves to hate :------>))
     
     
  #10192  
Old Posted Mar 12, 2020, 10:08 PM
Pedestrian's Avatar
Pedestrian Pedestrian is offline
Elite Member
 
Join Date: Dec 2016
Location: San Francisco
Posts: 24,128
Quote:
Originally Posted by Jerry of San Fran View Post
Pedestrian - thanks for posting the link. I've been wondering what was happening under the ground. I may yet live to ride on the new subway!
^^Did you watch the video?

PS: If you want to live to ride it, stay off Muni until it opens.
     
     
  #10193  
Old Posted Mar 13, 2020, 10:40 PM
BobbyMucho BobbyMucho is offline
Registered User
 
Join Date: Apr 2018
Posts: 284
After reading about 469 Stevenson on Socketsite I saw that there may also be some progress (finally) on 1125 Market, just a block away.

It appears a building permit was filed late December for a 14-story / 180-room hotel.

Here's the rendering I found via the engineer's site for the Woods Bagot designed structure:



I was surprised to learn that, according to 469 Stevenson's EIR, there are 16 or so active proposals within quarter-mile of the project.
     
     
  #10194  
Old Posted Mar 14, 2020, 4:38 AM
Pedestrian's Avatar
Pedestrian Pedestrian is offline
Elite Member
 
Join Date: Dec 2016
Location: San Francisco
Posts: 24,128
Quote:
Originally Posted by BobbyMucho View Post
After reading about 469 Stevenson on Socketsite I saw that there may also be some progress (finally) on 1125 Market, just a block away.

It appears a building permit was filed late December for a 14-story / 180-room hotel.
Fantastic (not the design but the fact of something being built there).
     
     
  #10195  
Old Posted Mar 14, 2020, 3:07 PM
Jerry of San Fran's Avatar
Jerry of San Fran Jerry of San Fran is offline
Registered User
 
Join Date: Jun 2007
Location: San Francisco
Posts: 1,567
Pedestrain - yes, of course. I did watch the video.
__________________
(Essex) Fox Plaza resident 54th year in 2025 - (the building everyone loves to hate :------>))
     
     
  #10196  
Old Posted Mar 14, 2020, 10:14 PM
Pedestrian's Avatar
Pedestrian Pedestrian is offline
Elite Member
 
Join Date: Dec 2016
Location: San Francisco
Posts: 24,128
Quote:
Originally Posted by Jerry of San Fran View Post
Pedestrain - yes, of course. I did watch the video.
Sorry but I get the impression a lot of people on this site might not have and that's the really informative part of the thing I posted. Some people don't even click on links it seems like.
     
     
  #10197  
Old Posted Mar 18, 2020, 1:16 AM
Jerry of San Fran's Avatar
Jerry of San Fran Jerry of San Fran is offline
Registered User
 
Join Date: Jun 2007
Location: San Francisco
Posts: 1,567
No workers today at Trinity Place IV on the 1st shelter in place day. Are all of the jobs sites now idle?!
__________________
(Essex) Fox Plaza resident 54th year in 2025 - (the building everyone loves to hate :------>))
     
     
  #10198  
Old Posted Mar 18, 2020, 2:51 AM
Iceman12 Iceman12 is offline
Registered User
 
Join Date: Nov 2019
Location: San Francisco, CA
Posts: 41
Quote:
Originally Posted by Jerry of San Fran View Post
No workers today at Trinity Place IV on the 1st shelter in place day. Are all of the jobs sites now idle?!
According to the Chronicle:

The order allows all housing projects to continue — market rate, affordable, and mixed-use — while construction projects that are strictly commercial must temporaily shut down.

https://www.sfchronicle.com/local-politi...-for-the-Bay-15136169.php#photo-19182220
     
     
  #10199  
Old Posted Mar 19, 2020, 8:50 AM
Jerry of San Fran's Avatar
Jerry of San Fran Jerry of San Fran is offline
Registered User
 
Join Date: Jun 2007
Location: San Francisco
Posts: 1,567
Iceman12 - thanks for the explanation!
__________________
(Essex) Fox Plaza resident 54th year in 2025 - (the building everyone loves to hate :------>))
     
     
  #10200  
Old Posted Mar 22, 2020, 11:36 AM
timbad timbad is offline
heavy user of walkability
 
Join Date: May 2008
Location: Mission Bay, San Francisco
Posts: 3,148
the Gate E area of the ferry terminal has re-opened



a sneak peek at the new plaza



     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Global Projects & Construction > City Compilations
Forum Jump



Forum Jump


All times are GMT. The time now is 7:21 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.