Quote:
Originally Posted by Dengler Avenue
At this point I’m just hoping that 417 extension to Renfrew will proceed even if the government changes hand. Just like anyone else, I don’t hold my breath until shovels are on the ground.
I hope that explains why I’ve been quiet in this thread lately. If anything, I’ve diverted my attention to Route 185 twinning in Québec lately.
|
Prelim design is already done to Bruce Street.
Route Planning for twinning is also complete to Petawawa
You are looking at least 3 years out until they start major construction work on the highway.
I'm currently designing culverts along HWY 17, we are making sure we have sufficient length for twinning, in my particular area there are some compressible soils so we have to pre-load the area so we get maximum settlement for when the twinning comes though.