HomeDiagramsDatabaseMapsForum About
     

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure


View Poll Results: Would you like to separate this thread for individual station projects?
Yes 19 31.15%
No 42 68.85%
Voters: 61. You may not vote on this poll

Reply

 
Thread Tools Display Modes
     
     
  #3621  
Old Posted Oct 26, 2019, 7:30 AM
Migrant_Coconut's Avatar
Migrant_Coconut Migrant_Coconut is offline
Registered User
 
Join Date: Oct 2015
Location: Kitsilano/Fairview
Posts: 10,059
Quote:
Originally Posted by Waders View Post
Uncertainty over new pedestrian bridge from SkyTrain Metrotown Station to mall

This doesn't look good.
I guess if the mall is really going to disappear in a few decades, then may be there is no need for the new pedestrian bridge.
Author: Kenneth Chan. Well-researched gossip is still gossip; funding and construction have been confirmed for a 2020-23 window.
Reply With Quote
     
     
  #3622  
Old Posted Oct 26, 2019, 5:03 PM
Sheba Sheba is offline
Registered User
 
Join Date: Jan 2015
Location: BC
Posts: 4,587
Quote:
Originally Posted by Migrant_Coconut View Post
Author: Kenneth Chan. Well-researched gossip is still gossip; funding and construction have been confirmed for a 2020-23 window.
Exactly. He brings up the 'bus loop around the station' thing again too - despite it being shot down years ago.
Reply With Quote
     
     
  #3623  
Old Posted Oct 28, 2019, 5:59 AM
Waders Waders is offline
Registered User
 
Join Date: May 2009
Posts: 1,361
Well. There is still a lot of uncertainty in various areas.
Funding was originally allocated for the project in 2019 but part of it was reallocated to other project. Same thing might happen again next year.

According to Burnaby’s new director of planning and building, Ed Kozak, planners are considering whether to severely constrain traffic on Central Boulevard, or maybe even close it. If that happens, a new footbridge across the street might not be needed.

Ivanhoé Cambridge, the mall owner, is now starting the mall redevelopment planning. According to Graeme Silvera, the vice-president for development and retail, the first phase in the next decade will be in the parking lots facing Kingsway. Though it will take a few decades, but eventually the existing bus loop will need to be removed when the site is ready for redevelopment. Where can the bus stops be moved?

Source: Burnaby finalizes plan to overhaul Metropolis mall into walkable city centre
Reply With Quote
     
     
  #3624  
Old Posted Nov 15, 2019, 4:12 AM
Waders Waders is offline
Registered User
 
Join Date: May 2009
Posts: 1,361
A&W has now open at Joyce station's retail location.
I wish Translink had built a bigger retail space there as the store only has 3 tables that can sit 12 people.
I wonder whether A&W can apply to put some extra tables outside the store.
Reply With Quote
     
     
  #3625  
Old Posted Nov 15, 2019, 4:53 AM
MIPS's Avatar
MIPS MIPS is offline
SkyTrain Nut
 
Join Date: Mar 2013
Location: Kamloops
Posts: 2,076
It's a station, not a food court. I doubt they are expecting people to hang around.
Reply With Quote
     
     
  #3626  
Old Posted Nov 20, 2019, 6:38 PM
deasine deasine is offline
Vancouver Moderator
 
Join Date: Mar 2007
Posts: 5,747
Quote:
Originally Posted by Waders View Post
A&W has now open at Joyce station's retail location.
I wish Translink had built a bigger retail space there as the store only has 3 tables that can sit 12 people.
I wonder whether A&W can apply to put some extra tables outside the store.
Quote:
Originally Posted by MIPS View Post
It's a station, not a food court. I doubt they are expecting people to hang around.
The unusual bit to me is that there's ample space in the concourse as it is right now near the stairwell. Not sure why they didn't carve out more space for the retail unit, even if it's only the "long strip" on the South side of the station.
Reply With Quote
     
     
  #3627  
Old Posted Nov 20, 2019, 9:21 PM
flipper316 flipper316 is offline
Registered User
 
Join Date: Dec 2016
Posts: 887
Quote:
Originally Posted by deasine View Post
The unusual bit to me is that there's ample space in the concourse as it is right now near the stairwell. Not sure why they didn't carve out more space for the retail unit, even if it's only the "long strip" on the South side of the station.
Who cares . It's a skytrain station . You grab your food and scarf it down fast . Who the hell wants to hang out at a skytrain station any longer than they have to . Unless you're some homeless crackhead .
Reply With Quote
     
     
  #3628  
Old Posted Nov 20, 2019, 10:46 PM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,540
Arguably that retail space is part of the neighbourhood, as it is not enclosed within the station.
ie. it could be a pitstop on the BC Parkway.
So some amenities would be nice for it.


http://sitings.ca/wp/wp-content/uploads/2017/01/JoyceCollingwood_Vancouver_January2017.pdf
Reply With Quote
     
     
  #3629  
Old Posted Nov 20, 2019, 10:50 PM
Vin Vin is offline
Registered User
 
Join Date: Sep 2013
Posts: 8,732
Quote:
Originally Posted by flipper316 View Post
Who cares . It's a skytrain station . You grab your food and scarf it down fast . Who the hell wants to hang out at a skytrain station any longer than they have to . Unless you're some homeless crackhead .
Chill. Sometimes people (non-crakhead) do wait around at the skytrain station. Would be nice to have a warm place in the winter to have coffee while waiting for a friend who's late, etc. You just never know.

Walked by the other night and the new A&W below the guideways does bring in some cheer to that otherwise drab neighbourhood.

On the train platform, it does look really good with the new LED displays and shiny modern white tiles of the elevators and stairwell walls.
Reply With Quote
     
     
  #3630  
Old Posted Dec 17, 2019, 5:22 AM
dpogue dpogue is offline
Registered User
 
Join Date: Aug 2013
Posts: 766
New LED signs on the platform are installed and working at Holdom, and installed (but not working) at Sperling. It seems they reconsidered having just one sign and have installed two sets of them at both Sperling and Holdom. The mounting brackets are in the process of being installed at Brentwood and Gilmore.
Reply With Quote
     
     
  #3631  
Old Posted Dec 17, 2019, 10:54 AM
Mac Write Mac Write is offline
Registered User
 
Join Date: Dec 2008
Posts: 1,423
Is the Evergreen extension getting the colour displays as well for uniformity?
Reply With Quote
     
     
  #3632  
Old Posted Dec 17, 2019, 3:26 PM
dpogue dpogue is offline
Registered User
 
Join Date: Aug 2013
Posts: 766
Quote:
Originally Posted by Mac Write View Post
Is the Evergreen extension getting the colour displays as well for uniformity?
No. I've already submitted feedback about the lack of uniformity, but it makes sense. It's a waste of money to replace perfectly good screens that are barely 4 years old.
Reply With Quote
     
     
  #3633  
Old Posted Dec 17, 2019, 8:05 PM
Mac Write Mac Write is offline
Registered User
 
Join Date: Dec 2008
Posts: 1,423
Though the Canada Line could use them as backups for their displays
Reply With Quote
     
     
  #3634  
Old Posted Dec 18, 2019, 2:29 AM
Sheba Sheba is offline
Registered User
 
Join Date: Jan 2015
Location: BC
Posts: 4,587
$28M transfer kickstarts new Canada Line station construction

Quote:
Construction of a new Canada Line station will soon get underway following the transfer of millions of dollars in developer-supported funds from the City of Richmond to Translink.

In a statement issued Tuesday, the city announced it has handed over $28 million to the transit authority to begin plans for the construction of Capstan Station.

The latest addition to the Canada Line will be built in the area of No. 3 Road and Capstan Way, between the existing Bridgeport and Aberdeen stations. The city hopes it will accommodate the roughly 6,000 new residential units in the Capstan Village area.

"This is an excellent example of how the City of Richmond works with developers and partners such as TransLink to build strong communities," said Mayor Malcolm Brodie.

Plans were first envisioned in a 2012 agreement between the city and Translink to support growing development in the area. In 2017, work on the concept design began after a $1.1 million transfer.

The city said further work can now be undertaken to finalize the station's design.

Capstan Station is expected to be complete around mid 2022.
Reply With Quote
     
     
  #3635  
Old Posted Dec 18, 2019, 2:38 AM
VancouverOfTheFuture's Avatar
VancouverOfTheFuture VancouverOfTheFuture is offline
Registered User
 
Join Date: Apr 2014
Posts: 3,481
nice, good to hear. this is the perfect example of something done right. by both the city and TransLink.
Reply With Quote
     
     
  #3636  
Old Posted Dec 18, 2019, 5:39 AM
Mac Write Mac Write is offline
Registered User
 
Join Date: Dec 2008
Posts: 1,423
Now as for Boundary Station?
Reply With Quote
     
     
  #3637  
Old Posted Dec 18, 2019, 5:56 AM
Sheba Sheba is offline
Registered User
 
Join Date: Jan 2015
Location: BC
Posts: 4,587
Quote:
Originally Posted by Mac Write View Post
Now as for Boundary Station?
If you mean on the Expo Line - it's not gonna happen. It got moved over to Patterson and the spacing between the stations is way too close for the density (which isn't likely to increase by much for a long time).
Reply With Quote
     
     
  #3638  
Old Posted Dec 18, 2019, 6:13 AM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,616
Quote:
Originally Posted by Sheba View Post
If you mean on the Expo Line - it's not gonna happen. It got moved over to Patterson and the spacing between the stations is way too close for the density (which isn't likely to increase by much for a long time).
Joyce seems too close as well. But Boundary does have more new towers going up than anything at Patterson.
Reply With Quote
     
     
  #3639  
Old Posted Dec 18, 2019, 3:44 PM
cairnstone cairnstone is offline
Registered User
 
Join Date: Jan 2010
Posts: 1,026
Quote:
Originally Posted by jollyburger View Post
Joyce seems too close as well. But Boundary does have more new towers going up than anything at Patterson.
its 3 blocks to Joyce. And there is limited development do to central park
Reply With Quote
     
     
  #3640  
Old Posted Dec 18, 2019, 5:36 PM
Tetsuo Tetsuo is offline
Registered User
 
Join Date: Oct 2013
Posts: 1,382
I wonder if Swanguard became a full fledged MLS "Stadium" if the case for a boundary station would have been bolstered, the Telus Boot is massive but how utilized/full is it? North of Kingsway there isn't much to redevelop with increased density, with a fair amount of new townhome developments having been built in the past twenty years.

If Expo were to be built today, I'd argue Boundary would have been a better spot than Patterson, it also allows for a better feeder to Burnaby Hospital/BCIT/employment centre. And RT line to UBC via Kingsway/41st
Reply With Quote
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Reply

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 8:13 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.