  #10381  
Old Posted Apr 29, 2019, 11:51 PM
Truenorth00 Truenorth00 is offline
Registered User
 
Join Date: May 2017
Posts: 28,880
Quote:
Originally Posted by kmcamp View Post
For example, in Shane's video they showed how the train would come to a complete stop if someone doesn't hit the deadman switch. All the operators have done simulator training, but things might be going wrong operationally when confronted with the real thing. Human error aborts the test and restarts the counter as much as infrastructure issues.
My point here is that these errors absolutely should not be there at this point in the timeline. They've had the whole guideway with the exception of the downtown stations for a year. What the heck have they been doing all this time?
     
     
  #10382  
Old Posted Apr 30, 2019, 12:53 PM
Badyouken's Avatar
Badyouken Badyouken is offline
Registered User
 
Join Date: Feb 2016
Posts: 239
Quote:
Originally Posted by kmcamp View Post
It wouldn't be surprising if everyday is the 12 days now, but they'll only tell us once it's complete, since every issue restarts the counter
That's what I'm reading from his comments. Every day is a 'business as usual' simulation, and once they reach 6 consecutive days without any error it will qualify as a success.
     
     
  #10383  
Old Posted Apr 30, 2019, 1:33 PM
OTownandDown OTownandDown is offline
Registered User
 
Join Date: Jul 2018
Posts: 1,615
I see it like the physical construction: nearing the end, things are getting cleaned up, but it looks like hell. You play whackamole for a few days, things start to streamline, and suddenly you're done and it's ready. The start of those times is hell though.
     
     
  #10384  
Old Posted Apr 30, 2019, 1:46 PM
Badyouken's Avatar
Badyouken Badyouken is offline
Registered User
 
Join Date: Feb 2016
Posts: 239
Yeah.

Meanwhile, this lines up with what I'm seeing from my vantage point overlooking Bayview station. Doubles running at very high frequency.
     
     
  #10385  
Old Posted Apr 30, 2019, 3:18 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Looks like the black bands on the lanterns are going up



https://mobile.twitter.com/chrisrands/status/1123213711894810625
     
     
  #10386  
Old Posted Apr 30, 2019, 3:54 PM
Uhuniau Uhuniau is offline
Registered User
 
Join Date: Jan 2010
Posts: 9,011
Quote:
Originally Posted by Truenorth00 View Post
This is nuts. How do they have such crap reliability? You gotta wonder if the work was shoddy or they cheaped out on systems.
"Crap reliability" by what measure?

This is what working out the bugs is for. It works out the bugs.
__________________
___
Enjoy my taxes, Orleans (and Kanata?).
     
     
  #10387  
Old Posted Apr 30, 2019, 4:06 PM
Uhuniau Uhuniau is offline
Registered User
 
Join Date: Jan 2010
Posts: 9,011
Quote:
Originally Posted by Badyouken View Post
Yeah.

Meanwhile, this lines up with what I'm seeing from my vantage point overlooking Bayview station. Doubles running at very high frequency.
Was at Bayview last night and in a handful of minutes (less than 10) there were two doubles in one direction and two and a half in the other. (One was pulling in as I was leaving.)
__________________
___
Enjoy my taxes, Orleans (and Kanata?).
     
     
  #10388  
Old Posted Apr 30, 2019, 4:30 PM
Gat-Train Gat-Train is offline
BANNED
 
Join Date: Nov 2018
Posts: 508
The doors without a roof look severely misplaced. Why couldn't they have gone with a nice black metal gate? Value engineering?
     
     
  #10389  
Old Posted Apr 30, 2019, 4:40 PM
Badyouken's Avatar
Badyouken Badyouken is offline
Registered User
 
Join Date: Feb 2016
Posts: 239
Quote:
Originally Posted by Gat-Train View Post
The doors without a roof look severely misplaced. Why couldn't they have gone with a nice black metal gate? Value engineering?
Yeah they do look a bit funny.
     
     
  #10390  
Old Posted Apr 30, 2019, 4:46 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,710
I figure that's temporary until Stage 2 opens and the bus loop is removed.
     
     
  #10391  
Old Posted Apr 30, 2019, 4:54 PM
Badyouken's Avatar
Badyouken Badyouken is offline
Registered User
 
Join Date: Feb 2016
Posts: 239
Quote:
Originally Posted by J.OT13 View Post
I figure that's temporary until Stage 2 opens and the bus loop is removed.
Doubt it, other stations also have these doors without a roof. Just a funny design decision.
     
     
  #10392  
Old Posted Apr 30, 2019, 5:48 PM
Truenorth00 Truenorth00 is offline
Registered User
 
Join Date: May 2017
Posts: 28,880
Quote:
Originally Posted by Uhuniau View Post
"Crap reliability" by what measure?

This is what working out the bugs is for. It works out the bugs.
According to reports they can't get through a day without major faults. If that's true, that should be really, really concerning at this stage of the game.
     
     
  #10393  
Old Posted Apr 30, 2019, 6:02 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
In other news, CF Rideau has replaced all their wayfinding signage to use the big red O, and now has Rideau Station on mall maps.
     
     
  #10394  
Old Posted Apr 30, 2019, 6:07 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by Truenorth00 View Post
According to reports they can't get through a day without major faults. If that's true, that should be really, really concerning at this stage of the game.
You used to be such an optimist about the project, now you're as cynical as the rest of us
     
     
  #10395  
Old Posted Apr 30, 2019, 9:08 PM
Truenorth00 Truenorth00 is offline
Registered User
 
Join Date: May 2017
Posts: 28,880
Quote:
Originally Posted by kmcamp View Post
You used to be such an optimist about the project, now you're as cynical as the rest of us


I reserve the right to flip flop based on flip flopping details......

I guess coming from the aerospace world, it's just shocking to me. I can't imagine finding faults weeks before handing over a new airplane.....
     
     
  #10396  
Old Posted Apr 30, 2019, 9:38 PM
RomanR27 RomanR27 is offline
Registered User
 
Join Date: Apr 2016
Posts: 1,951
Quote:
Originally Posted by Truenorth00 View Post


I reserve the right to flip flop based on flip flopping details......

I guess coming from the aerospace world, it's just shocking to me. I can't imagine finding faults weeks before handing over a new airplane.....
I guess you didn't work on the 737 MAX.
     
     
  #10397  
Old Posted Apr 30, 2019, 10:18 PM
HighwayStar's Avatar
HighwayStar HighwayStar is offline
Registered User
 
Join Date: Jul 2014
Location: PHX (by way of YOW)
Posts: 1,200
Quote:
Originally Posted by Truenorth00 View Post


I reserve the right to flip flop based on flip flopping details......

I guess coming from the aerospace world, it's just shocking to me. I can't imagine finding faults weeks before handing over a new airplane.....
I'm also in the Aerospace world... I think this is more like a new air traffic control system.

I mean the planes (trains) are certified and working... they are now putting the entire system through it's paces to work out the kinks... that is what validation and acceptance testing is all about.

Without more details on the nature of the issues, doesn't really seem out of the ordinary from an engineering point of view.
     
     
  #10398  
Old Posted May 1, 2019, 2:01 AM
Truenorth00 Truenorth00 is offline
Registered User
 
Join Date: May 2017
Posts: 28,880
Quote:
Originally Posted by HighwayStar View Post
I'm also in the Aerospace world... I think this is more like a new air traffic control system.

I mean the planes (trains) are certified and working... they are now putting the entire system through it's paces to work out the kinks... that is what validation and acceptance testing is all about.

Without more details on the nature of the issues, doesn't really seem out of the ordinary from an engineering point of view.
Again though. If you were building a new air traffic system, you wouldn't tolerate bugs this close to roll out. Imagine, for example, the roll out of RNAV out or ADSB couldn't get days without major failures weeks before launch.

I want to be optimistic. But reading those posts in Reddit was disappointing.
     
     
  #10399  
Old Posted May 1, 2019, 2:27 AM
CityTech CityTech is offline
Registered User
 
Join Date: May 2016
Location: Ottawa
Posts: 2,798
From my professional background (software/cloud) I don't really see much to panic about. Projects in my world always end up with LOTS of little things that require fixes in the final stages of QA.

Is anyone here actually from a rail or civil engineering background?
     
     
  #10400  
Old Posted May 1, 2019, 4:43 AM
HighwayStar's Avatar
HighwayStar HighwayStar is offline
Registered User
 
Join Date: Jul 2014
Location: PHX (by way of YOW)
Posts: 1,200
Quote:
Originally Posted by Truenorth00 View Post
Again though. If you were building a new air traffic system, you wouldn't tolerate bugs this close to roll out. Imagine, for example, the roll out of RNAV out or ADSB couldn't get days without major failures weeks before launch.

I want to be optimistic. But reading those posts in Reddit was disappointing.
Well... given Aero is an order of magnitude more complex than this system, it's a bit of a stretch to compare ADSB (or any other Aviation component) issues to switch and/or signalling issues.

I'm actually glad to see what appears to be full blown system tests going on with what appears to be a day-to-day start of the 12 day test.

At this time I'm keeping my optimistic hat on... hopefully the next few days/weeks are the final turning point.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 11:38 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.