That right turn lane at F will probably be "right turns only except buses" so they don't have to change 2 lanes.
     
     
  #19662  
Old Posted Feb 15, 2019, 2:22 AM
VancouverOfTheFuture's Avatar
VancouverOfTheFuture VancouverOfTheFuture is offline
Registered User
 
Join Date: Apr 2014
Posts: 3,481
Quote:
Originally Posted by Migrant_Coconut View Post

(DailyHive, unfortunately)

For anybody who doesn't like to read sideways:

F) Reassign the westbound curb lane to a right-turn lane and lengthen the existing westbound left-turn bay.
Why? To help prevent through-moving vehicles from getting stuck behind left- or right-turning vehicles which improves traffic.
Quote:
Originally Posted by ilikeredheads View Post
That right turn lane at F will probably be "right turns only except buses" so they don't have to change 2 lanes.
then that negates the point of F, since they'll get stuck behind cars turning right... also, assuming they really do build the curbs like that at E. Blvd, those buses will need to pull out into the 2nd lane to go around that sharp curb.
     
     
  #19663  
Old Posted Feb 15, 2019, 7:43 PM
waves's Avatar
waves waves is offline
waves
 
Join Date: Jun 2015
Location: North Vancouver
Posts: 382
Mayors Council Finished.

3.2 Funding of the 10 year Vision
> The full set of new train cars will be ready for implementation on completion of the Broadway Subway to Arbutus in 2025.
> A new fuel tax + development charges will be approved by the Provincial government thereby securing most all funding for Phase 2 of the 10 year vision.
> "Phase 3 is not funded at all"
> Investment Plans in 2020 and 2023
> 7% Bus increase could be accelerated but major road/bike/capital infrastructure will require senior government funding.
> The 7% is probably only enough to maintain status quo of overcrowding.

3.3 Green Infrastructure Fund
> Burnaby Mountain Gondola could be funded by the GIF
> It may go to buses instead

4.2 Rail to UBC
> Mike Little wants to know the vertical alignment cost differences before approval, cut & cover, bored tunnel, elevated, etc.
> Geoff Cross: Fastest start to construction is 2025.
> Jonathon Cote and others: Negotiations with the community over "enhancements" that they want beyond the base case (maybe Vancouver pays for the extra cost for bored tunnel vs cut & cover?). Coquitlam didn't pay the extra amount to have the last part of the Evergreen Line underground even though it wanted it. The Coquitlam mayor's emphasis was on the same fairness being provided here.
> General comments from mayors about the need to communicate to the public that Skytrain technology is not proprietary/owned by SNC Lavalin.
> Surrey: Fully supports the Skytrain all the way to UBC.
> Kennedy: Yes Vote would trigger $3 million will go towards a study? Cross: Yes. No vote we would have B-Line for decades? Cross: Yes. We already at the stage where we need it.
> Question asked about who has been the engineering contractor in the past, which Geoff Cross answered as only SNC Lavalin, Bombardier and then commented that the Canada Line is different (Hyundai Rotem). Kevin Desmond then stepped in to comment that the project is massive and there are many many companies that will be involved and there is a lot of interest worldwide. It will be a consortium of companies. There will be a public bid and it will be competitive with many companies worldwide not just SNC Lavalin.
> A number of mayors sympathized with the problems on the North Shore and questioned the need of it and the benefit to the region
> Mike Little is supportive but not supportive. He wants the solution for Broadway to be as cheap as possible so that other regions get their share.
> Rob Vagramov was not supportive.

The motion was called, and all but two supported the motion!
Skytrain is coming to UBC!


5.1-5.2 Ride Hailing Discussions
> Linda Buchanan bringing forward potential impacts to Transit Ridership. Same regulations should apply to taxi as ride sharing.
> Mike Little: Taxi doesn't meet our needs because of regulation and we need deregulation. We need to stop artificially inflating prices.
> Kevin Desmond: If too much deregulation to prices then people will start taking short trips and greatly increase congestion. Minimum prices are generally based to stop people leaving transit for ride hailing.
> Doug McCallum: Does not support ride hailing because the current government has continually denied Surrey increased number of taxi licenses. He believes that Surrey needs more taxi services. He generally supports Translink but will be voting against the motion.
> Jonathon Cote: We need to move forward and get our head out of the sand.
> Motion carried. McCallum was the the only dissenting vote
     
     
  #19664  
Old Posted Feb 15, 2019, 10:05 PM
Migrant_Coconut's Avatar
Migrant_Coconut Migrant_Coconut is offline
Registered User
 
Join Date: Oct 2015
Location: Kitsilano/Fairview
Posts: 10,151
Quote:
Originally Posted by Millennium2002 View Post
I'm not sure how I feel about those improvements. As VancouverOfTheFuture pointed out, the westbound B-Line stop is oddly placed and forces buses to cross a few lanes. And besides that, West 41st Avenue has so little room in that area that adding turn lanes might not really alleviate all the congestion.

Here are my suggestions to the CoV proposal:

-snip-

Basically the idea is to shift the left turn movement from eastbound W 41st Ave to northbound West Blvd to W 42nd Ave, as well as a dedicated pullout bay for the westbound B-Line stop. It costs somewhat more, but I think it'll be worth the trouble for this problem spot.
Cities Skylines, right? Nice work.

That said (if I'm reading that correctly), the westbound buses are going to have a hell of a time getting back onto 41st... and that's assuming the City even allows the Greenway to be split up like that.
     
     
  #19665  
Old Posted Feb 15, 2019, 10:06 PM
Migrant_Coconut's Avatar
Migrant_Coconut Migrant_Coconut is offline
Registered User
 
Join Date: Oct 2015
Location: Kitsilano/Fairview
Posts: 10,151
Quote:
Originally Posted by waves View Post
4.2 Rail to UBC
> Mike Little wants to know the vertical alignment cost differences before approval, cut & cover, bored tunnel, elevated, etc.
> Geoff Cross: Fastest start to construction is 2025.
> Jonathon Cote and others: Negotiations with the community over "enhancements" that they want beyond the base case (maybe Vancouver pays for the extra cost for bored tunnel vs cut & cover?). Coquitlam didn't pay the extra amount to have the last part of the Evergreen Line underground even though it wanted it. The Coquitlam mayor's emphasis was on the same fairness being provided here.
> General comments from mayors about the need to communicate to the public that Skytrain technology is not proprietary/owned by SNC Lavalin.
> Surrey: Fully supports the Skytrain all the way to UBC.
> Kennedy: Yes Vote would trigger $3 million will go towards a study? Cross: Yes. No vote we would have B-Line for decades? Cross: Yes. We already at the stage where we need it.
> Question asked about who has been the engineering contractor in the past, which Geoff Cross answered as only SNC Lavalin, Bombardier and then commented that the Canada Line is different (Hyundai Rotem). Kevin Desmond then stepped in to comment that the project is massive and there are many many companies that will be involved and there is a lot of interest worldwide. It will be a consortium of companies. There will be a public bid and it will be competitive with many companies worldwide not just SNC Lavalin.
> A number of mayors sympathized with the problems on the North Shore and questioned the need of it and the benefit to the region
> Mike Little is supportive but not supportive. He wants the solution for Broadway to be as cheap as possible so that other regions get their share.
> Rob Vagramov was not supportive.

The motion was called, and all but two supported the motion!
Skytrain is coming to UBC!
About muthaphuckin' time.
     
     
  #19666  
Old Posted Feb 15, 2019, 10:14 PM
SFUVancouver's Avatar
SFUVancouver SFUVancouver is offline
Registered User
 
Join Date: Dec 2006
Location: Hamilton
Posts: 6,695
This is very, very good news for Metro Vancouver. What a relief to finally have the question of if and when SkyTrain would extend to UBC be resolved. 2030 still sounds like a long way away, and we lost a decade already from what was promised in the 2008 Provincial Transit Plan, but at least it is finally on the books. Not to make light of the cost, but the "missing billion" between the $2.83B of approved funding for Phase 1 and the estimated $3.8B needed for the full VCC-Clark to UBC line is a surmountable obstacle. Breaking it into two chunks is still madness but admittedly pragmatic from a funding perspective.
__________________
VANCOUVER | Beautiful, Multicultural | Canada's Pacific Metropolis
     
     
  #19667  
Old Posted Feb 15, 2019, 10:16 PM
officedweller officedweller is online now
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,712
Another solution for the westbound on 41st B-Line problem of the bus getting to the middle lane is to move the bus stop to the intersection (the tail of the bus will block the East Blvd right turn lane while stopped) and implement a "bus only" traffic signal (vertical white bar) at West Boulevard so the bus can move from the curb lane to the middle lane while other traffic is stopped.
There's been one in operation at eastbound Marine Drive at Taylor Way for years, allowing the bus to cut diagonally across the intersection from the curb lane to the left lane to North Vancouver.
     
     
  #19668  
Old Posted Feb 15, 2019, 11:19 PM
CanSpice's Avatar
CanSpice CanSpice is offline
Registered User
 
Join Date: Dec 2014
Location: New Westminster, BC
Posts: 2,718
Quote:
Originally Posted by SFUVancouver View Post
This is very, very good news for Metro Vancouver. What a relief to finally have the question of if and when SkyTrain would extend to UBC be resolved. 2030 still sounds like a long way away, and we lost a decade already from what was promised in the 2008 Provincial Transit Plan, but at least it is finally on the books. Not to make light of the cost, but the "missing billion" between the $2.83B of approved funding for Phase 1 and the estimated $3.8B needed for the full VCC-Clark to UBC line is a surmountable obstacle. Breaking it into two chunks is still madness but admittedly pragmatic from a funding perspective.
The extension from Arbutus to UBC is estimated at between $3.3B and $3.8B (in 2018 dollars), so the full VCC-Clark to UBC SkyTrain would cost between $6.13B and $6.63B. TransLink also made an estimate assuming the Arbutus-UBC extension starts procurement in 2025 of between $4.1B and $4.8B in 2025 dollars.
     
     
  #19669  
Old Posted Feb 16, 2019, 12:25 AM
waves's Avatar
waves waves is offline
waves
 
Join Date: Jun 2015
Location: North Vancouver
Posts: 382
Quote:
Originally Posted by CanSpice View Post
The extension from Arbutus to UBC is estimated at between $3.3B and $3.8B (in 2018 dollars), so the full VCC-Clark to UBC SkyTrain would cost between $6.13B and $6.63B. TransLink also made an estimate assuming the Arbutus-UBC extension starts procurement in 2025 of between $4.1B and $4.8B in 2025 dollars.
This was actually a question asked to Geoff Cross by Mike Little. Geoff confirmed that the total overall VCC to UBC costs were a minimum $7 billion.
     
     
  #19670  
Old Posted Feb 16, 2019, 12:28 AM
CanSpice's Avatar
CanSpice CanSpice is offline
Registered User
 
Join Date: Dec 2014
Location: New Westminster, BC
Posts: 2,718
Quote:
Originally Posted by waves View Post
This was actually a question asked to Geoff Cross by Mike Little. Geoff confirmed that the total overall VCC to UBC costs were a minimum $7 billion.
Yep, and it was in the report to the Mayors Council too, which is where I got the numbers from.
     
     
  #19671  
Old Posted Feb 16, 2019, 12:47 AM
GeeCee's Avatar
GeeCee GeeCee is offline
Registered User
 
Join Date: Jan 2009
Location: Port Coquitlam, BC
Posts: 2,816
     
     
  #19672  
Old Posted Feb 16, 2019, 8:37 PM
fredinno's Avatar
fredinno fredinno is offline
Registered User
 
Join Date: Jan 2012
Posts: 2,317
Quote:
Originally Posted by officedweller View Post
Another solution for the westbound on 41st B-Line problem of the bus getting to the middle lane is to move the bus stop to the intersection (the tail of the bus will block the East Blvd right turn lane while stopped) and implement a "bus only" traffic signal (vertical white bar) at West Boulevard so the bus can move from the curb lane to the middle lane while other traffic is stopped.
There's been one in operation at eastbound Marine Drive at Taylor Way for years, allowing the bus to cut diagonally across the intersection from the curb lane to the left lane to North Vancouver.
Then you have the problem of all median bus stops- it's inconvenient since everyone has to cross the street to get to the bus stop.
     
     
  #19673  
Old Posted Feb 16, 2019, 10:41 PM
Aroundtheworld Aroundtheworld is offline
Registered User
 
Join Date: Oct 2013
Posts: 623
Quote:
Originally Posted by fredinno View Post
Then you have the problem of all median bus stops- it's inconvenient since everyone has to cross the street to get to the bus stop.
Yes, but everybody is also only crossing half the distance.

This got me thinking that what might be good for the B-Lines is gradually upgrading them to BRT level. The good thing about BRT instead of LRT is you could implement it gradually. You could start adding median stations and dedicated corridors in areas where it speeds up efficiently and it is easy to implement.

The stations would have payment before boarding and could accommodate local services as well by being long enough to accommodate both buses at the same time. It would provide a level of service similar to LRT at a fraction of the cost.
     
     
  #19674  
Old Posted Feb 16, 2019, 11:42 PM
waves's Avatar
waves waves is offline
waves
 
Join Date: Jun 2015
Location: North Vancouver
Posts: 382
Hey All, does anyone have information on the station depths or an elevation profile view of the Canada Line? I am curious as to the maximum grades present on the line currently. I have old pre-bid preliminary drawings (that have been posted on the forum before) but I haven't been able to find anything definitive in terms of what was actually built. Some of the stations I can find the depths on Wikipedia, but its very very hit and miss, as in Yaletown (17) and Granville (25) are listed but no others are.

Last edited by waves; Feb 17, 2019 at 12:05 AM.
     
     
  #19675  
Old Posted Feb 17, 2019, 9:17 AM
fredinno's Avatar
fredinno fredinno is offline
Registered User
 
Join Date: Jan 2012
Posts: 2,317
Quote:
Originally Posted by waves View Post
Hey All, does anyone have information on the station depths or an elevation profile view of the Canada Line? I am curious as to the maximum grades present on the line currently. I have old pre-bid preliminary drawings (that have been posted on the forum before) but I haven't been able to find anything definitive in terms of what was actually built. Some of the stations I can find the depths on Wikipedia, but its very very hit and miss, as in Yaletown (17) and Granville (25) are listed but no others are.
You can use http://www.heywhatsthat.com/profiler.html for an elevation profile.
     
     
  #19676  
Old Posted Feb 17, 2019, 10:33 AM
waves's Avatar
waves waves is offline
waves
 
Join Date: Jun 2015
Location: North Vancouver
Posts: 382
Quote:
Originally Posted by fredinno View Post
You can use http://www.heywhatsthat.com/profiler.html for an elevation profile.
I need an elevation profile of the track itself, not the surface elevation.
     
     
  #19677  
Old Posted Feb 17, 2019, 11:34 AM
SpongeG's Avatar
SpongeG SpongeG is offline
Registered User
 
Join Date: Jun 2006
Location: Coquitlam
Posts: 40,073
did it get discussed here about people being trapped on the train for over 3 hours last week in richmond?

what exactly caused it?
__________________
belowitall
     
     
  #19678  
Old Posted Feb 17, 2019, 6:17 PM
MIPS's Avatar
MIPS MIPS is offline
SkyTrain Nut
 
Join Date: Mar 2013
Location: Kamloops
Posts: 2,091
Quote:
Originally Posted by SpongeG View Post
did it get discussed here about people being trapped on the train for over 3 hours last week in richmond?

what exactly caused it?
The usual problems. Upwards-facing power rails can't handle the ice and snow and creates dead spots if not cleared quickly enough.
     
     
  #19679  
Old Posted Feb 18, 2019, 2:49 AM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,705
Sorry wrong thread.
     
     
  #19680  
Old Posted Feb 19, 2019, 1:31 AM
Xerx Xerx is offline
Registered User
 
Join Date: Apr 2009
Posts: 198
Quote:
Victoria transit to move to smartphone fare purchasing
Commuters in Victoria, B.C., might soon be able to use their smartphones to pay for bus fare.

Right now, the city's bus system operates on cash or paper tickets, but a $21-million upgrade to the fare system could change that.

Christy Ridout, vice-president of business development for B.C. Transit, said the idea is for transit users to buy their fares on a mobile phone application, then scan their phone when entering the bus — similar to checking in at an airport.

"The payment industry has come a long way in the last few years and I think we're really able to take advantage of some of the innovation that has occurred," said Ridout.

If the smart phone platform is successful, Ridout said the ultimate goal will be moving to fares being paid via debit or credit card, similar to Vancouver's TransLink system.

In Metro Vancouver, TransLink offers reloadable Compass cards. Ridout said Victoria will not be exploring a Compass card option because the infrastructure for such a system is costly.

She said Compass cards require expensive vending machines to load the cards, and a comprehensive database on the back end to avoid fraud.

Ridout noted some riders won't have a smartphone, and she doesn't want this new system to be seen as a barrier to customers. To that end, she said buses will not remove their cash boxes, and cash will always be acceptable when buying fare.

Ridout said B.C. Transit is looking for a company to partner with in the endeavour, and estimates the new technology will come online in late 2019 or early 2020.
CBC News

Looks like we'll never have an integrated provincial smartcard/ticket for transit.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 6:27 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.