Quote:
Originally Posted by BrownTown
1. Do you have a source for the SAS being a complex project? I've seen nothing to suggest that.
|
They had zero off-street staging space. By comparison, they were able to knock down low-rise buildings in Los Angeles to help build the station boxes under Wilshire:
https://www.google.com/maps/place/Wilshi...27880c97!8m2!3d34.0618154!4d-118.3086829
Here you can see that construction of the station box directly under Wilshire isn't obstructing even a single lane of traffic:
https://www.google.com/maps/@34.0626949,...23D-USY7asVwt8TtXi-Vw!2e0!7i16384!8i8192
I remember walking the length of Second Ave. above subway construction in 2011 or 2012 and they had 2-3 lanes blocked off for 2 miles straight. The fenced off space was filled with cherry pickers, scaffold, dump trucks -- you name it -- for two miles.
Also, NYC's subway runs very long trains and a ton of them. So the tail tracks for any line extension must be much longer than ordinary systems. I remember when the #7 simply ended at Grand Central, but the extension over to Hudson Yards also includes a tail track, which added substantially to the cost of the 1-station extension. Similarly, Phase 1 of the Second Ave. line included storage for four trains north of the 96th St. station. The future 125th at Lexington station will have 2,000~ feet of non-revenue storage tunnel west of Lexington.