January Mayor's Council agena

Of interest:

RRT capital cost estimate is now $3.3 to $3.8B
Mod. LRT1 cost estimate $1.7 to $2.0B, will be over capacity by 2050
Combo1 cost estimate is $2.8 to $3.2B, will be over capacity by 2045

The only acceptable solution for LRT is to build a second LRT line on 41st, and the capital cost ranges from $3.7 to $7.1B (depending on the option), and will be at capacity by 2070.

I think from this presentation, the LRT is pretty much out. It's just a matter of whether to build the SkyTrain, or not building anything at all.
     
     
  #19542  
Old Posted Jan 22, 2019, 12:41 AM
WarrenC12's Avatar
WarrenC12 WarrenC12 is offline
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,652
Quote:
Originally Posted by nname View Post
January Mayor's Council agena

Of interest:

RRT capital cost estimate is now $3.3 to $3.8B
Mod. LRT1 cost estimate $1.7 to $2.0B, will be over capacity by 2050
Combo1 cost estimate is $2.8 to $3.2B, will be over capacity by 2045

The only acceptable solution for LRT is to build a second LRT line on 41st, and the capital cost ranges from $3.7 to $7.1B (depending on the option), and will be at capacity by 2070.

I think from this presentation, the LRT is pretty much out. It's just a matter of whether to build the SkyTrain, or not building anything at all.
Good grief that's a lot of money just for the extension, in what appears to be straightforward geography.

No way they should waste time with LRT though. Bus, then Skytrain. That's it.
     
     
  #19543  
Old Posted Jan 22, 2019, 2:14 AM
WestCoastEcho WestCoastEcho is offline
Registered User
 
Join Date: Jul 2018
Posts: 395
Quote:
Originally Posted by ilikeredheads View Post
Obvious difference in loading gauge aside, you want Bombardier to build a special set of trains that uses BOTH LIM rail and conventional electric motor. lol wut?
Should be noted that Bombardier is building a variant of the INNOVIA Metro 300 (the same car type as the Mark III SkyTrain's) with regular rotary motors for the Riyadh Metro.
     
     
  #19544  
Old Posted Jan 22, 2019, 4:05 AM
ilikeredheads ilikeredheads is offline
Registered User
 
Join Date: Sep 2016
Location: west coast
Posts: 651
Quote:
Originally Posted by WestCoastEcho View Post
Should be noted that Bombardier is building a variant of the INNOVIA Metro 300 (the same car type as the Mark III SkyTrain's) with regular rotary motors for the Riyadh Metro.
that's normal because trains are never purchased just off-the-shelf but are always specifically customized to fit the system's needs. Both Innovia and Movia series can be configured in various ways.

What he was suggesting was to order trains that houses BOTH types of propulsion systems despite the fact that both Canada Line and Expo/Millennium Line are incompatible with each other. And doing so would require tremendous amount of money and significant periods of service disruptions. You are essentially rebuilding the entire line again. It's beyond absurd.
     
     
  #19545  
Old Posted Jan 22, 2019, 4:58 AM
dpogue dpogue is offline
Registered User
 
Join Date: Aug 2013
Posts: 767
Quote:
Originally Posted by fredinno View Post
Doesn't look like it would provide a meaningful increase in capacity.
This wasn't so much a prototype of the new vehicle itself as it was a test case for whether a longer/wider train could made it around the curves on the guideway.

Before that, there was also TV06:

Posted on Instagram by translinkbc

Quote:
TV06 was a prototype MK II vehicle, fabricated in Kingston in the early 1990’s by taking 2 MK I test vehicles and Siameseing them together to make one 16.7m car from the two 12.7m MK I chassis. One of these MK I’s was originally a PreBuild car from the 1983 Main St. summer demo.

TV06 was intended to prove out a new floating frame steerable truck and also test a new propulsion system from General Dynamics, using central cooling ducts for the linear motors. It was tested for 4 months in Vancouver, after Revenue hours, then returned to Kingston where it is still occasionally used at the Test Track there
     
     
  #19546  
Old Posted Jan 22, 2019, 6:02 AM
MIPS's Avatar
MIPS MIPS is offline
SkyTrain Nut
 
Join Date: Mar 2013
Location: Kamloops
Posts: 2,093
There's another bus heading your way.

I was driving east out of Kamloops and a very filthy TransLink bus was driving west on highway 1. I wonder what someone gets paid to drive a bus like that from the factory to the destination city hundreds of kilometers away.
     
     
  #19547  
Old Posted Jan 22, 2019, 8:24 AM
fredinno's Avatar
fredinno fredinno is offline
Registered User
 
Join Date: Jan 2012
Posts: 2,317
Quote:
Originally Posted by WarrenC12 View Post
Good grief that's a lot of money just for the extension, in what appears to be straightforward geography.

No way they should waste time with LRT though. Bus, then Skytrain. That's it.
It's for Broadway to UBC, note, since UBC proposed to build have it extend all the way.

It's definitely because it's bored the entire way, plus the traditional cost margin. If NIMBYs allowed for cut-and-cover, it would be more like ~$1.5-2B probably.

Quote:
Originally Posted by dpogue View Post
This wasn't so much a prototype of the new vehicle itself as it was a test case for whether a longer/wider train could made it around the curves on the guideway.

Before that, there was also TV06:

Posted on Instagram by translinkbc
Mostly longer, not wider.
     
     
  #19548  
Old Posted Jan 22, 2019, 5:27 PM
madog222 madog222 is online now
Moderator
 
Join Date: Jan 2014
Posts: 4,189
Render of the upgrades to 22nd Street Bus Exchange. I guess that dark line at the back is the electric bus charger.
It doesn’t like like there will be a bay for 60ft busses, I remember some talk a few years ago about using them on the 410 but with the Metrotown-Richmond B-line coming soon the 410 should seem reduced usage.

     
     
  #19549  
Old Posted Jan 22, 2019, 6:24 PM
WarrenC12's Avatar
WarrenC12 WarrenC12 is offline
Registered User
 
Join Date: May 2007
Location: East OV!
Posts: 24,652
What is the status of the Electric bus rollout? We had 2 for testing right?
     
     
  #19550  
Old Posted Jan 23, 2019, 1:56 AM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,725
That 22nd St. Bus Exchange needs more open space behind the bus shelters for passenger circulation (walking to the shelter).
I see a sidewalk a level up, but that's not likely how people will walk to the shelters.
     
     
  #19551  
Old Posted Jan 23, 2019, 3:06 AM
sweetnhappy sweetnhappy is offline
Registered User
 
Join Date: Feb 2016
Location: Central Alberta, formerly BC Upper Fraser Valley
Posts: 95
Quote:
Originally Posted by officedweller View Post
That 22nd St. Bus Exchange needs more open space behind the bus shelters for passenger circulation (walking to the shelter).
I see a sidewalk a level up, but that's not likely how people will walk to the shelters.
That's definitely true. I don't see all that much of an improvement over the existing exchange with regard to space for circulation. The lines for some of the routes get really long (from what I remember, been awhile). I wonder how much it would add to the cost for them to carve out additional space - it's not like there's anything besides shrubs and maybe some light posts.
     
     
  #19552  
Old Posted Jan 23, 2019, 3:35 AM
CanSpice's Avatar
CanSpice CanSpice is offline
Registered User
 
Join Date: Dec 2014
Location: New Westminster, BC
Posts: 2,722
Quote:
Originally Posted by sweetnhappy View Post
That's definitely true. I don't see all that much of an improvement over the existing exchange with regard to space for circulation. The lines for some of the routes get really long (from what I remember, been awhile). I wonder how much it would add to the cost for them to carve out additional space - it's not like there's anything besides shrubs and maybe some light posts.
They're doing some landscaping work and putting in shelters that don't have side walls on them, which will open up the waiting area a bit.
     
     
  #19553  
Old Posted Jan 23, 2019, 11:26 PM
cganuelas1995 cganuelas1995 is offline
Registered User
 
Join Date: Jan 2017
Posts: 1,659
Quote:
Originally Posted by nname View Post
January Mayor's Council agena

Of interest:

RRT capital cost estimate is now $3.3 to $3.8B
Mod. LRT1 cost estimate $1.7 to $2.0B, will be over capacity by 2050
Combo1 cost estimate is $2.8 to $3.2B, will be over capacity by 2045

The only acceptable solution for LRT is to build a second LRT line on 41st, and the capital cost ranges from $3.7 to $7.1B (depending on the option), and will be at capacity by 2070.

I think from this presentation, the LRT is pretty much out. It's just a matter of whether to build the SkyTrain, or not building anything at all.
I think one of the only ways to resolve the capacity issue is to make changes to the way jobs are. A majority of the jobs are the typical 9-5 monday to friday jobs and transit serves that. If they staggered it out more like having a 9-5 shift and an 11-7 shift and a 1-9 shift and a 3-11 shift and so on, then there might be less crowding. But that's my theory.
     
     
  #19554  
Old Posted Jan 24, 2019, 3:48 AM
Mac Write Mac Write is offline
Registered User
 
Join Date: Dec 2008
Posts: 1,423
How many of the new Mark III's are now in revenue service?
     
     
  #19555  
Old Posted Jan 24, 2019, 3:52 AM
jollyburger jollyburger is offline
Registered User
 
Join Date: Dec 2015
Posts: 15,724
Quote:
Originally Posted by Mac Write View Post
How many of the new Mark III's are now in revenue service?
One? 429 is the lead car?

https://buzzer.translink.ca/2018/12/new-mark-iii-trains-undergoing-testing-and-commissioning/
     
     
  #19556  
Old Posted Jan 24, 2019, 4:25 AM
dpogue dpogue is offline
Registered User
 
Join Date: Aug 2013
Posts: 767
Quote:
Originally Posted by Mac Write View Post
How many of the new Mark III's are now in revenue service?
None.
432 is still undergoing testing due to some on-board computer issues.
     
     
  #19557  
Old Posted Jan 24, 2019, 4:35 AM
Mac Write Mac Write is offline
Registered User
 
Join Date: Dec 2008
Posts: 1,423
With the delivery of 203 train cars in 2023-2024, what would be the frequency of train delivery, and are they expansion or replacements as the Mark I's aren't due to be replaced until 2026
     
     
  #19558  
Old Posted Jan 25, 2019, 10:27 AM
fredinno's Avatar
fredinno fredinno is offline
Registered User
 
Join Date: Jan 2012
Posts: 2,317
https://dailyhive.com/vancouver/skytrain-train-speed

Quote:
With a SkyTrain network that spans from UBC to Langley, one mayor in Metro Vancouver wants TransLink to consider getting faster trains for its upcoming new fleet order.
“Looking at how huge this network is going to end up, is there any conversation on the speed of rains? Are we going to have the ability to buy faster rolling stock?” Port Moody mayor Rob Vagramov asked TransLink staff during the Mayors’ Council meeting today.
He seemed to forget all those stations preventing Skytrain from hitting its max speed, and the need to prevent standees from 'drifting' to the back of the train from excess acceleration...
     
     
  #19559  
Old Posted Jan 25, 2019, 1:47 PM
teriyaki teriyaki is offline
Registered User
 
Join Date: Nov 2008
Posts: 601
Quote:
Originally Posted by fredinno View Post
https://dailyhive.com/vancouver/skytrain-train-speed



He seemed to forget all those stations preventing Skytrain from hitting its max speed, and the need to prevent standees from 'drifting' to the back of the train from excess acceleration...
Yea, don't think the trains are the problem here. They're more than capable of hitting some decent speeds.
     
     
  #19560  
Old Posted Jan 30, 2019, 11:27 PM
officedweller officedweller is offline
Registered User
 
Join Date: Jul 2001
Location: Vancouver
Posts: 41,725
Transit fights of the past illuminate the present:
Remember Granville B-Line opposition, and Canada Line battle?

http://www.francesbula.com/uncategorized...-line-opposition-and-canada-line-battle/
     
     
This discussion thread continues

Use the page links to the lower-right to go to the next page for additional posts
 
 
Closed Thread

Go Back   SkyscraperPage Forum > Regional Sections > Canada > Alberta & British Columbia > Vancouver > Transportation & Infrastructure
Forum Jump



Forum Jump


All times are GMT. The time now is 9:17 PM.

     

Powered by vBulletin® Version 3.8.7
Copyright ©2000 - 2026, vBulletin Solutions, Inc.