Relevant section on Limebank Road we were discussing (sorry for the long block of text and poor formatting):
Quote:
(i) Limebank Road
(i) Project Co shall design and construct the Roadway improvements on Limebank Road per the Design Criteria requirements specified in Appendix A of this Part 2.
(ii) Project Co shall design and construct a grade separation Bridge Structure, including its approach embankments, at a location approximately 300m south of the existing Earl Armstrong Road/ Limebank Road intersection, where the new Track corridor shall cross the Limebank Road corridor.
A. Under a scenario in which Project Co’s proposed grade separation facility may involve a road-over-rail grade separation configuration, Project Co shall construct an Overhead Structure, including its associated approach embankments, to carry the proposed Limebank Road over the Track corridor.
i Project Co shall design and construct the Overhead Structure to accommodate for a future widening of Limebank Road further south without the need to reconstruct the southern approach embankments for the Overhead Structure.
ii The entire raised length of Limebank Road over the Track corridor shall meet the 4-lane divided cross section requirements as specified in Appendix A of this Part 2. Project Co shall design and construct an appropriate transition for the improved Limebank Road to change its cross-section from the 4-lane divided urban cross section to the existing 2-lane undivided rural cross section beyond the southerly limits of the proposed grade raise.
iii The overall length of the Limebank Road Overhead Structure shall provide the span required to:
1. Carry Limebank Road over the Track corridor, and,
2. Accommodate a collector Roadway on the north side of the Track corridor, and a MUP on the south side of the Track corridor, as prescribed in Clause 6.18(i)(iii)(C) of this Part 2.
B. Under a scenario in which Project Co’s proposed grade separation facility may involve a rail-over-road grade separation configuration, Project Co shall construct a Guideway Structure, including its associated approach embankments, which spans over the Roadway cross-section as described in Appendix A of this Part 2.
i Project Co shall design and construct the single span Guideway Structure to accommodate for a future widening of Limebank Road without a need to reconstruct any part of the Guideway Structure.
1. The design of the Guideway Structure shall also accommodate and protect for a collector Roadway cross section, on the north side of the Track corridor, and a MUP on the south side of the Track corridor, as prescribed in Clause 6.18(i)(iii)(C) of this Part 2.
2. The design of the Guideway Structure shall also protect for a future MUP connection between the north and south sides of the Track corridor on the east side of Limebank Road (minimum 7.0m between the east abutment and the east edge of the Limebank Road ROW).
ii Project Co shall design and construct an at-grade signalized intersection at the intersection of Limebank Road and Connector Road.
1. Project Co shall undertake a detailed traffic analysis, including an intersection LOS analysis considering vehicular and non-vehicular road user needs as per the City of Ottawa’s TIA Guidelines, and confirm the intersection control type, storage lengths and geometry and general layout, using projected traffic and transit volumes for a 2031 horizon year, including cyclists and pedestrians.
2. Project Co shall submit a comprehensive traffic report and include the results and approval from the City at the early stages of the preliminary design, and recommendations of the above-noted traffic analysis and seek a minimum of 20 Business Days prior to initiating the detailed design per the requirements of Schedule 10 – Review Procedure.
(iii) Project Co shall accommodate a collector Roadway cross section, on the north side of the Track corridor and a MUP on the south side of the Track corridor, as described below.
A. Project Co shall design and construct the collector Roadway north of the Track corridor, herein referred to as Connector Road. Project Co shall refer to Article 6.18(j) for the scope of the design and construction requirements of Connector Road.
B. Project Co shall design and construct an appropriate transition required for Connector Road as per the requirements of Clause 6.18 (j)(i)(D) of this
Part 2.
C. Project Co shall protect for a future MUP south of the Track corridor. The future MUP shall have a minimum clear width of 7.0m and a minimum overhead clearance of 3.0m.
(iv) Project Co shall ensure the horizontal and vertical clearances for the proposed grade separation facility meet the requirements of the applicable Bridge codes as per Article 4 – Structural Design Criteria and requirements of this Part 2.
(v) Project Co shall undertake a detailed traffic analysis, including an intersection level of service analysis, as per the City’s TIA Guidelines, to confirm the traffic control types and storage lengths and geometry and general layout for the limit of the Works on the southern leg of the Limebank Road / Earl Armstrong intersection, as required, using a projected traffic and transit volumes for a 2031 horizon year and taking into consideration all associated pedestrian and cycling requirements. Project Co shall submit a comprehensive traffic report and include the results and recommendations of the above-noted traffic analysis and seek approval from the City at the early stages of the preliminary design, and a minimum of 20 Business Days prior to initiating the detailed design per the requirements of Schedule 10 – Review Procedure. Project Co shall provide for all additional intersection improvements as required on the southern leg of the intersection according to the results of the above-noted traffic analysis.
(vi) Project Co shall design and construct the proposed Roadway improvements for Limebank Road to include all necessary traffic staging detours and temporary access requirements such that all temporary and permanent Works are contained within the Lands as defined in Schedule 33 – Lands.
(vii) Project Co shall reference the information provided in Schedule 15-2, Part 7 – Traffic and Transit Management and Construction Access, for the specific traffic staging and access management requirements for all private approaches from Limebank Road during staged construction and temporary conditions.
(viii) Project Co shall refer to Schedule 15-2, Part 6 - Urban Design, Landscape Architecture and Connectivity Requirements, for the pedestrian and cycling connectivity, landscape and streetscape requirements for Limebank Road and associated intersecting Roadways.
(ix) Project Co’s design and construction of the Roadway improvements for Limebank Road shall meet the requirements of Clause 6.17 of this Part 2.
(x) Project Co shall protect for future access to/ from Limebank Road as per the requirements of the most current Riverside South community design plans and guidelines.
|
It looks like in the Limebank Road over Trillium Line option (Scenario A) they will only build the overpass to accommodate the north connector road ("transit road" in the CDP) with a multi-use pathway on the south side of the tracks. So I guess the south transit road won't continue through at Limebank.
|