  #9461  
Old Posted Feb 15, 2019, 12:29 PM
TransitZilla TransitZilla is offline
Registered User
 
Join Date: Dec 2006
Posts: 2,800
Quote:
Originally Posted by lrt's friend View Post
CBC late night news confirmed that only 14 trains are fully operational.
I think that wording is misleading. They are not yet certified but that doesn't mean they don't work; just that there are issues to resolve. How long it will take to resolve those issues is obviously a big question.

Quote:

There was some skepticism on how much testing has actually occurred during extreme weather.
That one seems bizarre to me... they have been running trains all winter and all of last winter as well.
     
     
  #9462  
Old Posted Feb 15, 2019, 12:51 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is offline
Busy Beaver
 
Join Date: Nov 2005
Location: Ottawa
Posts: 4,688
I didn't see them testing on Wednesday after the big storm and the tracks seemed covered in snow at the western end.
     
     
  #9463  
Old Posted Feb 15, 2019, 1:02 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by 11a2b3 View Post
Looks neat.
For all the griping here about Lyon's asethetics, it's still easily among the most impressive subway stations in North America, although i have to admit the competition isn't exactly fierce. The grand majority of subway stations in North America have all the charm of a public men's washroom (and smell about the same too)
     
     
  #9464  
Old Posted Feb 15, 2019, 3:22 PM
jcphoenix jcphoenix is offline
Registered User
 
Join Date: Oct 2011
Posts: 139
Quote:
Originally Posted by kmcamp View Post
For all the griping here about Lyon's asethetics, it's still easily among the most impressive subway stations in North America, although i have to admit the competition isn't exactly fierce. The grand majority of subway stations in North America have all the charm of a public men's washroom (and smell about the same too)
Yeah count me also in the camp that thinks Lyon looks completely fine. It's certainly nicer looking than most of the Toronto stations or Montreal stations so like
     
     
  #9465  
Old Posted Feb 15, 2019, 3:57 PM
CityTech CityTech is offline
Registered User
 
Join Date: May 2016
Location: Ottawa
Posts: 2,798
Lyon looks very 1960s-1970s ish and I personally detest architecture from that era, but putting aside my personal feelings and looking at it objectively its nice I guess. It matches the aesthetic of the area, so that's something.
     
     
  #9466  
Old Posted Feb 15, 2019, 4:12 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,971
Quote:
Originally Posted by lrt's friend View Post
CBC late night news confirmed that only 14 trains are fully operational. The remaining 20 have varying deficiencies including 2 trains that are in such poor shape that it is considered expedient to bring in two upgraded replacements. Effectively, it sounds like 2 trains are next to scrap or will take a long time to bring to operational condition.

There was some skepticism on how much testing has actually occurred during extreme weather.

Although an official update about the March 31st deadline will take place as part of a March 6th meeting, it was reported that we will probably know within a week.
We'll get an idea of the status of the trains by March 6th. Even if they get 34 trains ready to go, the 12 days of continuous testing could make or break the March 31st deadline.
     
     
  #9467  
Old Posted Feb 15, 2019, 4:23 PM
swimmer_spe swimmer_spe is offline
BANNED
 
Join Date: Apr 2014
Posts: 10,743
Quote:
Originally Posted by kmcamp View Post
I'd take the media reports with a grain of salt. They are on an attack angle right now, so they are being aggressively negative. For example the line that CBC is going with is "no proven track record". Incidentally the only two trains with a track record in our climate (Minneapolis specifically, which is even harsher than ours)are Bombardier's flexity and Siemens. I doubt things would have ended up much better with either. We'd be reading about Bombardier's general incompetence with various GTA projects or how were using a train that cost us tens of millions of dollars in cancellation fees when we aborted the 2006 plan.

The two "junk" trains are the ones they lost the parts for, and 10 are close to being certified, CBC is being overly dramatic.

That being said, obviously we have a problem since we're supposed to have 34, and I'm not letting Alstom of the hook.
How do you loose parts? How can the shipper be let off with an "oh well" and then not replace the parts?
     
     
  #9468  
Old Posted Feb 15, 2019, 4:32 PM
zzptichka zzptichka is offline
Registered User
 
Join Date: Dec 2015
Location: Outaouias
Posts: 2,381
How many trains we need to get going? For 4-minute interval there needs to be 15 on the rails at a time, so assuming they'll be running coupled trains that'd be 30?
I guess if some are not ready they'll be running a few single ones.
     
     
  #9469  
Old Posted Feb 15, 2019, 4:50 PM
OCCheetos OCCheetos is offline
Registered User
 
Join Date: Aug 2017
Posts: 2,111
Quote:
Originally Posted by zzptichka View Post
How many trains we need to get going? For 4-minute interval there needs to be 15 on the rails at a time, so assuming they'll be running coupled trains that'd be 30?
I guess if some are not ready they'll be running a few single ones.
The city won't accept a handover unless they have 34 operational trains.
They need the hot spare (two trains) and the maintenance spare (two more trains) to ensure operations.
     
     
  #9470  
Old Posted Feb 15, 2019, 6:56 PM
OTSkyline OTSkyline is offline
Registered User
 
Join Date: Jun 2012
Posts: 2,825
I did read in another article that some of the "unfinished" trains were only missing minor things like a handlebar or signage (which should be relatively easy and quick fixes).

Only question is how may of the incomplete trains are "near completion" with a few final touches and how many are half-complete and weeks/months away from being ready...
     
     
  #9471  
Old Posted Feb 15, 2019, 7:31 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by swimmer_spe View Post
How do you loose parts? How can the shipper be let off with an "oh well" and then not replace the parts?
Rtg lost the parts. That's why trains 35 and 36 from Stage 2 were sped up, to replace 33 and 34 until they can become operational. It all works out the same in the end
     
     
  #9472  
Old Posted Feb 15, 2019, 7:53 PM
J.OT13's Avatar
J.OT13 J.OT13 is offline
Moderator
 
Join Date: Mar 2012
Location: Ottawa
Posts: 28,971
So those aren't two extra trains. They are Stage 2 trains?

Still confused. Why not just get replacements for the parts instead of two entire trains. Is it not easier to add a few parts to a couple nearly completed vehicles instead of building new ones from scratch? We're still left with two non-functioning trains wasting space in the yard.
     
     
  #9473  
Old Posted Feb 15, 2019, 7:59 PM
kmcamp kmcamp is offline
Registered User
 
Join Date: Sep 2016
Posts: 1,401
Quote:
Originally Posted by J.OT13 View Post
So those aren't two extra trains. They are Stage 2 trains?

Still confused. Why not just get replacements for the parts instead of two entire trains. Is it not easier to add a few parts to a couple nearly completed vehicles instead of building new ones from scratch? We're still left with two non-functioning trains wasting space in the yard.
It's a new batch from the factory down in New York, maybe there's some sort of minor technical difference between the two orders, or they didn't want to cannibalize parts from the new order while they try to get/find/replace/whatever the original parts.

The order for 38 additional trains had already been given back in 2017.
     
     
  #9474  
Old Posted Feb 16, 2019, 1:47 AM
pattherat pattherat is offline
Registered User
 
Join Date: Nov 2018
Posts: 197
Quote:
Originally Posted by kmcamp View Post
I'd take the media reports with a grain of salt. They are on an attack angle right now, so they are being aggressively negative. For example the line that CBC is going with is "no proven track record". Incidentally the only two trains with a track record in our climate (Minneapolis specifically, which is even harsher than ours)are Bombardier's flexity and Siemens. I doubt things would have ended up much better with either. We'd be reading about Bombardier's general incompetence with various GTA projects or how were using a train that cost us tens of millions of dollars in cancellation fees when we aborted the 2006 plan.

The two "junk" trains are the ones they lost the parts for, and 10 are close to being certified, CBC is being overly dramatic.

That being said, obviously we have a problem since we're supposed to have 34, and I'm not letting Alstom of the hook.
This guy gets it.

Just look at the history of Joanne Chiannello’s articles overall. Almost always an angle of negativity and attack, no matter if the subject is LRT or anything else.
     
     
  #9475  
Old Posted Feb 16, 2019, 3:46 AM
Admiral Nelson Admiral Nelson is offline
Registered User
 
Join Date: Jun 2009
Posts: 519
Quote:
Originally Posted by pattherat View Post
This guy gets it.

Just look at the history of Joanne Chiannello’s articles overall. Almost always an angle of negativity and attack, no matter if the subject is LRT or anything else.
I'm glad she's there, so at least someone will try to cut through the smoke blowing and obfuscation at city hall. For years city officials have cited the RTG contract as reasons for not disclosing problems to the public and have stonewalled attempts to get information publicized. And you realize that it was only last week, approaching a third blown deadline, that city officials were willing to haul RTG representatives in front of council to answer directly to elected officials in a public forum?

Separately I also appreciate that she called out the mayor and his allies for their repeated media line about only delivering a safe system, which waves away legitimate questions about the project delivery and insinuates that trying to hold RTG and the City to account for continuing delays and mounting costs is in some way irresponsible.
     
     
  #9476  
Old Posted Feb 16, 2019, 4:28 AM
pattherat pattherat is offline
Registered User
 
Join Date: Nov 2018
Posts: 197
Quote:
Originally Posted by Admiral Nelson View Post
I'm glad she's there, so at least someone will try to cut through the smoke blowing and obfuscation at city hall. For years city officials have cited the RTG contract as reasons for not disclosing problems to the public and have stonewalled attempts to get information publicized. And you realize that it was only last week, approaching a third blown deadline, that city officials were willing to haul RTG representatives in front of council to answer directly to elected officials in a public forum?

Separately I also appreciate that she called out the mayor and his allies for their repeated media line about only delivering a safe system, which waves away legitimate questions about the project delivery and insinuates that trying to hold RTG and the City to account for continuing delays and mounting costs is in some way irresponsible.
I don’t. She blows things out of proportion and seems to wantingly mislead with sensationalist headlines. She fans the flames of people looking for corruption and politicians ‘hiding’ things.

The reality is the public rarely wants to find the full picture or reasoning behind decisions/delays/etc...and are more than happy to latch onto the first thing that affirms their already held view. She exploits this for clicks.

Of course, we are both free to our opinions of the ‘service’ she provides.
     
     
  #9477  
Old Posted Feb 16, 2019, 1:38 PM
McC's Avatar
McC McC is offline
Registered User
 
Join Date: Apr 2010
Posts: 3,057
Saw a steel-wheeled maintenance vehicle of some sort with a snow blower clearing the tracks at Bayview yesterday evening. Hadn’t seen a train on the western track all week, so it seems likely that they weren’t using the tried and true method to keep snow from accumulating on the tracks, nor testing heavily through the storm and aftermath.

Also have noticed the usual copious amounts of salt being used in front of the Stations, which unless something changes after opening day, will make a right mess of everything.
     
     
  #9478  
Old Posted Feb 16, 2019, 2:14 PM
OCCheetos OCCheetos is offline
Registered User
 
Join Date: Aug 2017
Posts: 2,111
Quote:
Originally Posted by McC View Post
Saw a steel-wheeled maintenance vehicle of some sort with a snow blower clearing the tracks at Bayview yesterday evening. Hadn’t seen a train on the western track all week, so it seems likely that they weren’t using the tried and true method to keep snow from accumulating on the tracks, nor testing heavily through the storm and aftermath.

Also have noticed the usual copious amounts of salt being used in front of the Stations, which unless something changes after opening day, will make a right mess of everything.
That's not necessarily true. Running regular trains over a track during heavy snowfall can keep enough snow off to keep things running smoothly, but they'll always send proper snow clearing vehicles out afterwards to do a proper job.

On the Trillium Line the tracks are properly plowed a few days after heavy snowfalls.
     
     
  #9479  
Old Posted Feb 16, 2019, 3:31 PM
Kitchissippi's Avatar
Kitchissippi Kitchissippi is offline
Busy Beaver
 
Join Date: Nov 2005
Location: Ottawa
Posts: 4,688
Quote:
Originally Posted by OCCheetos View Post
That's not necessarily true. Running regular trains over a track during heavy snowfall can keep enough snow off to keep things running smoothly, but they'll always send proper snow clearing vehicles out afterwards to do a proper job.
That's not the point. What happened to the rationale that one of the "advantages" of the delay is that it would give RTG a chance to test the trains in the worst of weather? The recent storm was the best example of the heavy snowfall Ottawa can get in a short period, and that opportunity might not come around again this season (at least I'm hoping it doesn't )
     
     
  #9480  
Old Posted Feb 16, 2019, 3:41 PM
OCCheetos OCCheetos is offline
Registered User
 
Join Date: Aug 2017
Posts: 2,111
Quote:
Originally Posted by Kitchissippi View Post
That's not the point. What happened to the rationale that one of the "advantages" of the delay is that it would give RTG a chance to test the trains in the worst of weather? The recent storm was the best example of the heavy snowfall Ottawa can get in a short period, and that opportunity might not come around again this season (at least I'm hoping it doesn't )
I'm just saying that just because the snow blower vehicle is out doesn't mean that no trains were tested. I saw two near Hurdman on Thursday afternoon for instance.

Even if vehicles had been testing in or after the snow, the snowblower would have been sent out anyway.
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Ontario > Ottawa-Gatineau > Transportation
Forum Jump



Forum Jump


All times are GMT. The time now is 9:26 AM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.