Council to learn 'substantial completion' decision Wednesday
Jon Willing, Ottawa Citizen
Updated: May 15, 2019
Council will be learning Wednesday how an independent certifier viewed the Rideau Transit Group’s request for “substantial completion” on the $2.1-billion Confederation Line LRT project.
Transportation general manager John Manconi said city lawyers and technical experts have been going over the certifier’s review.
“It’s a complicated process. We need to take our time. This is serious stuff,” Manconi said after a transit commission meeting Wednesday.
City and RTG officials met Tuesday afternoon at city hall.
“We’re aligned on the path forward,” Manconi said, but the city is waiting to update council in a memo before going public with what the certifier determined.
RTG submitted paperwork to the project’s independent certifier to decide if the project has reached substantial completion. The certifier had until late Monday afternoon to make a determination.
A substantially complete project would mean the LRT system is virtually ready for use. The declaration would allow RTG to begin the mandatory 12 days of full-system testing mimicking regular transit service. If, at the end of the 12 days, there were no major problems, the LRT system could be handed over to the city.
If the system isn’t substantially complete, RTG would have to provide a plan that addresses the unfinished work before applying again for a substantial completion designation, triggering another review by the certifier.
The city and RTG equally pay for the certifier. The independent certification services are provided by Altus Group.
The city has been largely concerned about the readiness of the Alstom Citadis Spirit trains. The problems, such as door jams and computer bugs, have been characterized as very fixable. Mayor Jim Watson has called the head of Alstom to emphasize to the French company the importance of getting the train work done.
There are 34 single vehicles in the Stage 1 fleet. Fifteen trains, each with two connected vehicles, will run during the peak service hours.
The 12.5-kilometre Confederation Line will run between Tunney’s Pasture and Blair Station via a downtown tunnel. All three levels of government are paying for the project, with city taxpayers paying the most.
The original revenue service availability date — in other words, the handover date to the city — was May 24, 2018. The project contract says the city has the right to terminate the agreement if completion is 365 days after the revenue service availability date.
After missing the May 2018 handover deadline, RTG proposed handover dates for Nov. 2, 2018, and March 31, 2019. The company missed both those handovers, too.
RTG has told they city that it can deliver the LRT system by the end of June.