What would be a good estimate on the completion of this tower? When phase 1 units were selling, the tentative completion date was Q1 2020... looks impossible at this point.
|
For Tower 1.
Its excavated and starting to get formed up.
5 months to ground level from here.
That's July.
42 floors at an average of floor a week plus mechanical level say 45 weeks.
That's about March 2020 to top out the tower.
You then have 3 months to finish glazing, and mechanical level work.
That's May.
6 months for interior finishes.
That's September 2020.
Few things go little late, little slow, Q1 2021 doesn't seem too unrealistic.