Still no launch date for LRT but signs of progress
Jon Willing, Ottawa Citizen
Updated: November 14, 2018
The city still doesn’t have an exact launch date for the Confederation Line LRT, sticking with the estimate that the $2.1-billion rail line will open sometime in the first three months of 2019.
Transportation general manager John Manconi told the finance and economic development committee on Wednesday that Rideau Transit Group has been achieving milestones and wants to do a full practice plan this month.
However, the city wants to make sure the next date is reliable. RTG has already missed handover dates in May and earlier this month. All the city will say is the 12.5-kilometre LRT line will open in the first quarter of 2019.
Manconi told the committee there are seven key things to track: the RTG practice plan, the signoff by a safety auditor, substantial completion of the project, trial running, revenue service availability (the handover date), revenue service and all of the city’s extra costs.
City treasurer Marian Simulik said her staff are working with Manconi’s staff to identify all of the extra costs incurred by the city during the delay. She said the information should be available within the next two weeks.
Manconi said OC Transpo plans to freeze fare prices until LRT launches. There will be a report during the 2019 budget process, he said.
More to come.