  #9621  
Old Posted Mar 5, 2019, 3:48 PM
CityTech CityTech is offline
Registered User
 
Join Date: May 2016
Location: Ottawa
Posts: 2,798
Updates from twitter coverage of meeting. All 34 trains are now complete. 24 have certificates. 9 of 13 stations are complete. Winter issues caused by track clearing problems not trains themselves.
     
     
  #9622  
Old Posted Mar 5, 2019, 3:49 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,798
Won't make March 31. Now saying Q2. But they say they will need less than 60 days after March 31 to provide a new date.

I'm guessing an approx. 1 month delay.
     
     
  #9623  
Old Posted Mar 5, 2019, 3:50 PM
daud's Avatar
daud daud is offline
Registered User
 
Join Date: Jun 2012
Location: Ottawa
Posts: 762
Quote:
Originally Posted by CityTech View Post
Updates from twitter coverage of meeting. All 34 trains are now complete. 24 have certificates. 9 of 13 stations are complete. Winter issues caused by track clearing problems not trains themselves.
Quote from Manconi(?) via Jon Willing on Twitter:

RTG last week confirmed it will not be able to hand over on March 31. Says it can hand over in second quarter. No exact date.
     
     
  #9624  
Old Posted Mar 5, 2019, 3:51 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by bradnixon View Post
Won't make March 31. Now saying Q2. But they say they will need less than 60 days after March 31 to provide a new date.

I'm guessing an approx. 1 month delay.
I'm still on track for my May prediction! Do I get a prize if I win
     
     
  #9625  
Old Posted Mar 5, 2019, 3:54 PM
Truenorth00 Truenorth00 is online now
Registered User
 
Join Date: May 2017
Posts: 28,836
I stand by my earlier comments. People need to lose their jobs over this. The March date was ridiculous when it was announced.

The fact that they haven't finished all the station work by now is maddening. RTG is purposely going slow and trying to match station finishing with vehicle acceptance. That's a recipe for further delays as station defects get found later.
     
     
  #9626  
Old Posted Mar 5, 2019, 3:55 PM
Truenorth00 Truenorth00 is online now
Registered User
 
Join Date: May 2017
Posts: 28,836
Quote:
Originally Posted by kmcamp View Post
I'm still on track for my May prediction! Do I get a prize if I win
Second quarter..... you should know with RTG's bad faith operation, this means September.... My most optimistic read is June 30th.
     
     
  #9627  
Old Posted Mar 5, 2019, 3:56 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
On more upbeat note, they unveiled a 360 tour of the train:

http://www.octranspo.com/ready4rail/new_vehicles#train360
     
     
  #9628  
Old Posted Mar 5, 2019, 3:59 PM
Ottawaresident Ottawaresident is offline
BANNED
 
Join Date: Jan 2019
Location: Guess! Hint: It's in my username
Posts: 317
Quote:
Originally Posted by Truenorth00 View Post
Second quarter..... you should know with RTG's bad faith operation, this means September.... My most optimistic read is June 30th.
My read is next year ... or never.
     
     
  #9629  
Old Posted Mar 5, 2019, 4:00 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by bradnixon View Post
Won't make March 31. Now saying Q2. But they say they will need less than 60 days after March 31 to provide a new date.

I'm guessing an approx. 1 month delay.
My guess is less than 3 months (1 quarter). It could be 1 month, but I wouldn't be surprised if its a bit longer.

As for opening for full revenue service. I think July 2 is looking likely. They will probably do public trials before that (and have it running on Canada Day), but I think that is the day they will stop having the Connexion and Rapid buses go downtown.

I also wouldn't be surprised if they do some sort of staggered start, where they continue to have some routes travel downtown while others terminate at an LRT station.
     
     
  #9630  
Old Posted Mar 5, 2019, 4:01 PM
Truenorth00 Truenorth00 is online now
Registered User
 
Join Date: May 2017
Posts: 28,836
Quote:
Originally Posted by CityTech View Post
. 9 of 13 stations are complete.
When they say complete does this mean with occupancy permits?
     
     
  #9631  
Old Posted Mar 5, 2019, 4:10 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by Truenorth00 View Post
Second quarter..... you should know with RTG's bad faith operation, this means September.... My most optimistic read is June 30th.
Nobody believed me when I said Trump would win the election either. At this point, the 1 million penalty is pointless but the finance charges RTG is carrying from the withheld milestone payment must be hurting a lot, so at this point they won't want to drag things out much longer. I wouldn't be surprised if they get the remaining trains certified within the first couple of weeks of April. Some of the unfinished things on the stations are kind of weather dependent, e.g. they don't have the fake elevator shroud on the roof of Pimisi, because they didn't install it before the snow fell and now the roof is buried in snow and ice.

This is actually probably what's most wrong with the Stage 2 contracts, the monthly payments remove the self imposed penalty of finance charges.
     
     
  #9632  
Old Posted Mar 5, 2019, 4:11 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by Truenorth00 View Post
When they say complete does this mean with occupancy permits?
I think "complete" means occupancy permit.
     
     
  #9633  
Old Posted Mar 5, 2019, 4:19 PM
Truenorth00 Truenorth00 is online now
Registered User
 
Join Date: May 2017
Posts: 28,836
Quote:
Originally Posted by kmcamp View Post
Some of the unfinished things on the stations are kind of weather dependent, e.g. they don't have the fake elevator shroud on the roof of Pimisi, because they didn't install it before the snow fell and now the roof is buried in snow and ice.
You can get occupancy permits without the cosmetic stuff being finished. That over a third of the line still has occupancy permits outstanding should be very worrisome. Why is nobody asking them when the permits are expected?
     
     
  #9634  
Old Posted Mar 5, 2019, 4:23 PM
roger1818's Avatar
roger1818 roger1818 is offline
Registered User
 
Join Date: Feb 2016
Location: Stittsville, ON
Posts: 6,610
Quote:
Originally Posted by CityTech View Post
Updates from twitter coverage of meeting. All 34 trains are now complete. 24 have certificates. 9 of 13 stations are complete. Winter issues caused by track clearing problems not trains themselves.
Which 4 stations are not complete? I assume Rideau is one. Are the three western stations (Tunnies, Bayview and Pimisi) the others?
     
     
  #9635  
Old Posted Mar 5, 2019, 4:23 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,798
Quote:
Originally Posted by roger1818 View Post

I also wouldn't be surprised if they do some sort of staggered start, where they continue to have some routes travel downtown while others terminate at an LRT station.
I think it has always been the plan that the bus network would remain as-is for at least a few weeks after LRT go-live.
     
     
  #9636  
Old Posted Mar 5, 2019, 4:24 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by roger1818 View Post
Which 4 stations are not complete? I assume Rideau is one. Are the three western stations (Tunnies, Bayview and Pimisi) the others?
Parliament is one, they are still doing a lot of work there, I work right by it.
     
     
  #9637  
Old Posted Mar 5, 2019, 4:31 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is online now
Busy Beaver
 
Join Date: Nov 2005
Location: Ottawa
Posts: 4,675
I passed by Parliament station the other day and they are still tiling the stairway.
     
     
  #9638  
Old Posted Mar 5, 2019, 4:34 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,798
Quote:
Originally Posted by roger1818 View Post
Which 4 stations are not complete? I assume Rideau is one. Are the three western stations (Tunnies, Bayview and Pimisi) the others?
I was at Bayview today and they were installing some exterior paneling but it seemed to be entirely cosmetic work.
     
     
  #9639  
Old Posted Mar 5, 2019, 5:19 PM
CityTech CityTech is offline
Registered User
 
Join Date: May 2016
Location: Ottawa
Posts: 2,798
Apparently last 10 trains expected to be certified within a week or two.
     
     
  #9640  
Old Posted Mar 5, 2019, 5:24 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by CityTech View Post
Apparently last 10 trains expected to be certified within a week or two.
If we have 34 trains at the end of the month, then my May prediction holds. If we don't, that's when all bets are off.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 5:57 PM.

     
SkyscraperPage.com - Privacy Statement - Top

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.