Got an email this morning from Alberta Transportation saying that some tree and brush clearing is going to start in early February in preparation for start of construction on the South segment in the spring. So it looks like all is proceeding very smoothly on this last stage of 201.

https://westringroad.ca/wp-content/uploads/2019/12/RPR_WCRR_24x36_treeclearing_121619.pdf

https://westringroad.ca/south-project/

Info Session

Wednesday, January 29, 2020
5 – 7 pm
Elbow Springs Golf Club
240086 Lott Creek Drive
Reply With Quote
     
     
  #7642  
Old Posted Jan 24, 2020, 5:43 AM
craner's Avatar
craner craner is offline
Go Tall or Go Home
 
Join Date: Mar 2007
Location: Calgary
Posts: 7,418
Reply With Quote
     
     
  #7643  
Old Posted Jan 29, 2020, 6:29 PM
eloy eloy is offline
Registered User
 
Join Date: Oct 2012
Posts: 8
They'll start tearing down the old overpass at Glenmore and 37th. Full closures of Glenmore coming up
http://www.swcrrproject.com/wp-content/u...-and-37th-ST-SW-Bridge-Demoliti.._-1.pdf
Reply With Quote
     
     
  #7644  
Old Posted Jan 29, 2020, 7:10 PM
Hackslack Hackslack is offline
Registered User
 
Join Date: Dec 2015
Posts: 2,889
When is the ring road supposed to be complete?
Reply With Quote
     
     
  #7645  
Old Posted Jan 29, 2020, 7:19 PM
lubicon's Avatar
lubicon lubicon is offline
Suburban dweller
 
Join Date: Jun 2003
Location: Calgary - our road planners are as bad as yours Edmonton
Posts: 5,047
Quote:
Originally Posted by Hackslack View Post
When is the ring road supposed to be complete?
2022, website does not specify which month however.
__________________
Two things are infinite: the universe and human stupidity; and I'm not sure about the the universe.

Albert Einstein
Reply With Quote
     
     
  #7646  
Old Posted Jan 29, 2020, 8:36 PM
Corndogger Corndogger is offline
Registered User
 
Join Date: Sep 2007
Location: Calgary
Posts: 7,727
Quote:
Originally Posted by lubicon View Post
2022, website does not specify which month however.
The SW leg is supposed to open in the fall of 2021 and the West leg a year later. I'm really impressed at how fast the West leg is coming along.
Reply With Quote
     
     
  #7647  
Old Posted Jan 30, 2020, 6:11 AM
Pegasus's Avatar
Pegasus Pegasus is offline
Registered User
 
Join Date: Jul 2008
Posts: 532
Quote:
Originally Posted by eloy View Post
They'll start tearing down the old overpass at Glenmore and 37th. Full closures of Glenmore coming up
http://www.swcrrproject.com/wp-content/u...-and-37th-ST-SW-Bridge-Demoliti.._-1.pdf
The "old" overpass was only built in 2010, so not so old! (Note: The project was temporary, some new approaches to construction were permitted having a design life of only 15-20 years. https://www.ucalgary.ca/EN/Civil/csce_calgary/2011/G37_Presentation_CSCE.pdf )
Reply With Quote
     
     
  #7648  
Old Posted Jan 30, 2020, 6:24 AM
Porfiry Porfiry is offline
Registered User
 
Join Date: May 2010
Posts: 802
Quote:
Originally Posted by Pegasus View Post
The "old" overpass was only built in 2010, so not so old! (Note: The project was temporary, some new approaches to construction were permitted having a design life of only 15-20 years. https://www.ucalgary.ca/EN/Civil/csce_calgary/2011/G37_Presentation_CSCE.pdf )
I wonder if they will be actually dismantling the bridge and reusing the girders, as was touted when it went up. The SWCRR site says "demolition", which does not sound promising.
Reply With Quote
     
     
  #7649  
Old Posted Jan 30, 2020, 11:55 PM
ImmortalHawk ImmortalHawk is offline
Registered User
 
Join Date: Nov 2017
Posts: 35
Quote:
Originally Posted by Pegasus View Post
The "old" overpass was only built in 2010, so not so old! (Note: The project was temporary, some new approaches to construction were permitted having a design life of only 15-20 years. https://www.ucalgary.ca/EN/Civil/csce_calgary/2011/G37_Presentation_CSCE.pdf )
I noticed with the pdf that there were designs for a small Richard Road interchange. Does anyone know anything about the intersection or if certain measures will be implemented to alleviate the traffic after SWCRR opens?
Reply With Quote
     
     
  #7650  
Old Posted Feb 3, 2020, 11:01 PM
Corndogger Corndogger is offline
Registered User
 
Join Date: Sep 2007
Location: Calgary
Posts: 7,727
Got an email this afternoon providing an update on the West leg. This part of the email was the most interesting and pertains to the North Project section.

Construction Progress Update

The two interchanges on the north project – at Valley Ridge Blvd NW and Stoney Trail – require a total of 20 bridges. Piling for the bridge foundations is about 35 percent complete, with about 350 steel piles now in place. Each pile is placed about 30m (100ft) into the ground to create the strength to support the bridge.

Once the bridge foundations are complete, the next step is to form the bridge abutments (the "book ends" on either side of a bridge). Six concrete bridge abutments have been poured using close to 600 cubic meters of concrete (equivalent to filling about 350 bathtubs).

Concrete girder fabrication has also started at a facility in Edmonton. The girders are the beams (sometimes called I-beams) that form the structure of the bridge deck. They will be transported from Edmonton for installation starting this spring.
Reply With Quote
     
     
  #7651  
Old Posted Feb 17, 2020, 10:08 PM
Corndogger Corndogger is offline
Registered User
 
Join Date: Sep 2007
Location: Calgary
Posts: 7,727
Received another email this afternoon with updates on the West leg of 201. I'm going to split this into multiple posts.

Bow River Bridge Twinning Project Construction Update

Now that the area on the south side of the river has been cleared and the staircase is open to access the pedestrian bridge, piling for the south bridge abutment and pier has begun.

Bridge construction on the north side of the river continues.



Reply With Quote
     
     
  #7652  
Old Posted Feb 17, 2020, 10:11 PM
Corndogger Corndogger is offline
Registered User
 
Join Date: Sep 2007
Location: Calgary
Posts: 7,727
West leg 201 update

North Project Construction Update

Currently, 11 bridges are in various stages of construction. Some are taking recognizable shape above the ground, while others are just getting underway with piling for the bridge foundations. Bridge construction will continue to be the contractors’ focus over the next several months.

Reply With Quote
     
     
  #7653  
Old Posted Feb 17, 2020, 10:13 PM
Corndogger Corndogger is offline
Registered User
 
Join Date: Sep 2007
Location: Calgary
Posts: 7,727
West leg 201 update

South Project Update

Tree & Brush Clearing Begins

Crews will be onsite this week preparing for tree and brush clearing, which begins on Thursday, February 20. Removals are expected to start at Old Banff Coach Road SW and move progressively south. More information about the tree and brush clearing is available online.

Safety is a top priority for the Government of Alberta and our contractors. Residents and all members of the public are reminded to stay out of the Transportation Utility Corridor as it is an active construction site.
Reply With Quote
     
     
  #7654  
Old Posted Feb 19, 2020, 12:52 PM
toddlakes toddlakes is offline
Registered User
 
Join Date: Jul 2019
Location: Culver City, CA
Posts: 4
Quote:
Originally Posted by Corndogger View Post
Got an email this afternoon providing an update on the West leg. This part of the email was the most interesting and pertains to the North Project section.

Construction Progress Update

The two interchanges on the north project – at Valley Ridge Blvd NW and Stoney Trail – require a total of 20 bridges. Piling for the bridge foundations is about 35 percent complete, with about 350 steel piles now in place. Each pile is placed about 30m (100ft) into the ground to create the strength to support the bridge.

Once the bridge foundations are complete, the next step is to form the bridge abutments (the "book ends" on either side of a bridge). Six concrete bridge abutments have been poured using close to 600 cubic meters of concrete (equivalent to filling about 350 bathtubs).

Concrete girder fabrication has also started at a facility in Edmonton. The girders are the beams (sometimes called I-beams) that form the structure of the bridge deck. They will be transported from Edmonton for installation starting this spring.
This design reminds me of the Tuskons Bridge. We use some cool resources to find the historical value of bridges in the United States. These resources https://phdessay.com/free-essays-on/countries/ collaborate with students who need literacy help. The main task of such resources is the search and processing of information. I read several essays on the creation of the Tucson Bridge in Virginia
Reply With Quote
     
     
  #7655  
Old Posted Feb 24, 2020, 11:12 PM
Corndogger Corndogger is offline
Registered User
 
Join Date: Sep 2007
Location: Calgary
Posts: 7,727
Bow River Bridge Project



Reply With Quote
     
     
  #7656  
Old Posted Feb 25, 2020, 12:43 AM
s211 s211 is offline
Registered User
 
Join Date: Oct 2008
Location: The People's Glorious Republic of ... Sigh...
Posts: 8,519
Quote:
Originally Posted by Corndogger View Post
Bow River Bridge Project



Honest question: didn't Calgary have a moratorium on new river crossings?
__________________
If it seems I'm ignoring what you may have written in response to something I have written, it's very likely that you're on my Ignore List. Please do not take it personally.
Reply With Quote
     
     
  #7657  
Old Posted Feb 25, 2020, 4:56 AM
craner's Avatar
craner craner is offline
Go Tall or Go Home
 
Join Date: Mar 2007
Location: Calgary
Posts: 7,418
Not sure about that s211 - perhaps crossings “already planned” are exempt.

Thanks for sharing the updates Corndogger.
Reply With Quote
     
     
  #7658  
Old Posted Feb 25, 2020, 8:13 AM
Corndogger Corndogger is offline
Registered User
 
Join Date: Sep 2007
Location: Calgary
Posts: 7,727
Quote:
Originally Posted by craner View Post
Not sure about that s211 - perhaps crossings “already planned” are exempt.

Thanks for sharing the updates Corndogger.
IIRC the Go Plan from the 1990s had or was supposed to have a moratorium on river crossings but I believe that plan died a long time ago. I also doubt the City could stop the province from building river crossings that were part of provincial highway projects.
Reply With Quote
     
     
  #7659  
Old Posted Feb 25, 2020, 7:19 PM
lubicon's Avatar
lubicon lubicon is offline
Suburban dweller
 
Join Date: Jun 2003
Location: Calgary - our road planners are as bad as yours Edmonton
Posts: 5,047
Quote:
Originally Posted by Corndogger View Post
IIRC the Go Plan from the 1990s had or was supposed to have a moratorium on river crossings but I believe that plan died a long time ago. I also doubt the City could stop the province from building river crossings that were part of provincial highway projects.
This more than anything else. IIRC the City doesn't plan on any more river crossing's but they can't stop other jurisdictions from crossing the river.
__________________
Two things are infinite: the universe and human stupidity; and I'm not sure about the the universe.

Albert Einstein
Reply With Quote
     
     
  #7660  
Old Posted Feb 26, 2020, 12:54 AM
Pegasus's Avatar
Pegasus Pegasus is offline
Registered User
 
Join Date: Jul 2008
Posts: 532
Quote:
Originally Posted by lubicon View Post
This more than anything else. IIRC the City doesn't plan on any more river crossing's but they can't stop other jurisdictions from crossing the river.
The updated Green Line Route includes a new river crossing . . . https://secure.campaigner.com/CSB/Public/archive.aspx?args=NDEwODIzMjU%3d&acc=NTgxNDIw
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Calgary > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 12:38 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.