  #11101  
Old Posted Jul 8, 2019, 8:52 PM
OCCheetos OCCheetos is offline
 
Join Date: Aug 2017
Posts: 2,118
Quote:
Originally Posted by Richard Eade View Post
It is no surprise to me that we are having problems with the new Light Rail Vehicles (LRVs). How many of you would buy a brand-new car that was assembled from parts by the mechanic in the service garage down the street? Probably none of you (unless the price was phenomenal).
That doesn't seem like a level comparison. We're talking about multi-million dollar vehicles. This isn't just some mechanic assembling parts, the manufacturer literally set up an assembly plant in the maintenance building. It isn't RTG or City of Ottawa workers performing the assembly, it's Alstom workers.

Quote:
In the procurement process, we wanted the LRVs to be assembled here in Ottawa. We were building a maintenance facility so we decided to use that. Yes, we deliberately chose to build the LRVs in our maintenance bays instead of having them built in a proper factory and then shipped here. It strikes me that the LINTs are a good reference point. They were manufactured in a factory and delivered to Ottawa. I don’t remember hearing that we had to fix five of the six before they worked properly.
With this logic, why would anyone ever buy something from Ikea? Except here, it'd be like if Ikea did the assembly for you, on-site.

Quote:
I can just imagine what the Alstom guy said when he came to see what the problem was: “Yeah, this is ridiculous. Any future LRVs will be assembled in a proper facility. The Stage 2 LRVs are not going to be done here.” And, so, the announcement of the new Brampton facility taking on the Stage 2 LRV assembly.
[citation needed] The Brampton facility was announced after Metrolinx signed the contract for their own order of vehicles. Brampton is closer to Hornell (where the parts are manufactured) and it makes sense to consolidate assembly for both regions. But that was an after-the-fact decision.

Quote:
The Brampton factory will have the capacity to finish 3 LRVs per month. In Ottawa, we have started 9 Stage 2 LRVs (No, they are not complete and tested!); but that has taken us how long? It surely takes a lot longer when the original LRVs need so much re-working. Remember, there are only so many resources available at the Belfast Yard. Once those resources can be dedicated to assembling the new LRVs, things should move a bit faster; which means that they are expecting to have 13 in production in November – so four more in four months.
To be fair, they've had their hands kind of tied up with retrofitting the existing fleet. The fact that they have 9 done already is actually kind of surprising, seeing as they only really need to complete 4 of them this year and the original ones aren't even done yet.

Quote:
Alstom didn’t need to have a factory in Canada, since there should have been no requirement for the LRVs to be assembled in Canada. That was simply a vanity addition.
And officially, they didn't. The trains were manufactured in the US. Alstom also had(s) a facility in Quebec for building Montreal's Azurs, though I don't think that could have been repurposed in any useful way for Ottawa/Toronto.

Quote:
And, had the LRVs been produced in Europe, I doubt that there would have been a need for the design to have undergone such a radical reworking. We have been able to live with European designed and built trains from both Bombardier and Alstom for the Trillium Line. The main reason that this is an ‘all-new’ LRV design is because it needed to be built here; with our technology, tools, and supplies.
Of course, the trains used on the Trillium Line have always been ill-suited for their task, even though they work fine, but that's another story. Also, they were a) tacked on to existing orders (the Talents) and b) an order of 6 vehicles, not 72 (+however many Metrolinx has ordered).

I'm sure it was up to the consortiums to select and propose a model of vehicle to be used in their bids, and I suspect that none of them submitted bids with off-the-shelf designs. Not a lot the city could do there if that was the case.

Quote:
As for Bombardier’s problems setting up a factory, that is an entirely different matter. Every new factory has teething-pains to work through. Once running properly, though, the factory will turn out reliably similar vehicles. We opted to have every LRV produced by hand in a maintenance bay.
So how is this different than what happened in Ottawa? "Maintenance bay" is an unsubstantiated point. But besides, everything we know about the problems with the LRVs point to it being a design flaw, not an assembly flaw. Frankly, I'd say it's better that they were assembled here because we have everything we need to retrofit the trains right here. We don't have to deal with any hassle of shipping them back to the US for retrofits.
     
     
  #11102  
Old Posted Jul 8, 2019, 10:55 PM
kmcamp kmcamp is offline
 
Join Date: Sep 2016
Posts: 1,401
Le sigh...... Another deadline missed. I believe at this point it's probably only newsworthy if RTG actually achieves a deadline

https://www.ottawamatters.com/local-news...72?utm_source=dlvr.it&utm_medium=twitter
     
     
  #11103  
Old Posted Jul 8, 2019, 11:27 PM
OCCheetos OCCheetos is offline
 
Join Date: Aug 2017
Posts: 2,118
Quote:
Originally Posted by kmcamp View Post
Le sigh...... Another deadline missed. I believe at this point it's probably only newsworthy if RTG actually achieves a deadline

https://www.ottawamatters.com/local-news...72?utm_source=dlvr.it&utm_medium=twitter
Hopefully we'll hear something good at FEDCO (this time...)
If they missed their deadline by 4 days, and the software update actually works, then it won't be a big deal in the big picture.
     
     
  #11104  
Old Posted Jul 8, 2019, 11:53 PM
kmcamp kmcamp is offline
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by OCCheetos View Post
Hopefully we'll hear something good at FEDCO (this time...)
If they missed their deadline by 4 days, and the software update actually works, then it won't be a big deal in the big picture.
True, but I think I've exhausted all my optimism for now, I'll only be happy when an actual service start date is announced.
     
     
  #11105  
Old Posted Jul 9, 2019, 2:43 AM
J.OT13's Avatar
J.OT13 J.OT13 is offline
 
Join Date: Mar 2012
Posts: 29,160
Quote:
Originally Posted by kmcamp View Post
Le sigh...... Another deadline missed. I believe at this point it's probably only newsworthy if RTG actually achieves a deadline

https://www.ottawamatters.com/local-news...72?utm_source=dlvr.it&utm_medium=twitter
It doesn't necessarily mean they missed the deadline, though I understand the the tendency to make that assumption. The secretive nature is usually a bad sign, but "An update on LRT will be presented at FEDCo on Wednesday. I encourage you to attend," could be interpreted as good news... if we try very hard.

As for the updates, the trains use a computer system for automation. Computers programs need updates regularly. And its a software updates for all trains, not just the few defective units. They might have completed the trains and took a day off for the regular system wide update in order to ready themselves for the substantial completion and subsequent 12 days of testing.
     
     
  #11106  
Old Posted Jul 9, 2019, 11:32 AM
kmcamp kmcamp is offline
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by J.OT13 View Post
It doesn't necessarily mean they missed the deadline, though I understand the the tendency to make that assumption. The secretive nature is usually a bad sign, but "An update on LRT will be presented at FEDCo on Wednesday. I encourage you to attend," could be interpreted as good news... if we try very hard.

As for the updates, the trains use a computer system for automation. Computers programs need updates regularly. And its a software updates for all trains, not just the few defective units. They might have completed the trains and took a day off for the regular system wide update in order to ready themselves for the substantial completion and subsequent 12 days of testing.
The software update really doesn't concern me, I expect them to receive them all the time. It really is the tight lipped "wait for the Fedco update" that makes me think we'll be seeing a delay yet again. After all, earlier in the week they were happy to tell the media that things were looking like they could make the date. This is the typical pattern we see before delays (and it's sad that it's so regular that there's a predictable pattern)
     
     
  #11107  
Old Posted Jul 9, 2019, 11:50 AM
kmcamp kmcamp is offline
 
Join Date: Sep 2016
Posts: 1,401
Meanwhile I wonder if the city should just go ahead and complete the bus service change now and use the extra drivers they have to provide R1 route service. It might actually make the current setup more reliable when every bus downtown is the right bus.
     
     
  #11108  
Old Posted Jul 9, 2019, 12:42 PM
OtrainUser OtrainUser is offline
 
Join Date: Jul 2017
Posts: 619
Quote:
Originally Posted by kmcamp View Post
Meanwhile I wonder if the city should just go ahead and complete the bus service change now and use the extra drivers they have to provide R1 route service. It might actually make the current setup more reliable when every bus downtown is the right bus.
I agree with this.
     
     
  #11109  
Old Posted Jul 9, 2019, 12:43 PM
Truenorth00 Truenorth00 is online now
 
Join Date: May 2017
Posts: 29,137
Sadly the nature of things. We just aren't are important enough client for them to prioritize issues with our orders.

I wish our governments has more foresight to maximize leverage. Had Stage 1 and Stage 2 orders been combined from the beginning, along with Metrolinx orders optioned through OC Transpo, Alstom would have had a whole different tone right from the start.
     
     
  #11110  
Old Posted Jul 9, 2019, 1:05 PM
OCCheetos OCCheetos is offline
 
Join Date: Aug 2017
Posts: 2,118
Saw several double trains parked in stations this morning.
Train parked at Hurdman with all its doors open for well over a minute
Two trains parked at uOttawa, one with a pretty bored-looking operator in the cab.

Hope nothing went too wrong...
     
     
  #11111  
Old Posted Jul 9, 2019, 1:14 PM
Truenorth00 Truenorth00 is online now
 
Join Date: May 2017
Posts: 29,137
Quote:
Originally Posted by Richard Eade View Post
It is no surprise to me that we are having problems with the new Light Rail Vehicles (LRVs). How many of you would buy a brand-new car that was assembled from parts by the mechanic in the service garage down the street? Probably none of you (unless the price was phenomenal).

In the procurement process, we wanted the LRVs to be assembled here in Ottawa. We were building a maintenance facility so we decided to use that. Yes, we deliberately chose to build the LRVs in our maintenance bays instead of having them built in a proper factory and then shipped here. It strikes me that the LINTs are a good reference point. They were manufactured in a factory and delivered to Ottawa. I don’t remember hearing that we had to fix five of the six before they worked properly.

I can just imagine what the Alstom guy said when he came to see what the problem was: “Yeah, this is ridiculous. Any future LRVs will be assembled in a proper facility. The Stage 2 LRVs are not going to be done here.” And, so, the announcement of the new Brampton facility taking on the Stage 2 LRV assembly.

The Brampton factory will have the capacity to finish 3 LRVs per month. In Ottawa, we have started 9 Stage 2 LRVs (No, they are not complete and tested!); but that has taken us how long? It surely takes a lot longer when the original LRVs need so much re-working. Remember, there are only so many resources available at the Belfast Yard. Once those resources can be dedicated to assembling the new LRVs, things should move a bit faster; which means that they are expecting to have 13 in production in November – so four more in four months.
Knockdown kits. Airplane and rail makers ship them all over and put them together at the other end with few to no issues. Having a FAL somewhere is really not that much of an issue.

The likely culprit here is that the Citadis Spirit was designed for North America, making Ottawa the launch customer. So despite the fact that "Citadis" have been sold elsewhere, this really is effectively a new design built to North American standards and we're the guinea pig on which they get to test out all their manufacturing processes, supply chains, etc. for their North American market and this specific model. It's not nearly as mature a design that the public and politicians think it is, or as RTG portrayed.

It's already worked out well for Alstom with a nice 61 LRV order from Metrolinx and more expected. They'll do really well with all the lessons learned from Ottawa.
     
     
  #11112  
Old Posted Jul 9, 2019, 1:47 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
 
Join Date: Mar 2012
Posts: 29,160
Quote:
Originally Posted by OCCheetos View Post
Saw several double trains parked in stations this morning.
Train parked at Hurdman with all its doors open for well over a minute
Two trains parked at uOttawa, one with a pretty bored-looking operator in the cab.

Hope nothing went too wrong...
One of two possibilities:
  1. The update broke something, as is often the case with software updates or;
  2. They are testing the update, and a shut-down of the entire system, which includes parking the trains at stations (to simulate evacuating passengers) is part of it.
     
     
  #11113  
Old Posted Jul 9, 2019, 2:08 PM
lrt's friend lrt's friend is online now
 
Join Date: Dec 2006
Posts: 12,815
Quote:
Originally Posted by kmcamp View Post
Meanwhile I wonder if the city should just go ahead and complete the bus service change now and use the extra drivers they have to provide R1 route service. It might actually make the current setup more reliable when every bus downtown is the right bus.
I wouldn't do this. This would mean that the public has to deal with substantial changes twice. I don't think the R1 is designed to be an ideal replacement for the entire rail service. I expect it would replace only part of the route as necessary. This also throws out the plan to run parallel service to make it a soft switchover at the time that the Confederation Line opens.
     
     
  #11114  
Old Posted Jul 9, 2019, 2:53 PM
CityTech CityTech is offline
 
Join Date: May 2016
Posts: 2,798
"Software update" isn't much to go on. Trains will be receiving updates after the launch, on a regular basis for decades to come.

That said, probably another delay. If they did submit substantial completion paperwork again the city would have wanted to announce it for the fanfare.

At this point, just hope its open before winter. The bus service can't survive another winter.
     
     
  #11115  
Old Posted Jul 9, 2019, 3:01 PM
OCCheetos OCCheetos is offline
 
Join Date: Aug 2017
Posts: 2,118
Quote:
Originally Posted by lrt's friend View Post
I wouldn't do this. This would mean that the public has to deal with substantial changes twice. I don't think the R1 is designed to be an ideal replacement for the entire rail service. I expect it would replace only part of the route as necessary. This also throws out the plan to run parallel service to make it a soft switchover at the time that the Confederation Line opens.
R1 is near identical to the detour routing we have now, with the exception of uOttawa and Queen St.

The more useful part of the idea is breaking cross-town routes into smaller pieces (like the LRT will) and having the middle portion simply being a high frequency shuttle between Tunney's and Blair.

Honestly, not the worst idea considering that the biggest delays are with how easily buses get backlogged on Albert and Slater.
A logistical and PR nightmare though.
     
     
  #11116  
Old Posted Jul 9, 2019, 3:01 PM
RomanR27 RomanR27 is offline
 
Join Date: Apr 2016
Posts: 2,049
Quote:
Originally Posted by lrt's friend View Post
I wouldn't do this. This would mean that the public has to deal with substantial changes twice. I don't think the R1 is designed to be an ideal replacement for the entire rail service. I expect it would replace only part of the route as necessary. This also throws out the plan to run parallel service to make it a soft switchover at the time that the Confederation Line opens.
Agreed, it's simply not feasible. It would resemble the post-Bluesfest crowd, which I don't think anyone wants to deal with at 7:30 in the morning.
     
     
  #11117  
Old Posted Jul 9, 2019, 3:02 PM
CityTech CityTech is offline
 
Join Date: May 2016
Posts: 2,798
Quote:
Originally Posted by lrt's friend View Post
I wouldn't do this. This would mean that the public has to deal with substantial changes twice. I don't think the R1 is designed to be an ideal replacement for the entire rail service. I expect it would replace only part of the route as necessary. This also throws out the plan to run parallel service to make it a soft switchover at the time that the Confederation Line opens.
Plus there's the capacity issue. Gathering all service through downtown into Line 1 works because a single train has 5 times more capacity than an 18m bus. This scenario would need R1 to be served with articulated buses leaving Tunneys every 40s. Not realistic at all.
     
     
  #11118  
Old Posted Jul 9, 2019, 3:08 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is offline
 
Join Date: Nov 2005
Posts: 4,703
Looks like a bit of heavy equipment is back in front of Rideau east entrance. More hydrovaccing?
     
     
  #11119  
Old Posted Jul 9, 2019, 3:09 PM
zzptichka zzptichka is offline
 
Join Date: Dec 2015
Posts: 2,401
Photo from Sunday, back when trains were still running.

     
     
  #11120  
Old Posted Jul 9, 2019, 3:09 PM
Dengler Avenue's Avatar
Dengler Avenue Dengler Avenue is offline
 
Join Date: Sep 2017
Posts: 8,683
Interesting photo

For reasons I don’t even know, it looks philosophical.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 1:21 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.