Originally Posted by Allandale25
I'm not from Alberta and haven't been following the project closely. Any further details/summary on how the City messed this up?
|
There's been hand-waving about how the tunnel greatly increased costs but going back to earlier documents, the portion through Downtown was always known to be expensive.
I think it may just be a case where the planners and politicians were optimistic (to the point of delusion) in order to get this project approved and funded to start so they could skip BRT. This was what was being sold back in late 2015. Class 5 and 3 estimates were noted but that $4.x figure that was being used in public messaging all the way until the line was truncated in 2017:
If compared with the costs now; everything has gone up in price. To get to the original end points at North Pointe and Seton, you're easily looking at another $3.5B.